1The probability that a risk event will occur is higher during the initial stages of a project.
- ATrue
- BFalse
2Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.
- ATrue
- BFalse
3Risk management is a reactive approach that is designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized.
- ATrue
- BFalse
4One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.
- ATrue
- BFalse
5The project being delayed is an example of a major risk that should be assessed.
- ATrue
- BFalse
6The first step in the risk management process is risk assessment.
- ATrue
- BFalse
7A risk profile is a list of questions that have been developed and refined from previous, similar projects.
- ATrue
- BFalse
8The risk identification process should be limited to just the core project team.
- ATrue
- BFalse
9While a "can do" attitude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification.
- ATrue
- BFalse
10Responses to all identifiable risks should be a top priority for the project manager.
- ATrue
- BFalse
11When considering risk value, the lower the value, the higher the level of risk.
- ATrue
- BFalse
12If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary.
- ATrue
- BFalse
13Adopting proven technology instead of experimental technology is an example of mitigating a risk.
- ATrue
- BFalse
14A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives.
- ATrue
- BFalse
15Performance bonds, warranties, and guarantees are financial instruments used to share risk.
- ATrue
- BFalse
16Fixed-price contracts are an example of transferring risk from an owner to a contractor.
- ATrue
- BFalse
17When developing a response to a risk by scheduling outdoor work in the summer, investing in up-front safety training, or choosing high-quality materials, these are examples of retaining a risk.
- ATrue
- BFalse
18Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.
- ATrue
- BFalse
19Change management systems involve reporting, controlling, and recording changes to the project baseline.
- ATrue
- BFalse
20Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.
- ATrue
- BFalse
21Contingency funding is made up of budget reserves and management reserves.
- ATrue
- BFalse
22Although most risks are presented as something not desirable, there can also be desirable risks called Opportunities.
- ATrue
- BFalse
23Opportunities identified within a project are treated very differently from risks.
- ATrue
- BFalse
24Having an environment where identified risks are treated professionally will lead to better control of risks.
- ATrue
- BFalse
Information
- Description
- Quiz on CH 7 TF, created by shamuz ALI on 04/11/2019.
- Author
- shamuz ALI
- Language
- English
- Views
- 1
- Rating
- No ratings yet Rate this quiz