Quiz
Project Management - Project Management & Planning
This quiz has question types that open in the usual player.
Questions in this quiz (126)
1Which of the following are duties or responsibilities of Project Management?
- AProject Planning
- BScheduling
- CMonitoring
- DCoordinating & Directing
- EUpdating Documentation
- FClosing out the job
- GFollowing Up with Clients
2Which of the following apply to Project Management?
- AIs often the responsibility of a single person
- BCan be the responsibility of various stakeholders (architect, owner, contractor, and vendors) who all participate in the decision-making process through "partnering"
- CThe lines of communication and of delegation of responsibility should be established at the beginning of the project
3Which of the following is an advantage of Partnering?
- ACan produce closer communication on a project and can result in shared responsibilities
- BCan shorten the project delivery schedule
- CCan reduce responsibility for all parties
- DCan reduce costs
4Which of the following is a disadvantage of Partnering?
- AThe day-to-day management of a project can be difficult with so many people involved
- BIncreases responsibilities of the architect
- CCan result in longer construction schedules
- DCan increase project costs
5Which of the following correctly describes Partnering?
- AVarious stakeholders in a project (the architect, owner, contractor, & vendors) all participate in the decision making process and can result in closer communication and shared responsibility
- BWhen project management is the responsibility of a single person
- CIs a separate legal entity created for a specific project in which multiple firms merge to complete
- DIs a form of agreement associated with Integrated Project Delivery established for multiple entities to merge into one for the purpose of completing a project
6Which of the following is the primary responsibility of the Project Manager?
- ACoordinate the activities of all members of the design & construction teams who are related to the firm
- BTake part in team marketing efforts
- CTake part in writing proposals & fee estimates
- DTake part in preparing the agreement between the architect & the owner
- EAssemble the project team
- FPrepare the time estimate for the project
- GCreate the project schedule
- HTake part in the hiring & coordination of consultants
- IOrganize & coordinate all activities needed to complete the project
- JKeep the project on track to meet the goals laid out by the client and the design team
7Place the following in the diagrams
- AContractor
- BConsultants
- CStaff
- DProject Designer
- EClient
- FFirm Principals
- GRegulatory Agencies
8Which of the following are business development responsibilities of the Project Manager?
- AWork with the upper management and other project managers to maintain overall office workload scheduling
- BTake part in team marketing efforts
- CDetermine the firm's annual indirect expenses budget
- DEmployee Evaulations
- ERepresent and Network at industry events
9Which of the following are possible Pre-Design Project Manager responsibilities?
- ATake part in preparing the agreement between the architect and the owner
- BAssemble the project team
- CPrepare the time estimate for the project
- DCreate the project schedule
- ETake part in preparing the agreement between the architect and the contractor
- FAssist the client in acquiring proper builder's insurance
- GTake part in writing proposals and fee estimates
10Which of the following are general project-related responsibilities of the Project Manager?
- ATake part in the hiring and coordination of consultants
- BOrganize and coordinate all activities needed to complete the project
- CKeep the project on track to meet the goals laid out by the client and the design team
- DMake sure that the office meets all its contractual obligations
- EReview all invoices that the firm will send to the client
- FReview in all invoices that the consultants have sent to the firm, and approve payment as appropriate
- GDetermine a form of arbitration or litigation if the client does not pay an invoice after 90 days
11Which of the following are possible project team and communication related responsibilities of the Project Manager?
- ASchedule meetings & coordinate progress among all team members
- BManage the personnel assigned to the project
- CTake part in resolving conflicts among team members
- DBe the primary link between the principals and the project team
- EKeep track of personnel time spent on the job, compare it against initial estimates, and take corrective action as needed
- FOperations management
12Which of the following are Design Development and Production related responsibilities of the Project Manager?
- AAttend client presentations
- BObtain client approvals at important project milestones
- CBe the contact person for the project with governmental agencies and other regulatory groups
- DProvide status reports to the principals
- EAt as the principal's agent
13Which of the following are possible construction documentation related Project Manager responsibilities?
- ASee that all aspects of the project are documented
- BCoordinate the production of construction documents
- CTake part in bidding or negotiation procedures
- DDetermine the means and methods of construction
14Which of the following are possible Construction Administration responsibilities of the Project Manager?
- AProcess all change orders, certificates for payment, work authorizations, and similar documents
- BKeep track of construction cost estimates as design and production proceed, and compare them against the client's budget
- CConfirm that proper contract administration and construction observation are carried out
- DHelp collect overdue billings
- EHelp the client with construction-related problems during and after move-in
- FClose out the job
- GFollow up with the client periodically after move-in
15Which of the following are software related tasks completed by the project manager?
