Construction Project Controls Final Exam Study

Alexander Afonso 32 questions

Take the quiz

Questions in this quiz (32)

  1. 1Which of the following is of most use to the construction superintendent and foremen for planning daily requirements as to labor, materials, and equipment?
    1. AThe baseline construction schedule
    2. BThe preliminary construction schedule
    3. CThe updated schedule
    4. DThe two week look ahead schedule
    5. EThe master schedule
  2. 2Which of the following is used to document how a project was actually carried out from start to finish?
    1. AThe master program schedule
    2. BThe baseline construction schedule
    3. CThe recovery schedule
    4. DThe impact schedule
    5. EThe as-built schedule
  3. 3A GC has filed for an extension of time based on a claim that the architect delayed a decision on a submittal by two weeks, causing the project to be late. The owner claims that the project is two weeks late because the GC mismanaged the subcontractors. What type of schedule would be used to support or refute the GC's claim?
    1. AThe master program schedule
    2. BThe baseline construction schedule
    3. CThe impact schedule
    4. DThe recovery schedule
    5. EThe current schedule
  4. 4There are many ways to display a construction schedule. Consider a mid or high rise building where the sequence of activities on each floor is the same once the steel frame is erected. Which of the following methods is most effective in displaying the scheduling of these activities in the least amount of space?
    1. AGantt Chart
    2. BPrecedence diagram
    3. CArrow diagram
    4. DMatrix diagram
    5. EAll of the above would be effective
  5. 5Which of the following schedules is usually presented at a summary level?
    1. AThe master program schedule
    2. BThe baseline construction schedule
    3. CThe three week look ahead schedule
    4. DThe recovery schedule
    5. EThe current construction schedule
  6. 6When a resource analysis is undertaken, which step in the process involves totaling up the demand for a given resource for all activities running during each time period?
    1. AResource loading
    2. BResource aggregation
    3. CResource availability analysis
    4. DResource leveling
    5. EResource allocation
  7. 7When a resource availability analysis is done, one starts by looking at the resource requirement of the early start schedule.
    1. ATrue
    2. BFalse
  8. 8When a schedule is said to be "resource driven", an assumption is made that all needed resources will be available in sufficient quantity to meet the requirements of the early start schedule.
    1. ATrue
    2. BFalse
  9. 9Another phrase used to describe a resource histogram is "resource profile".
    1. ATrue
    2. BFalse
  10. 10When construction time and costs are monitored, the difference between planned performance and actual performance is called variance.
    1. ATrue
    2. BFalse

Information

Description
Construction Management Quiz on Construction Project Controls Final Exam Study, created by Alexander Afonso on 20/04/2019.
Language
English
Views
10
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?