Help shape GoConqr. What should we add next?

Quiz

MGT 360 Exam 2

Mason Kimball 60 questions

Take the quiz

Questions in this quiz (60)

  1. 1One of the prerequisites to job rotation is cross-training
    1. ATrue
    2. BFalse
  2. 2Fitting the task to the person in a work environment is know as job analysis
    1. ATrue
    2. BFalse
  3. 3___________ illustrate the improvement rate of workers as a job is repeated
    1. ALearning curves
    2. BProcess curves
    3. CLearning charts
    4. DProcess charts
  4. 4A Gnatt chart provides a visual display of the project schedule that includes scheduled start times, finish time, and available slack
    1. ATrue
    2. BFalse
  5. 5Project scheduling is recognized as the most critical element in the project management process
    1. ATrue
    2. BFalse
  6. 6In project management the term slack refers to the amount of time
    1. Ato complete an activity without delaying the project
    2. Ban activity can be delayed without delaying the project
    3. Cneeded to complete the entire project
    4. Drequired to complete the project's critical activities
  7. 7In general, the latest finish time for an activity is equal to
    1. Alatest finish time minus the activity time estimate
    2. Bthe minimum of the latest start times for the activities that immediately follow
    3. Cthe maximum of the latest start times for the activities that immediately follow
    4. Dthe average of the latest start times for the activities that immediately follow
  8. 8The slack time for an activity can be computed as
    1. Alatest start time (LS) - latest finish time (FL)
    2. Bearliest start time (ES) + earliest finish time (EF)
    3. Clatest start time (LS) - earliest start time (ES)
    4. Dlatest finish time (LF) + earliest finish time (EF)
  9. 9Using Table XX, the earliest finish (EF) time for activity D isImage for question 9
    1. A7 weeks
    2. B13 weeks
    3. C20 weeks
    4. D30 weeks
  10. 10Using Table XX, the latest start (LS) time for activity B isImage for question 10
    1. A5 weeks
    2. B8 weeks
    3. C13 weeks
    4. D14 weeks

Information

Description
Quiz on MGT 360 Exam 2, created by Mason Kimball on 08/11/2017.
Language
English
Views
6
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What should we add next?