Help shape GoConqr. What should we add next?

Quiz

Confidence Quiz #2 - Module 4 & 5

Victoria Burton 20 questions

Take the quiz

Questions in this quiz (20)

  1. 1You are trying to improve the quality of estimates on your project. What is one think you can do?
    1. ADo not document assumptions
    2. BHave one person do the estimating
    3. CHave all estimates reviewed
    4. DUse a new estimating method
  2. 2Your project is over budget and you are trying to determine the cause. You are reviewing the estimates provided by team members to create the cost baseline. Fortunately, the estimates are by work package and you have the spreadsheet that was used, but it is hard to figure out what is going on, as all the team members who provided the estimates have left. What is the one thing you wish was provided with the estimate?
    1. ALink to strategy
    2. BWho approved the estimates
    3. CLink to requirements
    4. DList of assumptions
  3. 3You have just finished gathering the project requirements and you are building the WBS. There is still a lot more planning to do, including assigning resources. However, the project sponsor wants an update on the budget to see where things stand. What level of accuracy is required?
    1. ARough order of magnitude
    2. BDefinitive
    3. CBudget
    4. DDetail
  4. 4You have received a high level proposal from your boss for a new project. The project looks very exciting but there are not many details on what is involved. There are some elements of the project you have done before, but many you have not. What level of accuracy is required?
    1. ARough order of magnitude
    2. BPreliminary
    3. CBudget
    4. DDetail
  5. 5You are a renovation contractor, and a new client has asked you to estimate the cost of replacing their existing bathroom with a new one. The client has not given you any indication of what they want, except the existing bathroom be gone! You have done five bathroom renovations recently. The historical costs from 5 projects are below. Which estimate should you provide the client?Image for question 5
    1. A$5,500
    2. B$10,000
    3. C$5,700
    4. D$4,000 to $10,000
  6. 6You are reviewing the price you and your team have developed for a buyer. What are the items you should consider?
    1. AThe best estimate to create the product or service
    2. BWhat you think will win the bid
    3. CCost, risk, and profit
    4. DThe amount of money the company needs to survive
  7. 7You have been working with your team to develop a detailed estimate on the project. The team has completed the estimates and the total is $20,000 for labour and $10,000 for material. Your organization has a 20% overhead on labour and adds a further 10% on all project costs (excluding any contingency). In addition, the results from the risk analysis show that you need a 15% contingency on the total cost. What is the budget for your project, to the nearest thousand?
    1. A$42,000
    2. B$37,000
    3. C$43,000
    4. D$41,000
  8. 8You are reviewing the estimate from your team for an activity of a 2 week duration for 2 people working 8 hour days, giving an effort of 160 hours. The estimates look a little optimistic. You check with your team and they did not take into account availability and productivity. In your experience, the typical availability is 83% and productivity is 0.8. What should the estimate be?
    1. ACannot be determined
    2. BEffort: 200 hours, Duration: 3 weeks
    3. CEffort: 192 hours, Duration: 3 weeks
    4. DEffort: 200 hours, Duration: 6 weeks
  9. 9You have started to assign resources to the activities on your project schedule and the end date for the project, which was before the constraint, has now moved past the constraint date. What should you review to see why this has happened?
    1. ARisk responses
    2. BLearning curve
    3. CAssumptions
    4. DResource calendars
  10. 10In reviewing the schedule with your team, you identified an opportunity to introduce 5 days of overlap between activities A and B. Activity A occurs first. How would you show this overlap on the schedule?
    1. AActivity A has a dependency with Activity B of Finish to Start with a 5 day lag
    2. BActivity B has a dependency with Activity A of Finish to Start with a 5 day lag
    3. CActivity B has a dependency with Activity A of Finish to Start with a 5 day lead
    4. DActivity A has a dependency with Activity B of Finish to Start with a 5 day lead

Information

Description
Quiz on Confidence Quiz #2 - Module 4 & 5, created by Victoria Burton on 06/03/2019.
Language
English
Views
3
Rating
No ratings yet
Rate this quiz
Rate this quiz

More on Cost Estimation

Feedback

What is it about?

What should we add next?