The Deadbeats
After months of broken promises, partial payments, and general stupidity, the landlord had no choice but to evict the long term tenants that had become little more than squatters in his first rental property. As he surveyed the damage and pondered a mix of repairs an upgrades, he scoured the latest statistics on what different upgrades might be worth in terms of increased rent. Beautifully refinished wood floors could increase the monthly rent about $100 and an upgrade to the kitchen would fetch $80 per month. The garage door needed replacement, but even though it would receive daily use, it was almost an order qualifier, and wouldn't net more than $20 per month. The house had always suffered from lack of a back door&8211;you had to access the backyard through the garage, so taking out a window and replacing it with a safety door would cost $250 and add only $15 to the monthly rent. The garage door would cost $350, the kitchen update would cost $1000 if he went with granite, and the floor refinish job would cost $400 to rent the buffer and buy the chemicals. It wouldn't be easy doing these upgrades; the garage door would take a half week, the back door one week, the floors two weeks and the tile three weeks.
There was another way around these jobs though; instead of doing them himself, the landlord could always hire a professional in each field that could finish the job in half the time but would charge a pretty penny for that speed. Refinishing floors would cost $2700, upgrading the kitchen would cost $2500, replacing the back window with a door would cost $600, and installing a garage door opener would cost $350.
Suppose the landlord really wants the back door to be installed. For too long he has had to cut through the garage and he figures when he retires, this house will be a perfect downsize home for him to move into. How should the constraint for the back door be written if he uses the following scheme for decision variables?
- Ax5 - x6 ≤ 1
- Bx5 + x6 = 1
- Cx5 + x6 ≤ 1
- Dx5 - x6 = 1
2In a ________ integer model, all decision variables have integer solution values.
- Atotal
- B0-1
- Cmixed
- DAll of these
3
The Deadbeats
After months of broken promises, partial payments, and general stupidity, the landlord had no choice but to evict the long term tenants that had become little more than squatters in his first rental property. As he surveyed the damage and pondered a mix of repairs an upgrades, he scoured the latest statistics on what different upgrades might be worth in terms of increased rent. Beautifully refinished wood floors could increase the monthly rent about $100 and an upgrade to the kitchen would fetch $80 per month. The garage door needed replacement, but even though it would receive daily use, it was almost an order qualifier, and wouldn't net more than $20 per month. The house had always suffered from lack of a back door&8211;you had to access the backyard through the garage, so taking out a window and replacing it with a safety door would cost $250 and add only $15 to the monthly rent. The garage door would cost $350, the kitchen update would cost $1000 if he went with granite, and the floor refinish job would cost $400 to rent the buffer and buy the chemicals. It wouldn't be easy doing these upgrades; the garage door would take a half week, the back door one week, the floors two weeks and the tile three weeks.
There was another way around these jobs though; instead of doing them himself, the landlord could always hire a professional in each field that could finish the job in half the time but would charge a pretty penny for that speed. Refinishing floors would cost $2700, upgrading the kitchen would cost $2500, replacing the back window with a door would cost $600, and installing a garage door opener would cost $350.
The landlord uses the following scheme for decision variables:
What should the objective function be?
- AMin Z = 2700x1 + 400x2 + 2500x3 + 1000x4 + 600x5 + 250x6 + 350x7 + 400x8
- BMin Z = 2700x1 - 400x2 + 2500x3 - 1000x4 + 600x5 - 250x6 + 350x7 - 400x8
- CMax Z = 100x1 - 100x2 + 80x3 - 80x4 + 15x5 - 15x6 + 20x7 - 20x8
- DMax Z = 100x1 + 100x2 + 80x3 + 80x4 + 15x5 + 15x6 + 20x7 + 20x8
4Assume that we are using 0-1 integer programming model to solve a capital budgeting problem and xj = 1 if project j is selected and xj = 0, otherwise.
