BCM BOK2

Description

BCM BOK2
dabbler c
Quiz by dabbler c, updated more than 1 year ago
dabbler c
Created by dabbler c almost 4 years ago
12
0

Resource summary

Question 1

Question
[blank_start]Residual Risk[blank_end] is the [blank_start]remaining[blank_end] risk which cannot be defined in more detail after elimination or inclusion of all conceivable quantified risks in a risk consideration. Residual risk is the level of uncontrolled risk remaining after the risk treatment.
Answer
  • remaining
  • total
  • Residual Risk
  • Risk Acceptance
  • Risk Treatment
  • Risk Tolerance

Question 2

Question
[blank_start]Risk Acceptance[blank_end] is to make an informed decision to accept the [blank_start]likelihood[blank_end] and [blank_start]impact[blank_end] of a particular risk. Risk Acceptance depends on risk criteria and the risk appetite of Top Management.
Answer
  • likelihood
  • total
  • impact
  • probability
  • Risk Acceptance
  • Risk Treatment
  • Risk Tolerance
  • Residual Risk

Question 3

Question
[blank_start]Key Planing Scenario (KPS)[blank_end] provides the [blank_start]BC Team[blank_end] with a perspective of the [blank_start]magnitude[blank_end] of disaster that an organization is willing to commit the [blank_start]resources[blank_end] to mitigate and is acceptable to the organisation. This organisation includes the Executive Management, Organization BCM Coordinator, BCP team, DRP team and the Crisis Management Team.
Answer
  • magnitude
  • level
  • resources
  • human resources
  • BC Team
  • BCP Team
  • Key Planing Scenario (KPS)
  • Risk Appetite
  • Worst Case Disaster Scenario

Question 4

Question
A Man-made Threat is an event resulting from [blank_start]human intent[blank_end], negligence, or error. It is divided into into two category: [blank_start]human[blank_end] or [blank_start]technology[blank_end].
Answer
  • human intent
  • sabotage
  • technology
  • financial
  • human
  • management

Question 5

Question
[blank_start]Natural Threat[blank_end] is a threat resulting from the effect of [blank_start]nature[blank_end] that may cause a disruptive [blank_start]impact[blank_end] to an organization.
Answer
  • nature
  • environment
  • impact
  • effect
  • Natural Threat
  • Technology Threat

Question 6

Question
[blank_start]Period of Disruption[blank_end] is the expected [blank_start]residual[blank_end] disruption resulting from each identified threats, taking into consideration existing controls. The period of disruption is an estimated duration during which the organization’s operations are disrupted ([blank_start]operationally[blank_end]), or access to the primary location is denied ([blank_start]infrastructure[blank_end]).
Answer
  • residual
  • existing
  • operationally
  • intentionally
  • infrastructure
  • premise
  • Period of Disruption
  • Key Planning Scenario

Question 7

Question
A [blank_start]Threat[blank_end] is an indication or warning of probable man-made or natural situation that can cause [blank_start]disruption[blank_end] to an organization’s operations or services.
Answer
  • Threat
  • Disaster
  • disruption
  • disturbance
  • Hazard

Question 8

Question
The disruption caused by the occurrence of the [blank_start]threat[blank_end]. It can be operational in nature, causing disruption to the [blank_start]functionality[blank_end] of the organization, or infrastructure in nature which will deny access to or usage of the primary [blank_start]location[blank_end].
Answer
  • functionality
  • revenue
  • location
  • site
  • threat
  • disaster

Question 9

Question
[blank_start]Worst Case Scenario[blank_end] is the worst possible [blank_start]condition[blank_end] or outcome out of the several [blank_start]possibilities[blank_end] in planning for a [blank_start]disaster[blank_end].
Answer
  • condition
  • situation
  • possibilities
  • alternatives
  • disaster
  • crisis
  • Worst Case Scenario
  • Key Planning Scenario

Question 10

Question
[blank_start]Risk Analysis[blank_end] is the process to evaluate and determine the risk rating, which is the product of [blank_start]risk likelihood[blank_end] and [blank_start]risk impact[blank_end].
Answer
  • Risk Analysis
  • Risk Rating
  • Risk Assessment
  • risk likelihood
  • likelihood
  • risk impact
  • impact

Question 11

Question
[blank_start]Risk Appetite[blank_end] is amount and the type of risks that an organization is willing to take in or absorb.
Answer
  • Risk Appetite
  • Risk Impact
  • Risk Level

Question 12

Question
[blank_start]Risk Assessment[blank_end] is the overall process of [blank_start]risk identification[blank_end], [blank_start]risk analysis[blank_end] and risk evaluation.
Answer
  • Risk Assessment
  • Risk Appetite
  • Risk Likelihood
  • Risk Impact
  • risk identification
  • risk determination
  • risk analysis
  • risk assessment

