1A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.
What is the root cause of this issue?- ALack of team member training on documentation planning
- BImproper assignment of tasks to team member pairings
- CIncorrect communication techniques applied during implementation
- DTeam cohesiveness was lost because team members worked in pairs
2A project manager is working to create a product that can be released to the market as soon as it passes rigorous quality standards. Historically, the company has used a predictive methodology, but the company is exploring the implementation of agile methodologies.
The company asked the project manager to explain the value gained by using an agile process.
How should the project manager respond?- AEarly value cannot be achieved until the product is fully released.
- BEarly value can be gained by testing the most important features in the initial stages to fix deviations.
- CEarly value will be gained only if beta products can be released to the market.
- DEarly value will be gained only if the speed can be increased to release the product to the market.
3A risk was identified at the beginning of a project, and a response plan was established. Unforeseen consequences resulted in a higher level of risk. The project manager has an idea that could address the new risk in an efficient way, but the response is different from the original risk mitigation plan.
What should the project manager do?- ASubmit the new response plan to the stakeholders for their review.
- BObtain management approval prior to implementing the new risk response.
- CUse the management reserve to mitigate the risk.
- DImplement the new response to address the risk.
4During a project gate review meeting, it is identified that one of the project deliverables will require corrective actions to meet the project quality requirements. What should the project manager do first?
- AUpdate the risk register and implement the approved risk response plan for quality deviations.
- BIdentify the resources that were responsible for the deliverable and request a team development plan.
- CUpdate the issue log, identify the involved stakeholders, and assign resources to the corrective actions.
- DSubmit a change request to update the project quality requirements for the involved project deliverable.
5A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.
What conclusion should the project manager come to with regard to the product owner's statement?- AThe product owner does not have visibility into what the team has done in the product increment
- BThe product owner trusts the team and is marking the product as complete.
- CThe product owner has evaluated the product against the definition of done (DoD).
- DThe product owner will release the product to customers without showing them a demo.
6A product team is comprised of consultants and staff members Most of the team members agree on risks and the defined risk actions. One consultant discovers a new risk and communicates it directly to management.
What should the project manager do?- AReject the risk because the team is not in agreement on escalating it
- BInclude the risk in the risk assessment and evaluate it with the team
- CAccept the risk and immediately enter the risk into the risk register
- DDiscuss with the consultant to understand why the risk was escalated
7A project manager identifies an issue between two team members that is affecting the development of one of the deliverables during the second iteration of a project. How should the project manager address this issue to avoid any impact to the project?
- AContact the functional managers to request substitutes for the conflicting team members.
- BSend a warning to both team members indicating that if the issue continues, both will be removed from the project.
- CSchedule a meeting with both team members to understand the issue and facilitate a solution that satisfies both parties.
- DEscalate both team members to their respective functional managers and let them take the appropriate actions
8A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to analyze team performance? (Choose two)
- AProject schedule
- BProduct backlog burnup chart
- CWork breakdown structure (WBS)
- DCumulative flow diagram of completed features
- EBurndown chart
9In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What should the project lead do next?
- AInvite the stakeholders to the retrospective meetings.
- BInvite the stakeholders to the sprint review meetings.
- CHold a meeting every 2 weeks with the stakeholders.
- DNegotiate by sending an informative email to stakeholders.
10During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?
- AHave the project team work on other activities
- BImplement plans to remove the obstacles
- CEscalate to the project steering committee
- DPrioritize the obstacles for resolution
11A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?- ARefuse to manage the project as there is too much risk in developing this kind of project without a product owner.
- BDefine the project's requirements, prepare a long-term detailed plan, and manage the project according to it.
- CConvince the client that a product owner is needed, as the project manager is not able to run an agile project without all the relevant roles in place,
- DAgree up front on a minimum viable product (MVP), establish deadlines for review, and run the project with a backlog and weekly sprints.
12A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?- AProcess a bank loan to pay the payroll of the third-party supplier.
- BReassign resources from other projects to pay the third-party supplier.
- CExplain the third-party supplier situation to the client and request payment.
- DInform the client that the project must be delayed until payment is received.
13A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task What should the project manager do?
- AAsk the team member to follow the approved communications management plan to communicate their issue
- BSchedule a meeting with the concerned team member to review and update the issue log together
- CReview the risk register with the team member to find the proper response action for this issue.
- DAsk the team member to raise a change request to assess the issue in detail
14In the middle of a project, a business unit manager who regularly interacts with the project manager's team is promoted to a higher management position. The replacement manager is from the same unit and is somewhat familiar with the project.
