ISTQB 2018 Foundation Software Testing 1

Robyn Babbage 40 perguntas 5.764 visualizações 5,0 (1 avaliação)

Fazer o quiz

Este quiz tem tempo limite, por isso abre no player de sempre.

Perguntas do quiz (40)

  1. 1During the test process of an Internet of Things software, a defect was discovered, but it was not corrected due to the release deadline. After the release, it has not yet caused a failure. A test team decides to fix this defect. Which trigger for maintenance is described in this scenario?
    1. AUpgrade of the software
    2. BMigration
    3. CCorrective change
    4. DIntroduction of completely new or modified thing into the system
  2. 2Consider the following activities:
    (i) Implementing an automated test case
    (ii) Performing the review of the architectural design
    (iii) Checking grammar and spelling of a user manual
    (iv) Planning test activities
    (v) Designing a test case

    Select all the activities that are part of the testing process.
    1. A(i), (iv), and (v)
    2. B(ii) and (v)
    3. C(i), (iii), and (iv)
    4. D(i), (ii), (iii), (iv), (v)
  3. 3Consider the piece of code:

    You executed a predefined set of test cases for this code. Which of the following guarantees that in at least one of these test cases, the while loop was executed at least once?
    Imagem da pergunta 3
    1. AA set of test cases achieved 50% decision coverage.
    2. BA set of test cases achieved 100% statement coverage.
    3. COne of these tests executes the code with NumberOfValues = 0.
    4. DThere are at least two test cases in the test suite.
  4. 4You test the autopilot system for the airplanes. You want to perform the tests that check the correctness of the communication between two modules of this system: geolocalisation module and engine controller. Which of the following would be the best example of a test basis for designing your tests?
    1. ADetailed design of the geolocalisation module
    2. BArchitectural design
    3. CRisk analysis reports
    4. DLegal regulations in the field of avionics
  5. 5Choose the correct sequence of events.
    1. AA mistake results in defect, which in turn may result in a failure.
    2. BA defect results in a mistake, which in turn may result in a failure.
    3. CA failure results in a mistake, which in turn may result in a defect.
    4. DA defect results in a failure, which in turn may result in a mistake.
  6. 6You test a system that computes the pass/fail result for a student who attends a lecture on software testing. The lecture consists of laboratories and exam. For each of these two parts, a student can get from 0 to 50 points (it is always an integer number). The final evaluation is based on the following rule (Please see image)

    You want to apply the equivalence partitioning technique to a FinalResult variable. Assume that each test is a pair (L, E). Which set of test cases covers all valid equivalence classes?
    Imagem da pergunta 6
    1. A(1, 50); (50, 50)
    2. B(39, 19); (28, 23)
    3. C(0, 50); (50, 0)
    4. D(35, 15); (40, 20)
  7. 7You work as a tester in a software house and you concurrently work on two projects. One of them is an internal tool for on-line room reservation, done within an agile life cycle. The other one is a commercial software for managing hospital patients' data, conducted in the waterfall model. In one month, new versions of both systems will be released. You don't have time to perform all the planned tests for both systems. You decide to focus on testing the commercial system. Select the correct answer.
    1. AThis is a good decision, because the commercial software is much more important for the company than the internal system.
    2. BThis is a bad decision, because critical defects can occur in both systems, and one of them will not be tested.
    3. CThis is a bad decision, because testing commercial project will be much more expensive than testing the internal one.
    4. DThis is a good decision, because the waterfall model requires testing during the end of the project.
  8. 8Figure 6.1 presents the set of test cases you want to execute. An arrow from a test case A to B indicates logical dependencies between these test cases: the execution of B is possible only after the execution of A. The number in parentheses represent the priorities of test cases (1= the highest, 5= the lowest). In your strategy, you want to prioritise the execution sequence regarding the test priority.
    Which test case should be executed as the fifth one?
    Imagem da pergunta 8
    1. ATC2
    2. BTC7
    3. CTC5
    4. DTC6
  9. 9Consider the collapsed decision table presented in Table 6.1 that describes the business rules for admitting a free bus ticket.
    Assume that a test consists of three Boolean values corresponding to three conditions. Which of the following tests demonstrates that the business ruled described in the table are contradictory?
    Imagem da pergunta 9
    1. A(member of parliament = TRUE, disabled = FALSE, student = TRUE)
    2. B(member of parliament = TRUE, disabled = TRUE, student = FALSE)
    3. C(member of parliament = FALSE, disabled = FALSE, student = TRUE)
    4. D(member of parliament = FALSE, disabled = FALSE, student = FALSE)
  10. 10You test a system that produced very big output files. Their structure must follow some set of predefined rules. The expected result of a test case is the file that follows these rules. You want to execute a set of test cases. Suppose you have a tool that takes two files as an input and returns TRUE if they are identical and FALSE otherwise. What would be the type of this tool in this case?
    1. AA test oracle
    2. BA comparator
    3. CA test data generator
    4. DA monitoring tool

Informações

Descrição
ISTQB - Foundation Level Foundation - Certified Tester Quiz sobre ISTQB 2018 Foundation Software Testing 1, criado por Robyn Babbage em 13-11-2018.
Idioma
English
Visualizações
5.764
Avaliação
5,0 de 5 · 1 avaliação
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?