  1. 1​Frito-Lay uses aggregate planning to match capacity with demand because of the​ __________ associated with its specialized processes.
    1. Alow variable cost and high fixed cost
    2. Bhigh variable cost and high fixed cost
    3. Clow variable cost and low fixed cost
    4. Dhigh variable cost and low fixed cost
    5. ENone of the above.
  2. 2The typical time horizon for aggregate planning is
    1. A3 to 18 months.
    2. Bover 5 years
    3. Cless than a month
    4. Dup to 3 months.
    5. Eover one year.
  3. 3Aggregate planning is capacity planning for
    1. Athe intermediate range.
    2. Bthe long range.
    3. Ctypically three or more years
    4. Dthe short range.
    5. Etypically one to three months.
  4. 4The objective of aggregate planning is to meet demand while​ __________ over the planning period.
    1. Aminimizing cost
    2. Bminimizing fixed cost
    3. Cminimizing stock out
    4. Dmaximizing service level
    5. EAll of the above.
  5. 5Which of the following is not one of the four things needed for aggregate​ planning?
    1. Aa mathematical model that will minimize costs over the intermediate planning period
    2. Ba logical overall unit for measuring sales and output
    3. Ca method for determining​ costs, such as​ hiring, layoffs, and inventory​ costs, associated with production schedules
    4. Dan aggregate demand forecast for an intermediate planning period
    5. EAll of these are needed for aggregate planning.
  6. 6Planning tasks associated with​ loading, sequencing,​ expediting, and dispatching typically fall under
    1. Ashort-range plans.
    2. Bstrategic planning.
    3. Clong-range plans.
    4. D​intermediate-range plans.
    5. Emission-related planning.
  7. 7The planning tasks associated with​ staffing, production,​ inventory, and​ sub-contracting levels typically fall under
    1. A​intermediate-range plans.
    2. Bstrategic planning.
    3. Cdemand options.
    4. Dshort-range plans.
    5. E​long-range plans.
  8. 8Which of the following statements about aggregate planning is true​?
    1. AOvertime/idle time is a way of manipulating product or service demand.
    2. BWork station loading and job assignments are examples of aggregate planning.
    3. CAdvertising/promotion is a way of manipulating product or service supply.
    4. DAll of the above are true.
    5. EAggregate planning uses the adjustable part of capacity to meet production requirements.
  9. 9Which of the following statements about aggregate planning is false​?
    1. AAggregate planning produces a plan detailing which products are made and in what quantities.
    2. BYield management is a way of manipulating product or service demand.
    3. C​Hiring, layoffs,​ overtime, and subcontracting are methods of manipulating capacity.
    4. DThe transportation method is an optimizing technique for aggregate planning.
    5. EAggregate planning uses the adjustable part of capacity to meet production requirements.
  10. 10Top executives tend to focus their attention on which type of​ forecasts?
    1. A​long-range
    2. Bshort-range
    3. C​medium-range
    4. Dweather
    5. Ethe forecast for the next​ day's absentee levels

Information

Description
OM- Final Quiz on OM Chp 13- Final, created by Shelby Reitz on 20/04/2018.
Language
English
Views
0
History
Created on 20 Apr 2018 · updated on 2 May 2018
Tags
om- final
Rating
No ratings yet
Rate this quiz
Rate this quiz

More on Aggregate Planning and Sales and Operations Planning

Feedback

What is it about?

What do you think of the new look?

How do you like it?