Confidence Quiz #2 - Module 4 & 5
Create a free account to finish this quiz
Save your progress and see your final score.
Already have an account? Sign in
Questions in this quiz (20)
1You are trying to improve the quality of estimates on your project. What is one think you can do?
- ADo not document assumptions
- BHave one person do the estimating
- CHave all estimates reviewed
- DUse a new estimating method
2Your project is over budget and you are trying to determine the cause. You are reviewing the estimates provided by team members to create the cost baseline. Fortunately, the estimates are by work package and you have the spreadsheet that was used, but it is hard to figure out what is going on, as all the team members who provided the estimates have left. What is the one thing you wish was provided with the estimate?
- ALink to strategy
- BWho approved the estimates
- CLink to requirements
- DList of assumptions
3You have just finished gathering the project requirements and you are building the WBS. There is still a lot more planning to do, including assigning resources. However, the project sponsor wants an update on the budget to see where things stand. What level of accuracy is required?
- ARough order of magnitude
- BDefinitive
- CBudget
- DDetail
4You have received a high level proposal from your boss for a new project. The project looks very exciting but there are not many details on what is involved. There are some elements of the project you have done before, but many you have not. What level of accuracy is required?
- ARough order of magnitude
- BPreliminary
- CBudget
- DDetail
5You are a renovation contractor, and a new client has asked you to estimate the cost of replacing their existing bathroom with a new one. The client has not given you any indication of what they want, except the existing bathroom be gone! You have done five bathroom renovations recently. The historical costs from 5 projects are below. Which estimate should you provide the client?

- A$5,500
- B$10,000
- C$5,700
- D$4,000 to $10,000
6You are reviewing the price you and your team have developed for a buyer. What are the items you should consider?
- AThe best estimate to create the product or service
- BWhat you think will win the bid
- CCost, risk, and profit
- DThe amount of money the company needs to survive
7You have been working with your team to develop a detailed estimate on the project. The team has completed the estimates and the total is $20,000 for labour and $10,000 for material. Your organization has a 20% overhead on labour and adds a further 10% on all project costs (excluding any contingency). In addition, the results from the risk analysis show that you need a 15% contingency on the total cost. What is the budget for your project, to the nearest thousand?
- A$42,000
- B$37,000
- C$43,000
- D$41,000
8You are reviewing the estimate from your team for an activity of a 2 week duration for 2 people working 8 hour days, giving an effort of 160 hours. The estimates look a little optimistic. You check with your team and they did not take into account availability and productivity. In your experience, the typical availability is 83% and productivity is 0.8. What should the estimate be?
- ACannot be determined
- BEffort: 200 hours, Duration: 3 weeks
- CEffort: 192 hours, Duration: 3 weeks
- DEffort: 200 hours, Duration: 6 weeks
9You have started to assign resources to the activities on your project schedule and the end date for the project, which was before the constraint, has now moved past the constraint date. What should you review to see why this has happened?
- ARisk responses
- BLearning curve
- CAssumptions
- DResource calendars
10In reviewing the schedule with your team, you identified an opportunity to introduce 5 days of overlap between activities A and B. Activity A occurs first. How would you show this overlap on the schedule?
- AActivity A has a dependency with Activity B of Finish to Start with a 5 day lag
- BActivity B has a dependency with Activity A of Finish to Start with a 5 day lag
- CActivity B has a dependency with Activity A of Finish to Start with a 5 day lead
- DActivity A has a dependency with Activity B of Finish to Start with a 5 day lead
11In which organizational structure does a project team member have the best chance of completing their work package on time?
- AWeak matrix
- BBalanced matrix
- CFunctional
- DProject base
12You develop a small website. In discussing the project with the team leads and accounting, you obtained the information in the table below. What is your cost estimate?

- A$7,000
- B$6,000
- C$7,500
- D$6,500
13You are meeting with your team to develop an estimate to implement a new software application. After much discussion, the team agrees that it will most likely take 12 weeks. However, a number of members mentioned some potential problems, and if those occur it could take 26 weeks to complete the work. One the other hand, a couple of team members figures that if everything goes really well, it could be done in 20 days. What is your estimate?
- A12 weeks
- B14 weeks
- C13 weeks
- D26 weeks
14Unfortunately, you have a number of part-time resources on your project. You have tried to avoid this, but given the skills you need on your project, it cannot be avoided. When scheduling the part-time resources, what is one thing you should try to do?
- AAssigning multiple tasks to each resource at one time
- BKeeping each resource for as little time as possible
- CAssigning each resource to one task at a time
- DAssigning multiple resources to one task at a time
15You have been watching how one of your team members has approached completing their work package. This person has 4 weeks to complete the work package. The first couple of weeks there was not much focus, but in the last week, the team member was very focused and worked extra hours. What were you observing?
- APadding
- BStudent Syndrome
- CParkinson's Law
- DMurphy's Law
16What a frustrating meeting. You were reviewing your proposed budget with finance and you discovered that you had missed some significant costs. The good news is that the finance staff showed you how to calculate the costs and you can do it quickly; the bad news is you are going to have to explain to your boss. What cost did you miss?
- AProfit
- BOverhead costs
- CProject management
- DLabour costs
17You are reviewing the resource profile of your project and you notice that some of the key resources are over allocated on certain days, but when you look at the schedule by week, they are still over-allocated, but only by an hour or two. What should you do?
- ADo nothing, the staff can figure it out
- BMove activities with float to resolve the overallocation
- CLengthen the schedule to remove over-allocation
- DAdjust the duration of the activities to remove the over-allocation
18What is the duration to complete the six activities below?

- A16 days
- B12 days
- C10 days
- D9 days
19One of your colleagues has just been promoted. You are having a meeting to review the new project you colleague has just started. Your colleague starts off telling you that you have a great team, but the project should have started a month ago. Which schedule model did your colleague use?
- ARolling Wave
- BBackward schedule
- CCPM
- DAgile
20You are working with the project team to size and place the buffers in your schedule. Your team has identified several critical points in the network diagram. What type of butters should you place at those critical points?
- AFeeding
- BSafety
- CProject
- DResource
Information
- Description
- Quiz on Confidence Quiz #2 - Module 4 & 5, created by Victoria Burton on 06/03/2019.
- Author
- Victoria Burton
- Language
- English
- Views
- 3
- Rating
- No ratings yet Rate this quiz