After getting more information about the new manager, what is the project manager's next step?- AContact the previous business unit manager to learn more about the new manager.
- BUpdate the stakeholder register and the stakeholder engagement plan to include the new manager.
- CSend the new manager a copy of the project charter to ensure the project objectives are understood.
- DSchedule a meeting with the new manager to discuss the business analysis team's plans.
15A project manager is assigned to deliver an innovative solution that is part of a brand new offering. The project manager reviews the request for proposal (RFP) and realizes that key terms are restricted to technical resource assignments. There is also a gap in addressing compliance.
How should the project manager bridge the gap and ensure the project delivers the expected business value?- ADetermine the critical requirements.
- BDocument the risks and mitigations.
- CDefine the project schedule.
- DCreate a project scope statement.
16A project manager is assigned to a project that is in development As the project manager reviews the projects progress, they find a few tasks that are behind schedule After investigating the project manager discovers that a few team members were pulled to work on other assignments, which impacted their ability to focus on the project manager's project Which two actions can the project manager take to bring the team back on track? (Choose two)
- AEstablish daily standups to review project progress and track the completion of deliverables
- BAllow the team members to catch up at their own pace
- CAlert the business stakeholders immediately of the schedule delay.
- DDiscuss the risk of project delay and work priorities with the respective functional managers
- EWork with the team to identify options to accelerate project delivery.
17A project is delayed. The project manager added extra resources to some activities and approved overtime for several team members.
What technique is the project manager applying?- AFast tracking
- BResource leveling
- CCritical chain method
- DSchedule crashing
18After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?- AComply with the project sponsor's request to not archive the project artifacts.
- BDocument the project sponsor's instructions as the archived project artifacts.
- CArchive the project artifacts on the project manager's local computer for future reference
- DConsult with the project management office (PMO) for guidance on project artifacts.
19A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C.
The project was going well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference to each other's problems over team A.
The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)- ASchedule weekly progress meetings with all three teams and have them take turns as key players.
- BPlan for team members to temporarily work at each other's locations to better provide a sense of community.
- CUpdate the communications management plan and encourage the teams to review it promptly and proactively.
- DCreate a status reporting template and share it with all team members before the day ends.
- ESchedule daily meetings with each team to understand their progress and concerns in detail.
20A team member in an agile project informs the project manager they might not be able to finish an assigned task on time, which could generate an obstacle for the rest of the team. What should the project manager do?
- AMove the task to the next sprint.
- BAsk the team member to bring up the concern in the next daily meeting.
- CSend an email explaining the issue to all team members.
- DReassign the task to another team member.
21A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.
- AĐáp án

- BĐáp án ở trên
- AĐáp án
22A new solution is being deployed in countries A B and C.
This solution will allow the countries to propose new services to their customers Country A has asked for a change in the solution m order to comply with its own customer market What should the project manager in charge of the deployment in country A do?- AAccept the change request from country A and reschedule the deployment project for country A.
- BTake the request into account and ask the sponsor to inform countries B and C about the change
- CAsk country A to submit a change request that will be analyzed along with countries B and C
- DRefuse country As request as there is no time for the change as deployment has already begun
23During the execution of a construction project, the project sponsor asks to make changes to the floor plan by adding a minimal storage room. The sponsor insists on making this last- minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?- AChange management plan
- BSchedule management plan
- CScope management plan
- DCost management plan
24Match the project situation on the left to the meeting on the right where the situation could occur

- AĐáp án

- BĐáp án ở trên
- AĐáp án
25What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
- AHire employees who specialize in agile approaches so they can better contribute to projects.
- BAssign employees to agile projects so they can quickly adjust to the new approach.
- CTrain all employees in agile approaches.
- DShift the way the company views, reviews, and assesses employees.
26An organization is introducing agile to its projects. During an informal discussion the project manager learned that team members who are currently working on different teams are discussing how they would like to be together on the same team What should the project manager do?
- AThe project manager should not allow resources to choose teams because the project manager assigns the resources based upon project needs
- BThe project manager should not allow resources to choose on which team they would like to work because they will always choose their favorite team
- CThe project manager should allow the resources to periodically choose on which team they would like to work.
- DThe project manager should indicate that the team members have already been assigned to a team through workforce optimization
27A project manager is assigned to a project within a program. The high-level requirements of the project are known, but the priorities of some of the requirements are uncertain as they are interdependent on some other pipeline projects within the program.