- AProject Personnel Time and Fees and track actual time and fees in comparison to budgeted figures
- BCompile information from individual jobs into office-wide financial management reports
- CTrack consultant costs
- DSchedule work within the office
- EGenerate Invoices
- FMaintain project documentation such as Correspondence, Transmittals, and Meeting notes
- GTrack Construction-related documents such as Change Orders and Site Visits
- HMaintain information about individual project design and specification decisions
- IKeep a project address book with all team contacts
- JTrack Employee Productivity
16A Project Manager has been assigned to the construction of a new office building using the design-build project delivery method. The site has been fully designed by a landscape architect except for utilities. The contractor determines that the building systems will use design-build subcontractors. Which team members must the project manager include as consultants and staff to complete the project? (Choose the four that apply)
- ASpecification Writer
- BFire Protection Engineer
- CIn-house project designer
- DMechanical, Electrical, and Plumbing Engineers
- ECivil Engineer
- FStructural Engineer
17Select the minimum members of an overall project team:
- AArchitect
- BConsultants
- CClient
- DConstruction Manager
- EContractor
- FMajor subcontractors
18In addition to the minimum members of a project team, which of the following are also possible members depending on the project delivery method?
- AConstruction Manager
- BContractor
- CMajor Subcontractors
- DArchitect
- EConsultants
- FClient
19When submitting proposals in competition the architectural firms are usually required to identify which of the following as major players on their team?
- AThe firm principal overseeing the project
- BThe lead designer
- CThe project manager
- DThe consulting firms that will be used
- ESpecialty consultants, commissioning agents, and major suppliers to the job particularly if the costs associated with their services should be included in the architect's total fee proposal
- FThe contractor
- GThe subcontractors
20When submitting proposals in competition for a design-build project or project led by construction manager the design-build entities are usually required to identify which of the following additional members as major players on their team?
- AConstruction Manager
- BContractor
- CMajor Subcontractors
21Which of the following is one of the most important factors when an architecture firm is selecting consultants to bring into a project?
- APast working relationships
- BThe Available Staff
- CFee Proposal
22How the project manager selects the team depends on how the office is organized and how it works.
- ATrue
- BFalse
23Which of the following should be considered when the project manager of a studio based firm is assembling a project team?
- AThe Type and Complexity of a Project
- BThe Size of the Project
- CStaff Availability
- DExperience Level
- EBilling Rates
- FPersonalities
- GClient staff relationships
24[blank_start]Project Type and Complexity[blank_end]: Some projects may require experience and expertise that only a few people in the office have
[blank_start]Project Size[blank_end]: Small projects can be completed by just a few staff members with nominal experience, but large projects need more staff members with a wider range of experience and knowledge
[blank_start]Staff Availability[blank_end]: Some staff members will already be committed to other projects and unavailable to work on the new one
[blank_start]Experience Level[blank_end]: The project manager must determine the tasks that the project team will need to perform over the life of the project, and then match these tasks with the skills and knowledge that available staff members have
[blank_start]Billing Rates[blank_end]: The budget for the project may suggest that certain billing rates be kept to a minimum, but this must be balanced with the experience and knowledge needed for the job. For example, the project manager may decide to use several less skilled staff members with lower billing rates, and have them supervised by one experienced professional
[blank_start]Personalities[blank_end]: A project team requires close, long term cooperation and mutual support, so team members must have compatible personalities and working methods. A good project manager is aware of which working relationships in the office are good and which are problematic- AProject Type and Complexity
- BProject Size
- CStaff Availability
- DExperience Level
- EBilling Rates
- FPersonalities
25Which of the following are considered Building Systems?
- AMechanical
- BElectrical
- CPlumbing
- DFire Protection
- EStructural
- FCivil
- GSpecifications
26Using the provided Gantt chart determine which of the following project phases will require the longest time to complete.
- ASpecifications
- BDesign Development
- CConstruction Documents
- DSchematic Design
27Which of the following are the two methods commonly used for scheduling design and construction projects?
- AThe Bar Chart / Gantt Chart
- BThe Critical Path Method Chart
- CProject Progress Report
- DProject Cost Report
28Which method commonly used for scheduling design and construction projects is the simpler method?
- AThe Bar Chart / Gantt Chart
- BThe Critical Path Method Chart
- CProject Progress Report
- DProject Cost Accounting
29Which of the following apply to the Bar Chart method to scheduling a project?
- ACan show at a glance which tasks should be happening at any give time and which tasks must occur in sequence
- BAre easy to create and understand and are suitable for projects of almost any size
- CGantt Chart
- DIs used more often with construction projects than with design projects
- EDepicts all the tasks needed to complete a project, the sequence in which the tasks must occur, each task's duration, earliest and latest possible starting times, & earliest & latest possible finishing times
30Which of the following apply to the Critical Path Method (CPM) Chart to scheduling a project?
- AIs used more often with construction projects than with design projects
- BDepicts all the tasks needed to complete a project, the sequence in which the tasks must occur, each task's duration, earliest and latest possible starting times, & earliest & latest possible finishing times
- CIs the simpler of the two scheduling methods
- DCan show at a glance which tasks should be happening at any given time and which tasks must occur in sequence
- EIs easy to create and understand and is suitable for projects of almost any size
31Which of the following describe the organization of the Bar Chart?