The constraint (x1 + x2 + x3 + x4 = 2) means that ________ out of the ________ projects must be selected.- Aexactly 2, 4
- Bexactly 1, 2
- Cat least 2, 4
- Dat most 1, 2
5
The Deadbeats
After months of broken promises, partial payments, and general stupidity, the landlord had no choice but to evict the long term tenants that had become little more than squatters in his first rental property. As he surveyed the damage and pondered a mix of repairs an upgrades, he scoured the latest statistics on what different upgrades might be worth in terms of increased rent. Beautifully refinished wood floors could increase the monthly rent about $100 and an upgrade to the kitchen would fetch $80 per month. The garage door needed replacement, but even though it would receive daily use, it was almost an order qualifier, and wouldn't net more than $20 per month. The house had always suffered from lack of a back door&8211;you had to access the backyard through the garage, so taking out a window and replacing it with a safety door would cost $250 and add only $15 to the monthly rent. The garage door would cost $350, the kitchen update would cost $1000 if he went with granite, and the floor refinish job would cost $400 to rent the buffer and buy the chemicals. It wouldn't be easy doing these upgrades; the garage door would take a half week, the back door one week, the floors two weeks and the tile three weeks.
There was another way around these jobs though; instead of doing them himself, the landlord could always hire a professional in each field that could finish the job in half the time but would charge a pretty penny for that speed. Refinishing floors would cost $2700, upgrading the kitchen would cost $2500, replacing the back window with a door would cost $600, and installing a garage door opener would cost $350.
The landlord uses the following scheme for decision variables:
Which of these constraints would not be appropriate for this scenario?
- A1x1 + 2x2 + 1.5x3 + 3x4 + 0.5x5 + 1x6 + 0.25x7 + 0.5x8 ≤ 4
- B2700x1 + 400x2 + 2500x3 + 1000x4 + 600x5 + 250x6 + 350x7 + 400x8 ≤ 3000
- Cx1, x2, x3, x4, x5, x6 , x7, x8 ≥ 0 and integer
- Dx3 + x4 = 1
6Due to increased sales, a company is considering building three new distribution centers (DCs) to serve four regional sales areas. The annual cost to operate DC 1 is $500 (in thousands of dollars). The cost to operate DC 2 is $600 (in thousands of dollars). The cost to operate DC 3 is $525 (in thousands of dollars). Assume that the variable cost of operating at each location is the same, and therefore not a consideration in making the location decision.
The table below shows the cost ($ per item) for shipping from each DC to each region.
The demand for region A is 70,000 units; for region B, 100,000 units; for region C, 50,000 units; and for region D, 80,000 units. Assume that the minimum capacity for the distribution center will be 500,000 units.
Assume that Xij = quantity shipped from distribution i to region j. i = 1,2,3 and j = 1, 2, 3, 4.
Assume that Yi = 0 or 1 where i = distribution center 1, 2 or 3.
- AX11 + X12 + X13 + X14 ≥ 500.
- BX11 + X12 + X13 + X14D + 500y1 ≤ 0.
- CX11 + X12 + X13 + X14 ≤ 500.
- DX11 + X12 + X13 + X14 - 500y1 ≤ 0.
7The Deadbeats
After months of broken promises, partial payments, and general stupidity, the landlord had no choice but to evict the long term tenants that had become little more than squatters in his first rental property. As he surveyed the damage and pondered a mix of repairs an upgrades, he scoured the latest statistics on what different upgrades might be worth in terms of increased rent. Beautifully refinished wood floors could increase the monthly rent about $100 and an upgrade to the kitchen would fetch $80 per month. The garage door needed replacement, but even though it would receive daily use, it was almost an order qualifier, and wouldn't net more than $20 per month. The house had always suffered from lack of a back door&8211;you had to access the backyard through the garage, so taking out a window and replacing it with a safety door would cost $250 and add only $15 to the monthly rent. The garage door would cost $350, the kitchen update would cost $1000 if he went with granite, and the floor refinish job would cost $400 to rent the buffer and buy the chemicals. It wouldn't be easy doing these upgrades; the garage door would take a half week, the back door one week, the floors two weeks and the tile three weeks.