Question 13

Question
[blank_start]Risk Avoidance[blank_end] is to make an informed decision not to become involved in or to withdraw from a risk situation.
Answer
  • Risk Avoidance
  • Risk Treatment

Question 14

Question
[blank_start]Risk Evaluation[blank_end] is the process used to compare the estimated risk against the given risk criteria so as to determine the significance of the risk.
Answer
  • Risk Evaluation
  • Risk Appetite
  • Risk Assessment
  • Risk Level

Question 15

Question
[blank_start]Risk Impact[blank_end] is an outcome resulting from a threat that will impact an organization objectives or assets.
Answer
  • Risk Impact
  • Risk Appetite
  • Risk Likelihood
  • Risk Rating
  • Impact

Question 16

Question
[blank_start]Risk Level[blank_end] is the overall level of assessed risk to the risk rating.
Answer
  • Risk Level
  • Risk Appetite
  • Risk Likelihood
  • Risk Impact

Question 17

Question
[blank_start]Risk Likelihood[blank_end] is the state of being probable or chance of a threat occurring.
Answer
  • Risk Likelihood
  • Risk Appetite
  • Risk Impact
  • Risk Rating

Question 18

Question
[blank_start]Risk Mitigation[blank_end] is to implement measures so as to lower the exposure to the risk.
Answer
  • Risk Mitigation
  • Risk Reduction

Question 19

Question
[blank_start]Risk Rating[blank_end] is the result of the multiplication of the assigned value for Risk Likelihood against the assigned value of [blank_start]Risk Impact[blank_end].
Answer
  • Risk Rating
  • Risk Level
  • Risk Impact
  • Risk Appetite

Question 20

Question
[blank_start]Risk Reduction[blank_end] is to take appropriate actions to lessen the likelihood, negative consequences or both, associated with a risk.
Answer
  • Risk Reduction
  • Risk Treatment
  • Risk Mitigation
  • Risk Transference

Question 21

Question
[blank_start]Risk Tolerance[blank_end] is the amount if risk that an organization is willing to accept or be exposed to.
Answer
  • Risk Tolerance
  • Risk Acceptance
  • Residual Risk

Question 22

Question
[blank_start]Risk Transference[blank_end] refers to the shifting of the burden of loss for a risk to another party through legislation, contract, insurance or other means.
Answer
  • Risk Transference
  • Risk Treatment

Question 23

Question
[blank_start]Risk Treatment[blank_end] is the selection and implementation of appropriate options for dealing with risk.
Answer
  • Risk Treatment
  • Risk Management
  • Risk Tolerance
  • Residual Risk

Question 24

Question
A [blank_start]Crisis Event[blank_end] is an event (or occurrences that happen over a period of time) leading up to the crisis can pertain to people or human resources.
Answer
  • Crisis Event
  • Crisis Scenario

Question 25

Question
A [blank_start]Crisis Scenario[blank_end] describes a situation that might disrupt the business.
Answer
  • Crisis Scenario
  • Crisis

Question 26

Question
[blank_start]Impact[blank_end] is an evaluated consequence of a particular effect due to the cause, such as a threat.
Answer
  • Impact
  • Risk Impact

Question 27

Question
[blank_start]Hazard[blank_end] is potential harm or damage, or a situation which poses a level of threat to life, health, property or environment.
Answer
  • Hazard
  • Threat
  • Risk

Question 28

Question
What is the biggest benefit of a successfuly Risk Analysis and Review phase
Answer
  • Improved cost-effective controls
  • Threat reduction

Question 29

Question
Which of the following is NOT the responsibility of the an organization's BCM Coordinator during the Business Impact Analysis phase
Answer
  • Determine data collection process and format
  • Identify critical business function
Show full summary Hide full summary

Similar

Basic Insurance Concepts & Principles - exampdfs 01
shuiziliu
Basic Insurance Concepts & Principles (Fourth Edition - 2013) from SCI website
shuiziliu
Basic Insurance Concepts & Principles - exampdfs 02
shuiziliu
Basic Insurance Concepts & Principles - exampdfs 02
raralog106
Basic Insurance Concepts & Principles - exampdfs 01
raralog106
Basic Insurance Concepts & Principles - exampdfs 02
Desmond Lee
Les cas particuliers -ter/-ler
Ömer KARAKAYA
1_Basic Insurance Concepts & Principles (Fourth Edition - 2013) from SCI website
Desmond Lee
Basic Insurance Concepts & Principles - exampdfs 01
Desmond Lee
Basic Insurance Concepts & Principles - exampdfs 01
Nicholas Lee
Basic Insurance Concepts & Principles - exampdfs 01
MALVIN LIM