- AVarious tasks / activities that must be done in order to complete the project are listed in chronological order along the vertical axis
- BFor each task / activity, a horizontal bar is drawn from the task's start date to its end date
- CIf one task must be completed before another can start, an arrow is drawn from the end of the earlier task to the beginning of the later one
- DEach solid arrow represents a task
- EEach task's beginning and end points are represented by numbered circles
- FA task cannot begin until all the tasks that lead into its beginning circle have been completed
- GThe number under each arrow is the number of days that the task will take to complete
- HDashed arrows represent dependencies (aka dummies)
- IThe heavier arrows show the critical path, the sequence of those tasks (called critical tasks) that must start and finish on time if the project's final deadline is to be met
32Which of the following describe the organization of the Critical Path Method (CPM) Chart?
- AEach solid arrow represents a task
- BEach task's beginning and end points are represented by numbered circles
- CA task cannot begin until all the tasks that lead into its beginning circle have been completed
- DThe number under each arrow is the number of days that the task will take to complete
- EDashed arrows represent dependencies (aka dummies)
- FThe heavier arrows show the critical path, the sequence of those tasks (called critical tasks) that must start and finish on time if the project's final deadline is to be met
- GVarious tasks / activities that must be done in order to complete the project are listed in chronological order along the vertical axis
- HFor each task / activity, a horizontal bar is drawn from the task's start date to its end date
- IIf one tasks must be completed before another can start, an arrow is drawn from the end of the earlier tasks to the beginning of the later one
33Which of the following are included in the Critical Path Method (CPM) Chart?
- AAll the tasks needed to complete a project
- BThe sequence in which the tasks must occur
- CEach tasks duration
- DEarliest and latest possible starting times
- EEarliest and latest possible finishing times
- FBudgeted fee per project phase & task
34Which of the following are included in the Bar / Gantt Chart?
- AAll the tasks / activities needed to complete a project
- BThe sequence in which the tasks must occur
- CEach tasks duration
- DEarliest and latest possible starting times
- EEarliest and latest possible finishing times
- FBudgeted fees per project phase & task
35Which of the following is another term for tasks that must be done in order to complete a project?
- AActivities
- BDependencies
- CDummies
- DCritical Path
- ECritical Task
- FNoncritical Task
- GFloat
36In a Bar / Gantt Chart, which of the following is the term to describe when one task / activity must be completed before another can start (represented by an arrow drawn from the end of the earlier task to the beginning of the later one)?
- ADependency
- BActivities
- CDummies
- DCritical Path
- ECritical Task
- FNoncritical Task
- GFloat
37In a CPM (Critical Path Method Chart), which of the following is the term to describe when one task / activity must be completed before another can start (represented by dashed arrows)?
- ADummies
- BDependency
- CActivities
- DTasks
- ECritical Path
- FCritical Task
- GNoncritical Task
- HFloat
38In a CPM (Critical Path Method Chart), which of the following is the term to describe the heavier arrows that represent the sequence of tasks that must start and finish on time if the project's final deadline is to be met?
- ACritical Path
- BActivities
- CTasks
- DDependency
- EDummies
- FNoncritical Tasks
- GFloat
- HCritical Tasks
39In a CPM (Critical Path Method Chart), which of the following is the term to describe the tasks that must start and finish on time if the project's final deadline is to be met and if delaying the start of said tasks or increasing the duration delays the whole project?
- ACritical Tasks
- BActivities
- CTasks
- DDependency
- EDummies
- FCritical Path
- GNoncritical Tasks
- HFloat
40In a CPM (Critical Path Method Chart), which of the following is the term to describe the tasks that may start somewhat later or take somewhat longer without affecting the final completion date?
- ANoncritical Tasks
- BActivities
- CTasks
- DDependency
- EDummies
- FCritical Path
- GCritical Tasks
- HFloat
41In a CPM (Critical Path Method Chart), which of the following is the term to describe the maximum length of time that a noncritical task can be delayed or extended before it causes a delay in the overall project the what of that task?
- AFloat
- BActivities
- CTasks
- DDependency
- EDummies
- FCritical Path
- GNoncritical Tasks
- HCritical Tasks
42Label the CPM (Critical Path Method) Diagram

- ADays to Complete the Task
- BDays
- CEach Task's beginning & ending points
- DCritical Path
- EDummies
43Which of the following are functions of the Work Plan?
- ADetailed Project Schedule
- BBreaking the project down into its component tasks and assigning staff members and other resources to each task
- CDetails how the fee that the firm receives after deductions for profit, overhead, and other expenses - will be used to pay staff members and cover other costs over the course of the project
- DAll the various tasks that must be done in order to complete the project are listed in chronological order along the vertical axis of a bar chart
44Which is one of the earliest and most important tasks that a project manager must complete?
- ACreating the Work Plan (aka Fee Projection)
- BTake part in team marketing efforts
- CAssemble the project team
- DTake part in the hiring and coordination of consultants
45Which of the following apply to the Work Plan?