There was another way around these jobs though; instead of doing them himself, the landlord could always hire a professional in each field that could finish the job in half the time but would charge a pretty penny for that speed. Refinishing floors would cost $2700, upgrading the kitchen would cost $2500, replacing the back window with a door would cost $600, and installing a garage door opener would cost $350.
The landlord ran the model in Excel and received the answer report contained in the table. Which of the following statements is correct?
- AThe rent will be $195 higher and the project will take 3.5 weeks to finish at a cost of $3700.
- BThe rent will be $180 higher and the project will take 2.5 weeks to finish at a cost of $3700.
- CThe rent will be $195 higher and the project will take 2.5 weeks to finish at a cost of $2900.
- DThe rent will be $180 higher and the project will take 3.5 weeks to finish at a cost of $2900.
8
The Deadbeats
After months of broken promises, partial payments, and general stupidity, the landlord had no choice but to evict the long term tenants that had become little more than squatters in his first rental property. As he surveyed the damage and pondered a mix of repairs an upgrades, he scoured the latest statistics on what different upgrades might be worth in terms of increased rent. Beautifully refinished wood floors could increase the monthly rent about $100 and an upgrade to the kitchen would fetch $80 per month. The garage door needed replacement, but even though it would receive daily use, it was almost an order qualifier, and wouldn't net more than $20 per month. The house had always suffered from lack of a back door&8211;you had to access the backyard through the garage, so taking out a window and replacing it with a safety door would cost $250 and add only $15 to the monthly rent. The garage door would cost $350, the kitchen update would cost $1000 if he went with granite, and the floor refinish job would cost $400 to rent the buffer and buy the chemicals. It wouldn't be easy doing these upgrades; the garage door would take a half week, the back door one week, the floors two weeks and the tile three weeks.
There was another way around these jobs though; instead of doing them himself, the landlord could always hire a professional in each field that could finish the job in half the time but would charge a pretty penny for that speed. Refinishing floors would cost $2700, upgrading the kitchen would cost $2500, replacing the back window with a door would cost $600, and installing a garage door opener would cost $350.
Obviously if the model wants to upgrade the kitchen, it should be done by either the landlord or a subcontractor. As he creates the IP model, the landlord wants to leave the choice of whether to actually upgrade the kitchen up to the optimization algorithm. How should this constraint be written if he uses the following scheme for decision variables?
- Ax3 + x4 ≤ 1
- Bx3 + x4 = 1
- Cx3 - x4 = 1
- Dx3 - x4 ≤ 1
9If the solution values of a linear program are rounded in order to obtain an integer solution, the solution is:
- Aalways feasible.
- Balways optimal and feasible.
- Csometimes optimal and feasible.
- Dnever optimal and feasible.
10Binary variables are:
- Aany integer value.
- Bany negative integer value.
- Cany continuous value.
- D0 or 1 only.
11If a maximization linear programming problem consists of all less-than-or-equal-to constraints with all positive coefficients and the objective function consists of all positive objective function coefficients, then rounding down the linear programming optimal solution values of the decision variables will ________ result in a(n) ________ solution to the integer linear programming problem.
- Aalways, non-optimal
- Balways, optimal
- Cnever, non-optimal
- Dsometimes, optimal
12The Cruise
Their cruise would port out of New Orleans and promised seven days with a panoply of excursions in Jamaica, Cozumel, and Grand Cayman. A list of excursions at each site and key features of each appear in the table. The excursions were all day affairs, so it was possible to engage in only one per port. The cruise ship sailed at night and docked at each of these three ports at the crack of dawn. By dinner time, the ship was on its way to the next port and next set of excursions. The couple was energetic and active for a pair of 52 year-olds., and while enjoying an upper middle class lifestyle, they didn't want to spend money on excursions that might be better spent on tacky souvenirs. The couple therefore budgeted $250 for the excursions&8211;the prices shown are per couple, so for example, the $60 will pay for both of them to fill up on jerk chicken and mannish water.