How should the project manager prepare for the next steps of the project?- AEscalate to the management team to increase the timeline based on the complexity of the project
- BWait for the other project estimates before planning the schedule
- CPrioritize and estimate the milestones for the high-level requirements based on historical data
- DAsk the project management office (PMO) to estimate the tasks for all the projects and share the project management plan
28The business manager and the product owner are requesting a more flexible way to incorporate changes into the product baseline They are concerned about losing time to market with respect to other vendors What should the project manager do?
- AReview the assumption log and project management plan for changes.
- BIdentify adequate change management tools to conduct the project
- CEstablish a change control board (CCB) with key stakeholders.
- DAllow key stakeholders to make some changes to deliver the product faster
29A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team How can the project manager ensure knowledge transfer across the team?
- AAsk the project team to run a deviation log review meeting with the client, highlighting that the project may not be able to go live as scheduled
- BAsk the project management office (PMO) to provide team members with real-time visibility for deviations and facilitate team members to resolve issues
- CAsk the SMEs to share the knowledge transfer documents with all other members by placing the documents in the project management information system (PMIS)
- DAsk the project team to facilitate a lessons learned session during the project closure phase to incorporate this issue
30A team is the first team m the company to use agile methods for a traditional project. The team's manager is concerned that the risks are not being managed. What should the team do to assess and manage risks regularly?
- AIdentify and escalate any identified risks to the facilitator to handle
- BUpdate the risk register during every iteration with any open concerns
- CUse regular feedback loops through daily standups iteration demos and retrospectives
- DFocus on developing a working deliverable instead of documenting risks
31During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
- ACommunicate the concerns to the project management office (PMO) during the weekly project reports
- BCall for a team meeting to decide if the changes should be included
- CInitiate the change request to modify the scope and adjust the timelines
- DConduct an impact analysis and present the results to the steering committee for approval
32A project manager determines that a critical path activity is going to be delayed. The team proposes a fallback plan that could get the project back on track; however, the plan would require an additional cost to an already tight budget.
What should the project manager do?- AUse the existing budget for executing the fallback plan and update the baseline.
- BAdd additional resources to the project to fast track certain activities and reduce delays.
- CEvaluate the fallback plan proposed by the team and submit a change request, if required.
- DCommunicate the delay to stakeholders and maintain the existing budget baseline.
33A project manager has been assigned to a project that is in progress. The project manager is looking for information regarding why the project is being completed.
What should the project manager do first?- AEvaluate the project exit criteria in the project charter.
- BReach out to the senior executive sponsor for the project.
- CUnderstand the project success criteria and objectives.
- DReview the project status reporting for the latest information.
34A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.
What should the servant leader do to address this risk?- AInclude this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every iteration.
- BForecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.
- CAsk the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.
- DContact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential information.
35A project manager is assigned to a project to develop a mobile app. The sponsor explains that the application should do better than their closest competitor's app. The sponsor's expectation is that the team can be put together and start work immediately.
What should the project manager do?- AStart working on the resource management plan in order to identify the best team for the project.
- BUtilize expert judgment and organizational process assets (OPAs) to estimate the effort and budget.
- CReview the competitor's app to understand the functionalities that the project scope should consider.
- DDefine the project scope with the stakeholders and determine how formal acceptance will be obtained.
36A project leader is assigned to a new project and is asked to assemble an effective five- member agile team. If the project leader has no restrictions, which team should they choose?
- AA team whose members work independently and are the best subject matter experts (SMES)
- BA team whose members have more general aptitudes but like to work individually
- CA team whose members have different skill sets and are spread out geographically
- DA team whose members have more general aptitudes and can collaborate on different tasks
37A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay What should the project manager do next?
- AHave a discussion with the sales team to find a solution to the issue
- BValidate the reason and add n as an issue m the issue log
- CEscalate the issue to the functional manager
- DDirect the sales team to speak with accounting to resolve the issue
38A product owner has provided the team with a prioritized backlog for the initial launch of a new product. After analysis, the team concludes that some work is missing to support the initial launch and provides this information to the product owner. The product owner acknowledges the missing work and adds it to the bottom of the backlog. The team is not happy with the prioritization that the missing work received.
What should the project manager do in this situation?- ALet the project team pull the recommended work from the bottom of the backlog to maximize value creation.
- BAnalyze and reprioritize the backlog and provide the decision to the product owner and team.
- CRecommend the product owner prioritize the missing work higher because it is needed for the minimum viable product (MVP).
- DEmpower the product owner by supporting the decision and instructing the team to follow the prioritization as provided.
39A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.
