- Process: Plan Quality Management Process Group: Planning Knowledge Area: Quality Management
Part of the Plan Quality Management process involves defining quality on the project. Many of the seven basic quality tools, listed below, can help clarify stakeholder´s requeriments and expectations when it comes to quality and can also help you plan the product and project work appropriately, clarify acceptance criteria and manage stakeholder expectations. You should also be thinking ahead and planning wich ofthese tools you´ll use in Perform Quality Assurance to determine whether practices and procedures are being followed and in Control Quality to measure quality performance and uncover quality problems.
Cause and effect diagram (Fishbone Diagram, Ishikawa Diagram)
- To understand how a cause and effect diagram work´s, it´s useful to first consider how you would use it in quality control. Is it better to fix a defect or get to the root cause of the defect? Think about this question for a moment. The answer is that you should do both, and a cause and effect diagram can help you.
- Cause and effect diagrams are also called fishbone and Ishikawa diagrams. They are used to figure out what caused a defect. You list all of the categories of the defects that you have identified and then write the possible causes of the defect you are analyzing from each category. Fishbone diagrams help you see all of the possible causes in one place so you can think of how you might prevent the defect in the future. Cause and effect diagrams can also be used to plan how the work of quality should be performed to produce deliverables that meet requeriments. You can star, for example, with a quality requirement and use the diagram to work backward and identify the factors that will influence it and the possible callenges and work necessary to deliver it. This lets you take proactive approach to anticipating problems and callenges. This can also be the basis of planning where control efforts are likely to provide the greatest value: what should be measured, when it should be measured, how it should be measured, etc
- A creative way to look at the causes of a problem or to identify the best way to plan and clarify the definition of quality
- Helps stimulate thinking, organize thoughts, and generate dicussion
- Can be used to explore the factors that will result in a desired future outcome
Flowchart
- One common flowchart model is a SIPOC, wich shows the connections among the supplier, input, process, output, and customer in a process. Flowcharts can be used in may parts of the project management, In the PLAN QUALITY MANAGEMENT process, flowcharts can help determine the cost of quality by mapping the spected monetary value of pursuing paths of conformance and nonconformance to quality. They´re also useful is planning because they can help you deffine and communicate to the team processes that will be used on the project, and show how the processes will be measured for conformance and effectiveness.
- You can also use this tool in Plan Quality Management to "see" a process and find potential quality problems. In the Control Quality process, flowcharts can help you analyze quality problems and develop solutions.
- let you show how processes work visually. You can use a flowchart to show how the tasks inyour project interrelate and what they depend on. They are also good for showing decision-making processes.
- or process map shows how a process or system flows from beginning to end, how the elements interrelate, alternative paths the process can take, and how the process translates inputs into outputs.
Checksheet (Tally Sheet)
- This data collected can in turn be translated into other formats. Checksheets are created in Plan Quality Management and used in Control Quality. Don´t confuse checksheet with the quality checklist, an output of Plan Quality Management also used in Control Quality. The primary purpose of the checksheet is to gather data; the quality checklist, wich might be a list of items to inspect or steps to be performed, is intentented to help verify a required action has taken place or item has been included. So whereas on the checksheet you might document how often a particular defect occurs.
- Is a type of checklist that can be used to keep track of data such as quality problems uncovered during inspections.
Pareto Diagram (Pareto chart)
- In Plan Quality Management, you can identify potential problems that would be documented on Pareto diagram (using, for example, historical information from past projects); in Control Quality, you would measure the data and represent it on the diagram to help analyze the situation and determine where to focus corrective action. in may even be useful to create the structure of the pareto diagram during planning so people know how to represent the data gathered in Control Quality.
- Is a type of bar chart that arranges the results from most frequent to least frequent to help identify which root causes are resulting in the most problems.
- Joseph Juran adapted Vilfredo Pareto´s 80/20 rule to create the 80/20 principle (also known as the pareto Principle) , which states that 80 percent of problems are due to 20 percent of the root causes.
