Procure to pay basics
This quiz has a time limit, so it opens in the usual player.
Questions in this quiz (10)
1A purchase order is a formal demand to a vendor for supplying particular goods or services under the negotiated conditions stated in the purchase order. Which of the following statement is true regarding purchase orders?
- AA purchase order cannot be created without reference to a purchase requisition
- BA purchase order can be created without reference to a purchase requisition
- CA purchase order must be created with reference to a request for quotation
- DVendor/Supplier code is not mandatory for creating purchase order
2There are 3 suppliers A, B, C. We have to order a item such that it arrives before 30th July 2018. The quotations provided by A, B, C are as follows:
A: Price=1000, Del Date=30th July 2018
B: Price=1200, Del Date=29th July 2018
C: Price=1000, Del Date=29th July 2018
Which Vendor(s) can receive a purchase order from us?- AA and C
- BOnly C
- COnly A
- DB and C
- EA and B
3There are a total of 1000 items in the inventory with a moving average cost of 5 rs. A goods receipt is made for 200 items, each costing 8 rs. What will be the final MAC (moving average cost) of the inventory?
- A7.5
- B7
- C5.5
- D5
4There are a total of 1000 items in the inventory with a moving average cost of 5 rs. A goods receipt is made for 200 items, each costing 8 rs. Then a sale is done for total 300 quantity each with selling price of 7. What will be the final MAC (moving average cost) of the inventory?
- A5.5
- B5
- C7.5
- D6
5After doing goods receipt entry, which all updates will happen in the ERP system?
- AInventory, G/L accounts, Purchase order, requisition, material cost
- BInventory, G/L accounts, Purchase order, quotation, requisition, material cost
- CInventory, G/L accounts, Purchase order, material cost
- DInventory, G/L accounts, material cost
6Which of the options given below are examples of payment terms with supplier? (you can choose multiple options)
- APayment expected before 30 days
- BReceive 2% payment on paying before 10 days
- Cpayment in advance
- Drecurring invoices
7In determination of requirements stage, how can purchase requisitions be created?
- AManually
- BManually or through MRP run
- CAutomatically
- DOnly through MRP run
8What is release strategy in a purchase order?
- AStrategy for automatic determination of quantities in a PO
- BStrategy for automatic determination of prices in a PO
- CConfiguration to select vendor in a PO
- DApproval mechanism of a PO
9During invoice confirmation, which account gets debited?
- AGR/IR Clearing account
- BInventory account
- CAccounts Payable-Vendor
- DCash in Bank
10After determination of requirements, generally what is the next step in procure to pay cycle?
- AVendor selection
- BSource Determination
- CPO creation
- DNone of the above
Information
- Description
- Quiz on Procure to pay basics, created by shashank sachan on 16/07/2018.
- Author
- shashank sachan
- Language
- English
- Views
- 2
- Tags
- Rating
- No ratings yet Rate this quiz
More on Purchase Orders and Procure-to-Pay