- AFee Projection
- BIs one of the earliest and most important tasks that a project manager must complete
- CIs a detailed project schedule breaking the project down into its component tasks and assigning staff members and other resources to each task
- DDetails how the fee that the firm receives - after deductions for profit, overhead, and other expenses - will be used to pay staff members and cover other costs over the course of the project
- EIs a general summary of the project schedule
46A good Work Plan includes which of the following items?
- AThe Scope of Services in the Agreement
- BA Breakdown of the services to be provided into phases and individual tasks
- CDependencies
- DMilestones
- EThe staff needed to do the work
- FAllocation of time and fees to phases and individual tasks
- GWhat work will be done by consultants, and what fees and other costs will be associated with their work
- HHow individual insurance policies apply to specific phases of a project
47[blank_start]The Scope of Services[blank_end]: in the agreement is drawn directly from the owner-architect agreement, and states what the architect is legally required to provide. It is important that all members of the project team understand what services are included in and excluded from the contract. If the client requests additional services, the project manager should request additional compensation.
[blank_start]A Breakdown of the services[blank_end] to be provided into phases & individual tasks: This is the heart of the work plan. It requires the project manager to think through the entire project in detail and identify exactly what needs to be done to complete the project.
[blank_start]Dependencies[blank_end]: The work plan should identify all the cases where one task cannot be started until some other task has been completed.
[blank_start]Milestones[blank_end]: The work plan should identify specific points & events in the project's schedule that will act as markers of the progress made toward completion. Typical milestones can include a crucial meeting, the completion of a phase, the completion of a deliverable, the client's approval of a deliverable, or the approval of a governmental agency
[blank_start]The Staff needed to do the work[blank_end]: The project manager assigns specific members of the project team to the individual tasks.
[blank_start]Allocation of time and fees[blank_end] to phases and individual tasks: This is crucial for project monitoring.
[blank_start]What work will be done by consultants[blank_end], what fees & other costs will be associated with their work: The work plan should also give the major components of the consultants' schedules.- AThe Scope of Services
- BA Breakdown of the services
- CDependencies
- DMilestones
- EThe Staff needed to do the work
- FAllocation of time and fees
- GWhat work will be done by consultants
48Which is the primary element of a Work Plan?
- AThe Schedule
- BThe Scope of Services in the Agreement
- CA breakdown of services to be provided
- DDependencies
- EMilestones
- FThe staff needed to do the work
49Which of the following are steps needed in forming the project schedule?
- AConsider the scope of the project: includes project type, size, budget, and services that must be completed
- BDefine each tasks, establishing the start and end dates both for design services and any construction that is required
- CAssign staff members for the completion of each tasks within its allotted time
50Which of the following apply to the scope of a project?
- AType
- BSize
- CBudget
- DServices that must be completed
- EClient
51The level of detail that a work plan needs depends on the complexity of the project
- ATrue
- BFalse
52The work plan must be detailed enough so that
- AThe project manager can assign specific tasks to individual staff members
- BSo that the staff members can understand and perform their assigned tasks
- CSo that staff members' progress can be tracked
53A project manager must have sufficient experience in all phases of design in order to accurately determine how much time a task will take based on the experience level of the person who will perform the task.
- ATrue
- BFalse
54Which of the following is one of the more difficult parts of the work plan process?
- AEstimating how much time will be required for various tasks and depending on the experience level of the person who will perform the task
- BDetermining Milestones
- CDetermining what work will be done by consultants and what fees and other costs will be associated with their work
- DThe scope of services in the agreement
55The organization of a Work Plan is best described as,
- AThe tasks are listed in chronological order along the vertical axis of a bar chart so that the first task is at the top of the schedule and the final task is at the bottom, closest to the horizontal axis
- BThe tasks are listed in chronological order along the horizontal axis of a bar chart so that the first task is at the left of the schedule, closest to the vertical axis, and the final task is at the far right
- CThe time needed for each task is listed along the horizontal axis
- DThe timeline is usually divided into weeks for easy and accurate planning and monitoring but may be divided into months for projects with very long durations
- EThe time needed for each task is listed along the vertical axis
56[blank_start]Bottom-Up Analysis[blank_end] : considers the efforts associated with each task during each phase of the project and includes the efforts to resolve risks. It tends to be higher than other methods because all efforts and risks are considered
[blank_start]Top-Down Analysis[blank_end] : This approach starts out with having an idea with what the total fee should be at the beginning. It can be based on experience with similar types of projects / clients, specific market, competition, or percentage based on construction costs. Once the total fee has been established it is divided among consultants & contingencies, resulting in a net fee for the Architectural service.
[blank_start]Staff Analysis[blank_end] : Considers the durations and staffing requirements necessary to complete each phase- ABottom-Up Analysis
- BTop-Down Analysis
- CStaff Analysis
57Which of the following describe the Bottom-Up Approach for estimating fees?
