11._______ refer(s) to all the work involved in creating the products of the project and the pro- cesses used to create them.
- Aa. deliverables
- Bb. milestones
- Cc. scope
- Dproduct development
22. Which tool or technique for collecting requirements is often the most expensive and time consuming?
- Aa. interviews
- Bb. focus groups
- Cc. surveys
- Dd. obseravation
33. A _______ is a deliverable-oriented grouping of the work involved in a project that defines its total scope.
- Aa. scope statement
- Bb. WBS
- Cc. WBS dictionary
- Dd. work package
44. What approach to developing a WBS involves writing down or drawing ideas in a nonlinear format?
- Aa. top-down
- Bb. bottom-up
- Cc. analogy
- Dd. mind mapping
55. Assume that you have a project with major categories called planning, analysis, design, and testing. What level of the WBS would these items fall und
- Aa. 0
- Bb. 1
- Cc. 2
- Dd. 3
66. Which of the following is not a best practice that can help in avoiding scope problems on IT projects?
- Aa. Keep the scope realistic
- Bb. Use off-the-shelf hardware and software whenever possible
- Cc. Follow good project management processes
- Dd. Don't involve too many users in scope management
77. Why did McDonald’s terminate a large project after spending $170 million on it?
- Aa. The copmany found a better technology
- Bb. The company decided to outsource the work
- Cc. The scope was too much to handle
- Dd. The government requirement that prompted the project was repealed
88. Scope _______ is often achieved by a customer inspection and then sign-off on key deliverables.
- Aa. acceptance
- Bb. validation
- Cc. completion
- Dd. close-out
99. Which of the following is not a suggestion for improving user input?
- Aa. Develop a good project selection process for IT projects
- Bb. Have users on the project team
- Cc. Co-locate users with developers
- Dd. Only have meetings as needed, not on a regular basis
1010. Project management software helps you develop a _______, which serves as a basis for creating Gantt charts, assigning resources, and allocating costs.
- Aa. project plan
- Bb. schedule
- Cc. WBS
- Dd. deliverable
Information
- Description
- CIS 4375 Quiz on Chapter 5 IT Book Questions, created by . . on 18/10/2017.
- Author
- . .
- Language
- English
- Views
- 1
- Tags
- Rating
- No ratings yet Rate this quiz
More on Work Breakdown Structure