For each of the duplicate excursions (e.g., snorkeling is offered in all three ports), the couple researched the quality of the activity and ranked the excursion among the available alternatives, with higher numbers indicating better quality. Thus, snorkeling in Jamaica is better than in Cozumel, and snorkeling in Cozumel is better than in Grand Cayman. For the unique experiences, i.e., the turtle farm, the default rating was the a 3.
What is an appropriate objective function for this vacation?
- AMax Z = JS + JP + JH + JL + CS + CP + CH + CL + CTe + GS + GP + GH + GL + GTu
- BMin Z = 100JS + 95JP + 120JH + 60JL + 110CS + 55CP + 70CH + 90CL + 130CTe + 90GS + 60GP + 110GH + 130GL + 95GTu
- CMax Z = 3JS + 1JP + 2JH + 3JL + 2CS + 3CP + 1CH + 2CL + 3CTe + 1GS + 2GP + 3GH + 1GL + 3GTu
- DMin Z = 3JS + 1JP + 2JH + 3JL + 2CS + 3CP + 1CH + 2CL + 3CTe + 1GS + 2GP + 3GH + 1GL + 3GTu
13If we are solving a 0-1 integer programming problem, the constraint x1 + x2 ≤ 1 is a ________ constraint.
- Aconditional
- Bcorequisite
- Cmutually exclusive
- Dmultiple-choice
14Companies A, B, and C supply components to three plants (F, G, and H) via two crossdocking facilities (D and E). It costs $4 to ship from D regardless of final destination and $3 to ship to E regardless of supplier. Shipping to D from A, B, and C costs $3, $4, and $5, respectively, and shipping from E to F, G, and H costs $10, $9, and $8, respectively. Suppliers A, B, and C can provide 200, 300 and 500 units respectively and plants F, G, and H need 350, 450, and 200 units respectively. Crossdock facilities D and E can handle 600 and 700 units, respectively. Logistics Manager, Aretha Franklin, had previously used "Chain of Fools" as her supply chain consulting company, but now turns to you for some solid advice.
How many constraints are required to model this as a linear program?- A10
- B9
- C8
- D12
15Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
What is an appropriate objective function for this scenario?
- A

- B

- C

- D

- A
16Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
David is qualified to teach Management Science, but has misplaced his slide rule and doesn't feel he can complete the necessary calculations if he is assigned to teach it next semester. Which of these constraints would ensure that he isn't the instructor?
- ASM + GM + TM + DM ≤ 1
- BDM = 0
- CDI + DP + DQ + DC + DL ≥ 2
- DDI + DP + DQ + DC + DL + DM ≤ 3
17Which of the following are assumptions or requirements of the transportation problem?
- AGoods are the same, regardless of source.
- BThere must be multiple sources
- CThere must be multiple destinations.
- DThere must be multiple routes between each source and each destination.
18In a balanced transportation model where supply equals demand:
- Aall constraints are inequalities.
- Ball constraints are equalities.
- Cnone of the constraints are equalities.
- Dnone of the constraints are inequalities.
19Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
Copied below is a portion of the answer report that shows the status of the variable cells related to the faculty assignment. Which of these statements is consistent with the answer report?
- Atillegg til spm.

- BTim is assigned to teach two courses.
- CSaba is assigned to teach two courses.
- DDavid is assigned to teach Introduction to Operations.
- EGeoff is assigned to teach Introduction to Operations.
- Atillegg til spm.
20In a transshipment problem, items may be transported:
- Afrom destination to destination.
- Bfrom one transshipment point to another.
- Cdirectly from sources to destinations.
- DAll of these.
21In the linear programming formulation of a transportation network:
- Athere is one variable for each arc.
- Bthere is one constraint for each node.
- Cthe sum of variables corresponding to arcs out of an source node is constrained by the supply at that node.
- DAll of these.
22In a transportation problem, items are allocated from sources to destinations:
- Aat a minimum cost.
- Bat a minimum revenue.
- Cat a minimum profit.