Which life cycle should the project manager use for this project?- AA predictive execution strategy
- BA hybrid execution strategy
- CAn iterative execution strategy
- DAn agile execution strategy
40A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team What should the project manager do?
- ASend a formal communication regarding the missed milestone
- BDelay sending a formal communication until the project team catches up
- CAsk for a meeting with the sponsor to decide whether to send the formal communication
- DForego the formal communication and have a conversation with the supervisor
41A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members Which three actions should the project manager take? (Choose three)
- AAllow team members to resolve personal issues without involving the project manager
- BArrange and conduct team-building sessions to improve team effectiveness
- CObtain feedback from the isolated team member to understand the situation
- DGet feedback from other team members to understand what led to this situation
- EIdentify the isolated team member as a risk and document the situation in the risk register.
42Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior"- AWorked on a fixed-price contract to switch the product owner's attention to value instead of money
- BWorked on a communications management plan with reports of budget spent in each iteration versus planned to avoid these discussions during ceremonies
- CWorked on different approaches of estimating to give confidence of the cost spent in each product increment.
- DWorked with the product owner to clarify their role in an agile project and the scope of the agile ceremonies
43A project manager is assigned to a project related to taxes, which will be managed using an agile approach. By reviewing lessons learned from a previous project, the project manager discovers that a key stakeholder is an expert on taxes and is willing to help. How should the project manager leverage this information?
- ARecognize the stakeholder's skills are important for the project and evaluate the possibility of the stakeholder supporting the project team.
- BRequest the functional manager to assign the team from the lessons learned project to the current project to avoid a learning curve.
- CAsk the project team to review the lessons learned and have the team contact the stakeholder directly if there are any questions.
- DSend a request to the project sponsor to hire the stakeholder and have them become part of the project team.
44Project A is critical for the company and must be completed within nine months. The project charter has been signed but the project scope statement has not been prepared Management asks the project manager to move forward with the project without an approved project scope statement What should the project manager do next?
- AEscalate the issue to the project sponsor and add it to the risk register
- BRefuse to work on the project because management is not following standard project management practices
- CMeet with management to explain the potential problems with running a project without a project scope statement
- DStart the project with inputs from the project charter to save time
45An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?
- ASupport the team as necessary to find the minimum viable product (MVP).
- BAmend the project budget to include MVP testing
- CSubmit a change request to the project sponsor for accelerated testing.
- DDevelop the product as per the schedule to perform integration and testing
46A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?- AContact the design team manager and ask to reconsider the priority list based on the latest situation,
- BMeet with the designer to share the current status and develop a solution to complete the task
- CMeet with the design team manager to inform them of the current status and request an additional designer.
- DAsk the software engineer to move forward without completing the important feature.
47A project manager has established daily standup meetings with the team during the execution phase of the project. The project manager has been successful in removing 75% of the obstacles reported, but the timeline continues to deviate further each day with no signs of improvement.
What should the project manager have done to avoid this issue?- APrioritized blockers on the critical path
- BDistributed the daily standup meeting agenda beforehand
- CFollowed the quality control measurements
- DDeveloped the team members' competences
48During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?
- AReviewed the risk register to identify a response plan for the audit
- BAssigned a project team member to ensure all project documentation was updated
- CUpdated the project management plan regularly and had it securely shared with all stakeholders
- DKept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders
49A project just kicked off and management's expectation is to ensure that the deliverable of the first iteration helps the marketing team present the product prototype to potential customers. What should the project manager do?
- AIncrease the details of the work breakdown structure (WBS) to minimize errors and delays.
- BSplit the backlog into phases to ensure that the key features are delivered first
- CAsk the sponsor to prioritize some functionalities of the product.
- DIdentify the minimum functionality required for the product
50A company initiated a project to introduce a new product to the market. The product must undergo the industry's regulatory process prior to approval and launch. However, the company sees a great demand for this product and wants it to launch as soon as possible. What should the project manager do to realize this opportunity?
- ACommunicate with the industry's regulatory authority to grant the company an exception
- BEscalate the issue to the company's CEO who has experience with the regulations.
- CComply with the regulatory requirements and work to compress the project schedule.
- DHire a third party who is an expert on the industry's regulations to work out the details.
51A project team identified a low-cost software product available for purchase that would drastically reduce the scope of development. The development manager has confirmed that this tool would fulfill the business need.
What should the project manager do?- ARemind the team that their primary responsibility is software development.
- BAdd a user story to the product backlog to test the software product.
- CDiscuss the Option in the next daily standup meeting to finalize the decision.
- DRecommend the option to the product owner for consideration.