- AConsiders the efforts associated with each task during each phase of the project and includes the efforts to resolve risk
- BTends to be higher than other methods because all efforts and risks are considered
- CStarts out with having an idea of what the total fee should be at the beginning
- DCan be based on experience with similar types of projects / clients, specific market, competition, or percentage based on construction costs.
- EOnce the total fee has been established it is divided among consultants & contingencies, resulting in a net fee for the Architectural service
- FConsiders the duration and staffing requirements necessary to complete each phase
58For a traditional Design-Bid-Build project, the fee allocations per phase are:
Schematic Design: [blank_start]15%[blank_end]
Design Development: [blank_start]20%[blank_end]
Construction Documentation: [blank_start]40%[blank_end]
Bidding: [blank_start]5%[blank_end]
Construction Administration: 20%- A15%
- B20%
- C40%
- D5%
59In a Design-Bid-Build, What is the typical fee allocation for schematic design?
- A15%
- B20%
- C40%
- D5%
60In a Design-Bid-Build, What is the typical fee allocation for Design Development?
- A20%
- B15%
- C40%
- D5%
61In a Design-Bid-Build, What is the typical fee allocation for Construction Documentation?
- A40%
- B15%
- C20%
- D5%
62In a Design-Bid-Build, what is the typical fee allocation for Bidding?
- A5%
- B15%
- C20%
- D40%
63In a Design-Bid-Build, what is the typical fee allocation for Construction Administration?
- A20%
- B15%
- C5%
- D40%
64The Top-Down approach of estimating fees is generally made using a combination of which of the following rules of thumb?
- ACertain Percentage of the Construction Costs
- BCertain Amount Per Square Foot
- CThe amount varying with the building's size and type
- DHistorical Data (data about similar buildings in the past)
65With the Top-Down Approach for estimating fees, the total fee will typically include:
- AFees for Direct Labor
- BFees for Indirect Labor
- CConsultant's Fees
- DNon-Reimbursable expenses
- EContingency
- FReimbursable Expenses
66To determine the portion of the total fee that is available for "Direct Labor," with the Top-Down Approach for fee estimation, the amounts of which other elements must be subtracted from the total fee?
- AIndirect Labor
- BDirect Labor
- CConsultant's Fees
- DNon-Reimbursable Expenses
- EThe Contingency
67Top-Down Approach to estimating fees is typically based on [blank_start]Historical Data[blank_end] and are often calculated as a [blank_start]Percentage of the Total Fee[blank_end].
- AHistorical Data
- BPercentage of the Total Fee
- CAmount per square foot
- DMarket Data & Pricing
68Which of the following are factors that may cause the percentage of fee allocation per phase to vary from the typical?
- AIf additional services such as programming, and post-construction work are included
- BDiffers per project delivery method, The project manager will allocate fees quite differently if an integrated delivery method is used instead of design-bid-build
69The attached Work Plan shows which approach to fee estimation?
- AThe Top-Down Approach
- BThe Bottom-Up Approach
- CStaff Analysis Approach
70Which of the following apply to the "Total Working Fee" shown in a Work Plan with a Top-Down approach?
- AThe fee available to pay people to do the job after subtracting fees for profit, consultants, and other expenses
- BIs listed in the upper right hand corner of the chart
- CIs listed in the lower right hand corner of the chart
- DThe fee available to pay people to do the job including consultants after subtracting fees for profit, expenses, and contingency
71The time periods listed at across the top of the Work Plan chart are typically divided into:
- AWeeks
- BDays
- CMonths
- DHours
72What is the dollar amount available for a phase that is 20% of the total working fee of $26,400?
- A5280.00
- B1320.00
- C3960.00
- D2640
73A phase that consists of 5 time periods has 20% of the of the total working fee of $26,400. What is the monetary amount of fee that is available for each time period of this phase?
- A1056.00
- B1320.00
- C1980.00
- D790.00
74Which of the following apply to the Bottom-Up Approach for fee estimation?
- ABegins by breaking the project down into individual tasks, listing the tasks in order along the left side of the chart & estimating how much time will be needed (in hours or weeks) to complete each one
- BThe total estimated fee can be calculated by assigning a specific staff member with a defined billing rate to each task
- CConsiders the efforts associated with each task during each phase of the project and includes the efforts to resolve risks
- DTends to be higher than other methods because all efforts and risks are considered
- EStarts out with having an idea of what the total fee should be at the beginning
- FOnce the total fee has been established (usually based of off historical data) it is divided among consultants & contingencies resulting in a net fee for the architectural service (aka working fee)
75Which of the following apply to the Top-Down Approach to fee estimation?
