Project Management Final

Laura Qualey 198 perguntas Atualizado em 18 jan 2017

Fazer o quiz

Perguntas do quiz (198)

  1. 1You are the Project Manager for a large construction project. While reviewing the expenditures, you realize that you are 20% over budget. What process group are you working in?
    1. AClosure
    2. BExecution
    3. CPlanning
    4. DMonitor & Control
  2. 2What is the main benefit of a balanced matrix organization over a projectized organizational structure?
    1. AAs a Project Manager, you have a great deal of authority
    2. BMore efficient use of resources
    3. CReporting to a functional manager
    4. DReporting to 2 Managers
  3. 3As the Sponsor on a large, multi-national hydroelectric power project, during the execution phase, your primary responsibilities are to:
    1. AProvide the financial resources and champion the project
    2. BManage a group of interrelated projects
    3. CManage the Project Team
    4. DProvide status updates to the customer
  4. 4Name the 5 project management process groups.
    1. AInitiating, Planning, Executing, Monitoring & Control, Closing
    2. BPlanning, Executing, Monitoring, Integrated Change, Closing
    3. CBusiness Case, Planning, Executing, Monitoring & Control, Closing
  5. 5You are hired to manage an exciting new project for a software development company making CRM tools. You are unfamiliar with the project management resources available in the company. Who should you go to for help identifying the resources and best practices?
    1. AProject Sponsor
    2. BOperations Manager
    3. COther Project Managers
    4. DProject Management Office
  6. 6As you progress through the project life cycle:
    1. ARisk increases and cost of changes increases
    2. BCost of changes decreases and risk increases
    3. CRisk decreases and cost of changes increases
    4. DCost of changes decreases and risk decreases
  7. 7The purpose of the Closer Process Group is:
    1. AComplete the work as quickly as possible
    2. BAnalyze the project risks at the end of the project
    3. CInspect the outputs to ensure the quality is as planned
    4. DFormally complete the project
  8. 8In the Statement Of Work, you provide:
    1. AProject charter
    2. BMarket demand analysis
    3. CChange control tools you will use
    4. DScope description
  9. 9The output of the Develop Project Charter process is:
    1. AProject charter
    2. BProject Management Plan
    3. CWork performance data
    4. DBusiness case
  10. 10According to the PMBOK all the following are types of project constraints except:
    1. AScope
    2. BPortfolio Alignment
    3. CRisks
    4. DSchedule

Informações

Descrição
Quiz sobre Project Management Final, criado por Laura Qualey em 22-07-2015.
Idioma
English
Visualizações
80
Histórico
Criado em 22 jul 2015 · atualizado em 18 jan 2017
Avaliação
Ainda sem avaliações
Avalie este quiz
Avalie este quiz

Fale Conosco

Sobre o que é sua mensagem?

O que você acha do novo visual?

Você gostou?