- Dat a maximum cost.
23The linear programming model for a transportation problem has constraints for supply at each ________ and ________ at each destination.
- Ademand, source
- Bsource, destination
- Csource, demand
- Ddestination, source
24Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
- AAddition to problem.

- BTim is assigned to teach two courses.
- CGeoff is assigned to teach Introduction to Operations.
- DDavid is assigned to teach Management Science.
- ESaba is assigned to teach two courses.
- AAddition to problem.
25Companies A, B, and C supply components to three plants (F, G, and H) via two crossdocking facilities (D and E). It costs $4 to ship from D regardless of final destination and $3 to ship to E regardless of supplier. Shipping to D from A, B, and C costs $3, $4, and $5, respectively, and shipping from E to F, G, and H costs $10, $9, and $8, respectively. Suppliers A, B, and C can provide 200, 300 and 500 units respectively and plants F, G, and H need 350, 450, and 200 units respectively. Crossdock facilities D and E can handle 600 and 700 units, respectively. Logistics Manager, Aretha Franklin, had previously used "Chain of Fools" as her supply chain consulting company, but now turns to you for some solid advice.
Which of these constraints allows for some inventory to be held at one of the crossdock facilities?- AAD + BD + CD - DF - DG - DH ≥ 0
- BAD + BD + CD + DF + DG + DH = 600
- CAD + BD + CD - DF - DG - DH = 600
- DAD + BD + CD = DF - DG - DH = 600
26Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
Which constraint ensures that Introduction to Operations is offered according to the scenario?
- ASI + GI + TI + DI ≥ 6
- BSI + GI + TI + DI ≤ 6
- CSI + SP + SQ + SC + SL + SM ≤ 6
- DSI + SP + SQ + SC + SL + SM ≥ 6
27Companies A, B, and C supply components to three plants (F, G, and H) via two crossdocking facilities (D and E). It costs $4 to ship from D regardless of final destination and $3 to ship to E regardless of supplier. Shipping to D from A, B, and C costs $3, $4, and $5, respectively, and shipping from E to F, G, and H costs $10, $9, and $8, respectively. Suppliers A, B, and C can provide 200, 300 and 500 units respectively and plants F, G, and H need 350, 450, and 200 units respectively. Crossdock facilities D and E can handle 600 and 700 units, respectively. Logistics Manager, Aretha Franklin, had previously used "Chain of Fools" as her supply chain consulting company, but now turns to you for some solid advice.
Which of these is not an element of the objective function?- A600D
- B3CE
- C9EG
- D4DF
28Semester Prep
The department chair reviewed last year's schedule, the degree requirements for the ever popular Operations and Supply Chain major, and the emails that had drifted into her mailbox over the last week. Naturally, every professor in the department had his own pet course and wanted to maintain control of it while avoiding 8 a.m. classes at all costs. In an effort to placate the senior faculty members of the department, the chair sent an email asking them to supply the prep time for each of the classes they were qualified to teach, promising to assign them the least taxing schedule possible. Each of her department members had to teach at least two courses, but no more than three. The elective courses, Project Management, Quality Management, Control and Planning, Logistics, and Management Science each had to be offered once and the department needed to offer at least six sections of the Introduction to Operations class. The prep times each professor estimated for each course appear in the table below.
Which constraint is appropriate for this scenario?
- ASI + SP + SQ + SC + SL + SM ≤ 3
- BSM + GM + TM + DM ≥ 1
- CSI + GI + TI + DI ≤ 6
- DDI + DP + DQ + DC + DL + DM = 2
29If we wanted to represent an office layout as a network flow problem, which of the following would be represented as a branch?
- AOffices
- BHeating and ventilation systems
- CWaiting areas
- DComputer rooms
30If we wanted to represent an urban transportation system as a network flow problem, which of the following would be represented as nodes?
- AStreet intersections
- BStreets
- Cpedestrian right of ways
- Drailway lines
31In a network modeling problem, the linear programming decision variables are given by:
- ASource node
- BNetwork nodes
- CNetwork branches
- DSink node
32In a network flow model, a directed branch:
- Ais a branch in which flow is possible in only one direction.