- AStarts out having an idea of what the total fee should be at the beginning
- BThe total fee can be based on experience with similar types of projects / clients, specific market, competition, or percentage based on construction costs
- COnce the total fee has been established it is divided among consultants & contingencies, resulting in a net fee for the Architectural service (working fee)
- DConsiders the efforts associated with each task during each phase of the project and includes the efforts to resolve risks. It tends to be higher than other methods because all efforts and risks are considered
- EBegins by breaking the project down into individual tasks, listing the tasks in order along the left side of the chart, and estimating how much time will be needed (in hours or weeks) to complete each one
- FThe total estimated fee can be calculated by assigning a specific staff member with a defined billing rate to each task
76Label the following

- ATotal Fee
- BBudgeted Fees per Period
- CPerson-Hours or Weeks
- D% Of Total Fee
- EFee Allocation per Phase / Task
77Which of the following is true?
- AThe bottom-up approach is more accurate than the top-down method
- BThe top-down method is more accurate than the bottom-up approach
78The project manager can feel confident that the estimate is sound if,
- AThe fees found using both the Bottom-Up and the Top-Down approach are about equal
- BThe fees found using the Bottom-Up approach are less than the Top-Down approach
- CThe fees found using the Bottom-up approach are greater than the Top-down approach
79The project manager can compare the actual hours (or fees) expended to the budgeted time (or fees) and take correction action if the actual time exceeds the budgeted time by monitoring employee's time sheets at what frequency?
- ADaily
- BWeekly
- CBiweekly
- DMonthly
80Which specialized chart can the project manager use to monitor employee's time sheets in order to compare the actual hours (or fees) expended to the budgeted time (or fees) and take correction action if the actual time exceeds the budgeted time?
- AProject Monitoring Chart
- BWork Plan aka Fee Projection chart
- CGantt Chart
- DCritical Path Method Chart
81Which of the following are means to monitor a project? (Select Two)
- AFull Wall Schedule
- BProject Monitoring Chart
- CTop-Down Approach
- DBottom-Up Approach
82Which of the following is the one of the most important parts of the project manager's job?
- ACoordinating the work of the design office staff, consultants, and client while making sure all codes and regulations requirements are met
- BTake part in resolving conflicts among team members
- CBe the primary link between the principals and the project team
- DProvide status reports to principals
- ESee that all aspects of the project are documented
- FProcess all change orders, certificates for payment, work authorizations, and similar documents
- GTake part in the bidding or negotiation procedures
83The success of the management of a project ultimately depends on,
- AThe project manager's ability to understand interpersonal relationships within the context of a business environment and use this knowledge to organize and motivate all the people involved in the project
- BThe project manager's ability to use a variety of computer aided scheduling & budgeting software
- CThe project manager's network of professionals & clients and understanding of the targeted market and user groups
- DThe project manager's years of experience managing projects and construction
84Which of the following are some of the actions a project manager can take to add a personal dimension to the everyday direction of the project team coordination?
- ACommunicate & Open up communication among team members
- BAlways clarify the expectations of project team members
- CNever give responsibility to an employee who does not have enough authority to make decisions and carry out actions
- DBe sensitive to the manager-subordinate relationship
- EDon't shut out the client, instead direct the client's interest to areas where his or her contributions will be most valued
- FCommit to resolving conflicts as they occur and stay calm when people get angry
- GModel the behavior you want to see
- HGive Recognition when it is due and provide ways for staff members to grow and advance
- IEvaluate the performance of the staff members on the project team
- JEstablish an environment in which initiative is encouraged
85Which of the following are the four basic kinds of communication in a design office?
- AWork Assignments
- BInstructions
- CReward and Punishment
- DSocial Interaction
- EDigital
- FWritten
- GSpoken
86Which are the 3 main items that a project manger should always provide to clarify the expectations of project team members?
- AOutline the task (What is wanted/needed)
- BThe Time allowed (When it needs to be completed)
- CThe Results that are expected (at what level of detail or quality)
- DCollaboration (who to work with or consult)
- EHow to perform the task (instruction)
87A project manager wants to reward a staff member on their performance on a project. How should the project manager communicate appreciation of the staff member's efforts?
- AChat with the staff member about yesterday's football game and then mention that he is doing a good job to lessen the emphasis and effect of the praise
- BTell the staff member directly that he/she is valuable to the team without mixing it with social communication
88Never give responsibility to an employee who does not have enough authority to make decisions and carry out actions
- ATrue
- BFalse
89The greatest impact, each kind of communication should be handled separately
- ATrue
- BFalse
90A message with a single purpose is more likely to be understood
- ATrue
- BFalse
91A good project manager recognizes anger as a symptom of a significant problem, not just a personality trait. It may indicate a problem with the project that would not come to the surface any other way until it was too late. The manager should analyze the anger, find out what is causing it, and work with the person to solve the problem. Don't simply dismiss the anger or get angry in return
- ATrue
- BFalse
92A conflict has occurred what is the best action to take?
- AAvoid a problem and hope it will go away
- BSolve the problem as soon as possible and commit to resolving conflicts as they occur
93When giving recognition when it is due, a project manager should, (select 2)
- AGive praise publically
- BEncourage self-esteem
- CGive praise privately
- DBe cautious to avoid instigating jealousy or competition among staff members or inflating a staff member's ego
94When evaluating a staff member's performance on the project team, the project manger should
- AProvide evaluation on a continuing basis
- BGive it privately
- CSuggest techniques for improvement and offer help if it is needed
- DGive evaluations with all team members present
95Which of the following is a successful means to establish an environment in which initiative and success of the project & work is encouraged and an atmosphere that inspires fresh thinking and the willingness to explore?
