Mapa mental
SAB6#59_Types_Estimations
Conteúdo do mapa
SAB6#59_Types_Estimations
Activities defined and sequenced
Resources are identified (type and quantity)
Resources calendars
OPAs (Past project calendars, scheduling methodology, lessons learned)
EEFs (estimating software / productivity metrics)
Risks / Assumptions / Constraints should be reflected in estimations
One-Point Estimating (button up)
- Submit ONE estimate per activity
- It can lead people into padding their estimates
- It hides important information (risks uncertainties)
- Based on Expert Judgment or Historical Data
- Done by the responsible of the activity
Analogous Estimating (top down)
- Time and Cost
- Based on Expert Judgment or Historical Data
- Project of task level
- Compare data with previous projects (similar tasks)
Parametric estimating
- Based on historical records: Previous projects / Industry requirements, standards, metrics
- 1 Regression analysis: Compares two variables to see if they are related
- 2 Learning curve: Time will be less as efficiency improves (due to repetition)
Three point estimating
- Estimations given are: Optimistic (O), Pessimistic (P) and Most Likely (M)
- Triangular distribution (simple average) = (P+O+M) / 3
- 3 scenarios are equal
- Beta distribution (weighted average) = (P + 4M + O) / 6
- Oriented to Most Likely scenario
- Takes into consideration the benefits of risk management
- Activity standard deviation = (P - O) / 6
Informações
- Descrição
- Mapa Mental sobre SAB6#59_Types_Estimations, criado por Beto L em 13-06-2015.
- Criado por
- Beto L · jun 2015
- Atualizado
- 19 fev 2016
- Visualizações
- 9
- Avaliação
Mais sobre Estimating Activity Resources and Durations