- Bis a branch with a positive distance value.
- Cis a branch on which the flow capacity is exhausted.
- Dis a branch in which flow is not possible in either direction.
33Comedy Pasture
A horse and two llamas are discussing the key areas of their domain on a lazy summer afternoon. The llamas favor the pond and shade and like to browse the fruit trees and oaks on the property, making their way to the barn only when their owner favors them with some oats. The horse prefers to graze the grass and hay for food and drink from the pond but will race up to the barn when the owner is handing out oats up there. Between the three of them, they have stepped off the distances between many of these key points several times and believe that they have developed an accurate map, shown below. As incredible as it may seem, neither the horse nor the llamas have had any training in management science, which is where you come in.
The horse decides that a small system of trails would be perfect for connecting his points of interest, the Grass, Barn, Hay and Pond along with the Oak. What is the minimal total path length for this construction project?
- A270
- B290
- C280
- D295
34Comedy Pasture
A horse and two llamas are discussing the key areas of their domain on a lazy summer afternoon. The llamas favor the pond and shade and like to browse the fruit trees and oaks on the property, making their way to the barn only when their owner favors them with some oats. The horse prefers to graze the grass and hay for food and drink from the pond but will race up to the barn when the owner is handing out oats up there. Between the three of them, they have stepped off the distances between many of these key points several times and believe that they have developed an accurate map, shown below. As incredible as it may seem, neither the horse nor the llamas have had any training in management science, which is where you come in.
Which of these routes for the horse is actually the shortest between the pair of nodes?
- AFruit - Shade = 165'
- BGrass - Pond = 190'
- CBarn - Pond = 200'
- DFruit - Hay = 160'
35Comedy Pasture
A horse and two llamas are discussing the key areas of their domain on a lazy summer afternoon. The llamas favor the pond and shade and like to browse the fruit trees and oaks on the property, making their way to the barn only when their owner favors them with some oats. The horse prefers to graze the grass and hay for food and drink from the pond but will race up to the barn when the owner is handing out oats up there. Between the three of them, they have stepped off the distances between many of these key points several times and believe that they have developed an accurate map, shown below. As incredible as it may seem, neither the horse nor the llamas have had any training in management science, which is where you come in.
Llamas are pack animals and the owner occasionally has them tote supplies from the fruit trees down to the hay stand. What is the shortest route between the two?
- A155'
- B150'
- C160
- D165
36Comedy Pasture
A horse and two llamas are discussing the key areas of their domain on a lazy summer afternoon. The llamas favor the pond and shade and like to browse the fruit trees and oaks on the property, making their way to the barn only when their owner favors them with some oats. The horse prefers to graze the grass and hay for food and drink from the pond but will race up to the barn when the owner is handing out oats up there. Between the three of them, they have stepped off the distances between many of these key points several times and believe that they have developed an accurate map, shown below. As incredible as it may seem, neither the horse nor the llamas have had any training in management science, which is where you come in.
The llamas decide that a small system of trails would be perfect for connecting their points of interest, the Fruit, Barn, Hay, Shade, Pond and the Oak. What is the minimal total path length for this construction project?
- A270'
- B265'
- C275'
- D260'
37The shipping company manager wants to determine the best routes for the trucks to take to reach their destinations. This problem can be solved using the:
- AShortest route solution technique.
- BMinimal spanning tree solution method.
- CMinimal flow solution method,
- DMaximal flow solution method.
38Determine the maximal flow through the network in Figure 4. Assume that all branches are directed branches.

- A13
- B16
- C10
- D11
Information
- Description
- Quiz on Management Science test 2, created by Isak Reinhardsen on 18/03/2018.
- Author
- Isak Reinhardsen
- Language
- English
- Views
- 32
- History
- Created on 18 Mar 2018 · updated on 21 Mar 2018
- Rating
- No ratings yet Rate this quiz