- AWhen employees feel that their contributions are valued
- BHold a mandatory team lunch every 2 weeks to bond with staff members
- CCreate an adversarial atmosphere of competition between staff members
96Which of the following consultants are most often engaged by architectural firms? (Select 3)
- AStructural Engineers
- BMechanical Engineers
- CElectrical Engineers
- DCivil Engineers
- EBuilding Code Compliance
- FInterior Designers
- GFire Protection
97Which of the following are non standard consultants that may be needed by the architectural firm?
- AAcoustical Design
- BConstruction Specifications
- CBuilding Code Compliance
- DFire Protection
- EHardware
- FCommercial Food Service
- GSecurity Systems
- HAudiovisual systems
- ITelecommunication systems
- JStructural, Mechanical, Electrical, Plumbing Engineers
98Which member of a project team is responsible for coordinating the work of all consultants?
- AProject Manager
- BConstruction Manager
- CClient
- DContractor
- ETeam lead Designer
- FPrinicipal
- GArchitect of Record
99Which of the following are responsibilities of the Structural Engineer?
- ADesigns any new structure or structural modifications
- BBuilding foundations
- CBuilding frames
- DFloors
- ELoad-bearing walls
- FProduces any drawings and specifications for the structural portion of the project
100The Mechanical Engineer typically designs and produces the drawings and specifications for?
- AHeating Ventilating and Air Conditioning (HVAC)
- BPlumbing Systems
- CFire Protection Systems, including sprinkler systems
- DElectrical
101The Electrical Engineer typically designs and produces the drawings and specifications for the?
- APower System
- BOutlets and Equipment
- CLighting System
- DTelephone system
- ESignal System
- FSecurity System
- GCoordinate the work of any specialized consultants on the job to ensure that what they do complies with the design intent
102The project manager should involve the consultants in the project,
- AAs early as possible
- BOnly when they are needed
- CAt the start of Construction Documentation
- DAt the start of Design Development
103The advice and expertise of consultants is vital to determining,
- AThe Scope of the Project
- BDeveloping Broad Conceptual Approaches to solving the client's problem
- CUnderstanding the concerns of the client
- DUnderstanding the concerns of design professionals working on the project
104Once the consultants are retained, the project manager should inform the appropriate consultants about
- AAny applicable code requirements and design decisions that may have code implications
- BThe agree upon fee and scope of work
- CThe complete design of the project
- DClear methods of communication
105Which of the following are true regarding responsibility associated with the code compliance of consultant engineering drawings?
- AAlthough the project manager and design team are responsible for ensuring that the drawings and specifications conform to the applicable codes, the consultants are responsible for code compliance regarding their areas of work
- BBy signing their drawings, the engineering consultants become responsible for compliance with applicable codes and regulations
- CEach consultant is also responsible for the accurate production of their own drawings and specifications and checking their own documents for consistency
- DThe architect is the main consultant and is liable to the owner for the consultant's work
106When should reviewing and applying code requirements occur in the design process?
- ADuring Programming and Early Space Planning and should continue throughout the project
- BDuring Construction Documentation
- CDuring Design Development
- DDuring Schematic Design
107Which of the following is one of the best methods a Project Manager can use to improve coordination of code requirements for current and future projects?
- ACode Checklists
- BHire a Code Specialist consultant
- COne designated employee becomes a single source of responsibility for coordinating code requirements for all projects
108When should all preliminary information used in schematic design be verified for code compliance?
- ADesign Development
- BConstruction Documentation
- CQAQC
- DThird Party Reviews
109During design development, all preliminary information used in schematic design should be verified especially if changes are being made to:
- ASpace Plan
- BOccupancy Type
- COccupant Load
- DFloor Finishes
110The Project Manager assigns someone to check the basic exiting code requirements which includes:
- AQuantity of Exits
- BSeparation between Exits
- CTravel Distance
- DCommon Path of Egress Travel
- EExit Width
- FDead-End Corridors
- GDoor Swings
111For design elements that could affect the overall space plan or have significant cost implications if its often acceptable if very detailed code requirements are not verified and applied until later, during the construction document stage.
- ATrue
- BFalse
112Which of the following apply to the Project Notebook?
- AIs one of the most useful project management tools
- BProvides information for planning
- CProvides information for coordinating
- DProvides information for monitoring the job
113A project notebook can be modified to suite the unique needs of individual offices and project types but still should contain which of the following items?
- AGeneral Reference
- BContracts
- CFees and Schedules
- DProgramming
- EBudget
- FJob Communication
- GConstruction Administration
- HClose-out and Follow Up
114Which of the following should be included in the General Reference of the PM's Project Notebook?
