Contract Practice - Interim Valuations & Payment Privisions

tsn_07 Inglês

Conteúdo do mapa

Contract Practice - Interim Valuations & Payment Privisions

  1. Valuations

    • Purpose?
      • To provide recommendation to certifier on value to them 2 issue thier interim cert.
    • the Construction Act Relevant?
  2. Retention

    • JCT Rules
      • rtn = certified amount retained by client
      • % stated in approx - usually 5%
      • Held on wrk executed
        • material off site, measured works, listed items, materials on site etc.
        • NOT:
          • restoration of loss or damage
          • statutory fees/ charges
          • L&E
          • Fluctuations
          • cost of emp. MG defects
          • opening up 4 inspection
      • PC 1/2 is relased
      • Emp. gains interest from retention & can keep it
      • must be placed into a seperate bank account if specified by MC
      • statement of retention must be issued to MC with each interim cert.
      • Balance of retention release on issue of certificate of Making Good
    • why?
      • provide degree of security 4 client
      • intended 2 provide funds should issues become apparent e.g. insolvency of MC
      • provide incentive to ensure defects are MG
    • Weaknesses?
      • cost easily be greater than 2.5% or 1.5%
      • sets precedence 2 accept defects & snagging
      • retention often not treated properly by emp.
    • Retention Bonds
      • What
        • some sectors such as lifts & piling will not accept costs feat. retention but offer bonds in lieu
        • form of on demand bond
        • inc consideration - in lieu of retention
        • remains in force until end of defects period
        • provided by bank/ guarantor
      • ADVANTAGES:
        • assignable
        • latham report = retention bonds are a better option than normal retention
        • can provide same level of security as interim retention
        • does not inflict cashflow problems
        • ease MC could b passed onto tender prices
      • DISADVANTAGES:
        • only advantage over suing if MC goes bust
        • not ready access 2 the money as with interim retention
      • Types
        • its conditional and to enforce you must;
          • prove MC default of obs
          • prove beneficiary has sustained damages
          • prove that damage has been reasonably sustained
      • Terms of bond
        • immediate in insolvency
        • payable if MC not performed obligations
        • expires after completion of rectification of defects

Informações

Descrição
Mapa Mental sobre Contract Practice - Interim Valuations & Payment Privisions, criado por tsn_07 em 14-09-2015.
Criado por
tsn_07
Visualizações
9
Histórico
  • Criado por alison_patey0437 · 14 set 2015
  • Copiado por tsn_07 · 14 set 2015
Avaliação

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?