- * Help focues attention on the must critical issues * Prioritize potential "causes" of the problems * Separate the critical few from the uncritical many
Histogram
- Display data in the form of bars or columns. This tool helps identify which problems are worth dealing with.
- A typical histogram presents data in no particular order and without reference to time. As with the Pareto diagram, you can anticipate in Plan Quality Mangement the potential problems, but then plot the results of your measurements in Control Quality on a histogram to determine the most pressing problems.
- Display data in the form of bars or columns. This tool helps identify which problems are worth dealing with.
Control Chart
- Control charts are SET UP in Plan Quality Management as part of the effort to define quality on the project. Ths involves detemining in advance the mean, specification limits, and control limits. Control charts are USED in Control Quality to help determine if the results of a process are within acceptable limits.
- A control chart can also be used to the monitor things like project performance figures, such as cost and schedule variances. Most commonly, however, a control chart helps monitor production and other processes to see if the results are within acceptable limits.
- Upper and lower Control Limits
- Control limits are often shown as two dashed lines on a control chart. These limits are the acceptable range of variation of a process or measurement´s results. Contro limites indicate what is stable versus unstable (out control) in the process. The project manager and relevant stakeholders need to analyse and evaluate what would be appropiate upper and lower control limits for the metrics or standars related to quality for this project. Normally this range this calculated based on +/-3 sigma, or standard desviations, but it can go as high as +/-6 sigma.
- Mean (average)
- The mean is indicated by a line in the middle of the control chart. It shows the middle of the range of acceptable varation. A normal distribution curve represents the acceptabe ranfe of variance around a mean, and is likely to fall within the boundaries of the Control limits.
- Specification limits
- While control limits represent the performing organzation´s standars for quality, specification limits represent the customer´s expectations or contractual requeriments for performance and quality on the project. Specification limits are characteristics or a measured process and are. not inherent. In other words, specification limits are not calculated based on the control chart ; instead, they are inputs from the customer.
- Out of Control
- The process is out off a state of statistical control under either of two circunstances: - A data point falls outside of the upper or lower control limit. - There are nonrandom data points; this may be within the upper and lowwer control limits, such as the rule of seven.
- Rule of Seven
- Is a general rule , or heuristic. It refers to a group or series of nonrandom data points that total seven on one side of the mean. The rule of seven tells you that, although none of this points are outside of the control limits, they are not random an the process is out of control. The project manager should investigate this type of situation and find a cause.
- Assignable Cause / Special Cause Variation
- Signifies that a process is out of control. If there is an assignable cause or special cause variation signifies that a process is out of control. Is there is an assignable cause or special cause variation , it means a data point or series of data points (as discussed with the rule of seven) falls outside the control limits and requeries investigation to determine the cause of the variation. The project manager could use additional tools, such as a cause and effect diagram, to try to uncover the root cause of the variation.
- Control charts are SET UP in Plan Quality Management as part of the effort to define quality on the project. Ths involves detemining in advance the mean, specification limits, and control limits. Control charts are USED in Control Quality to help determine if the results of a process are within acceptable limits.
Scater diagram (Correlation chart)
- Show how two different types of data relate to each other. If you worked with your test team to create a bunch of new tests, you might use a scatter diagram to see if the new test cases had any impact on the number of defects you found. The chart here shows that as more test cases pass, 10 fewer defects are found.
- This diagram tracks two variables to determine their relationship. Imagine our door manufacturer has a project to develop a new painted door product line. Scatter diagrams may be used to determine the relationship of independent variables such as paint quantity , dryer fan speed, and door weight to the dependent variable of drying time. A regression line (or trend line) is calculated to show the correlation of variables, and can then be used fore estimation and forecasting.
- Show how two different types of data relate to each other. If you worked with your test team to create a bunch of new tests, you might use a scatter diagram to see if the new test cases had any impact on the number of defects you found. The chart here shows that as more test cases pass, 10 fewer defects are found.
Imagens e arquivos do mapa
Informações
- Descrição