- ANotebook Index
- BThe Project Directory (names, addresses, phone numbers of the client, consultants, contractors, regulatory agencies, major vendors and others)
- CThe Filing Index (names and code numbers of the office filing system for the job)
- DThe Owner-Architect Agreement
- EProject Summary
- FDetailed Schedule
115Which of the following should be included in the Contracts of the PM's Project Notebook?
- AOwner-Architect Agreement
- BArchitect-Consultant Agreements
- CWork Authorizations
- DProject Summary
116Which of the following should be included in the Fees and Schedule of the PM's Project Notebook?
- APreliminary Schedule
- BDetailed Schedule
- CTime Projections
- DFee Budgets
- ETask Assignments
- FFinancial Management Report Summaries
- GProject Summary
117Which of the following should be included in the Programming of the PM's Project Notebook?
- AGoal Statements
- BProgram or Program Summary
- CCode and Zoning Search
- DSpecial Equipment Needs
- EOther Special Needs
- FUtility Information
118Which of the following should be included in the Budget of the PM's Project Notebook?
- AOverall Project Budget
- BConstruction Budget
- CFurnishings Budget
- DOther Special Items
- EUpdates
- FFees
119Which of the following should be included in the Job Communication of the PM's Project Notebook?
- AMajor Correspondence
- BMeeting Minutes
- CTelephone and Email Logs
- DTransmittal Log
- EDesign Review Notes
- FWritten Client Approvals
120Which of the following should be included in the Construction Administration of the PM's Project Notebook?
- AShop Drawing/Sample Log
- BMinutes or Notes from Job Conferences and Site Visits
- CBulletins
- DChange Orders
- EField Orders
- FField Reports
- GTest and Site Observation Reports
- HApplications and Certificates for Payment
- ICommissioning Reports
- JPunch List
121Which of the following should be included in the Close-Out and Follow-Up of the PM's Project Notebook?
- APunch List
- BCertificate of Substantial Completion
- CSummary of Construction Costs
- DSummary of fee expenditures & other job-related costs
- ECommissioning reports
- FTesting and balancing reports
- GComments on completed job
- HConsultant Evalutations
- INotes on Follow-Up Visits
- JTest and Site Observation Reports
122Meetings are a necessity of any office, but they can also be large time wasters. Which of the following are some ways that PMs can make meetings more efficient?
- AEvery meeting should have a clearly stated purpose, an "Agenda," and be distributed in advance to all invitees
- BDon't schedule a meeting unless it is truly necessary
- CRequire that everyone turn of cell phones
- DSend a reminder email to all participants the day before and arrive early and start on time
- EIf a follow-up meeting is needed, set the date and time for it at the end of the meeting, and include this information in the meeting minutes
- FA conference call is often more productive than an in-person meeting
- GIf there is a lot to accomplish & the topics to be discussed are independent, arrange the meeting in shifts
- HOrganize your notes and prepare the minutes as soon after the meeting as possible
- IAppoint a team member to take notes or manage the computer & projector if the PM is leading the meeting
- JEstablish an ending time and stick to it, schedule meetings just before lunch or at the end of the workday, to encourage participants to keep them short, or use stand-up meetings to reduce the tendency of people to stay longer than necessary
123The best technique for taking meeting minutes is to use a template. Which of the following should be included in meeting minutes?
- ADecisions
- BAccomplishments
- CAction Items
- DThe Date and Time for a follow-up meeting if needed
- EThe Weather Conditions and Temperature if the meeting is held at a construction site
- FProject name, number, date, place of the meeting, time, people attending, and the subjects covered
- GFilled out sign in sheet by meeting participants that ensures that the email addresses and phone numbers for all participants have been recorded
- HA column for follow-up, including who is assigned to perform a task and by when
- IA Statement such as, "If there are any additions or corrections to these minutes, please notify this office within five days."
124Which of the following are important reasons to create and record meeting minutes?
- AImprove Communication
- BHelp the team avoid misunderstandings
- CProvide a written or electronic record should disputes or legal problems arise
125The construction administrator has returned from a visit to the construction site to review the project progress with the contractor's superintendent. While on site, the construction administrator and the superintendent note that metal conduit material stored on the site by the electrical subcontractor is located in an unsecured and unsafe area. How should the administrator respond?
- ACall the electrical subcontractor
- BInclude this observation in a written memo or report
- CStop the work and call the owner immediately
- DAssist the superintendent in moving the conduit to a safe location
126To curb the Project Perfection Syndrome of an office, the project manager should,
- AMake sure that everyone on the project team understands how much time is budgeted for each task and which tasks must be completed
- BAlways tell the project team that there is no or little remaining fee to cover the work, even if there is or isnt, so that they complete the task as quickly as possible
- CStop all work once the fee and time budgeted has run out
Information
- Description
- Quiz on Project Management - Project Management & Planning, created by Marita Rose on 01/24/2018.
- Author
- Marita Rose
- Language
- English
- Views
- 33
- Tags
- Rating
- No ratings yet Rate this quiz