  1. 16. A likely result of fast tracking, in addition to hoped-for shortening of the project schedule, is:
    1. Aa. Fewer resources.
    2. Bb. Increased risk.
    3. Cc. Lower costs.
    4. Dd. Greater control.
  2. 25. PMBOK@ Guide states that the Estimate Resource process is 'closely coordinated with' the Estimate Costs process. The Course states that resource estimating cannot be done independently from a still different process. Which one is that?
    1. Aa. Sequence Activities.
    2. Bb. Estimate Durations.
    3. Cc. Plan Quality.
    4. Dd. Identify Risks.

Information

Description
Quiz on Untitled, created by brandon mayo on 09/10/2017.
Language
English
Views
0
History
Created on 9 Oct 2017 · updated on 9 Oct 2017
Tags
pmp
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?