52A project manager finished reviewing the project deliverables for the current iteration with the customer A new key stakeholder who just joined the customer's team, complains that the results do not provide the capabilities the business anticipated What should the project manager do to address this issue?
- ACreate a change request and update the scope management plan
- BConduct stakeholder identification and a project objectives review session
- CUpdate the stakeholder list and fix the deliverables
- DUpdate the project management plan and lessons learned
53A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder's behavior on the development team.
What training should the project manager choose for their team to help with this situation?- ACommunication training
- BNegotiation training
- CEmotional intelligence training
- DAgile training.
54A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important milestone in a week.
What should the project manager do next?- AAsk the vendor if the minimally sufficient materials can be produced in time to meet the deadline.
- BPerform market research to find out if there are other vendors that can produce similar kinds of materials.
- CSubmit a change request to the change control board (CCB) asking to extend the deadline in order to reflect the late delivery.
- DInvolve the legal department, as the vendor is breaching the contract by not delivering the full amount in time.
55A project manager is made aware that there are defects in the parts provided by a supplier, which are causing delays in the testing phase. The supplier claims that all parts have been delivered as per the contract. If the defects are not fixed by the supplier within one week, the product release will be impacted.
What should the project manager do?- AScalate this issue to senior management, as the supplier is not following the procurement contract.
- BRequest a revision of the procurement contract to include specifications for the parts.
- CRequest a cancellation of the procurement contract with the supplier and impose a penalty.
- DReview the procurement contract and ask the supplier to negotiate a solution.
56During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past What should the project manager do next to improve this situation?
- ACall for a team meeting to identify the root cause for the declining performance
- BEstimate the baseline impacts and submit a change request.
- CImplement compression techniques to bring the project back on track.
- DReview the resource management plan and organizational assets
57An agile team was hired to work on a public service project. The team received a list of vague ideas about the business and now needs to understand, develop, and prioritize a list of functionalities.
Who will be responsible for this task?- AProject owner
- BAgile leader
- CAgile team
- DProduct owner
58After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?- AImpact mapping
- BRolling wave planning
- CCollective code ownership
- DScrum of Scrums
59A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders.
What does the project manager need to do next to help the team understand the work that needs to be done?- AWork with the team to decompose the scope into a WBS and work packages in order to create required deliverables and timelines.
- BWork directly with stakeholders on the work breakdown structure (WBS) and assign tasks with a required timeline for each team member to start the work.
- CCreate the requirements management plan to outline how project requirements will be collected analyzed and documented and then assign requirements to team members
- DStart working on the project management plan with work packages, a detailed schedule, and work assignments for team members
60A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.
Which action should the project manager take?- ACreate a specific sprint to deliver the project documentation.
- BAssign a dedicated resource to work on the documentation during the project.
- CMake documentation a standard part of the definition of done (DoD).
- DFocus on the documentation after the features are delivered.
61A project manager is in the process of creating a strengths-based team and is organizing a series of workshops to identify and document the strengths of each project team member. During this session, there are multiple team members who are not actively participating.
These meetings are becoming futile due to a lack of participation. What should the project manager do?- AHave a one-on-one discussion with each team member to emphasize their individual talents.
- BDocument the behavior of the team members and highlight it during their performance reviews.
- CIdentify the team members who are not participating and reprimand them.
- DExplain the benefits of the approach and the effects of positive psychology.
62A project manager is managing a project to develop a new tool Because of the nature of the project, the project manager decides to use an agile approach One of the identified risks becomes an issue when the project manager finds out that another company patented a very similar tool.
What should the project manager do to address this issued- ASchedule a meeting with critical stakeholders to review the issue and decide on the next steps
- BPut the project on hold and release the resources until the issue is resolved
- CInform the product owner and log the issue in the risk register to monitor closely for next steps.
- DContact the company that owns the patent of the similar tool to compare the similarities and differences with the current project.
63A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during project execution?- AInclude a planned value (PV) calculation in the sprint report for each build cycle.
- BConduct a customer demonstration at the end of each build cycle.
- CProvide the customer with the refined specification during each build cycle.
- DShow the customer a sprint burndown chart for each build cycle.
64A new agile team is having trouble completing tasks. There are many disputes occurring in the team. What should the agile leader do in this situation?
- AEscalate the issue to the team's manager.
- BRemove some of the team members.
- CReview the roles and responsibilities document.
- DDevelop working agreements with the team.
65A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?- ADelay the project until the issue is addressed and no longer presents as a risk to the project.
- BInform the sponsor that the issue has arisen and that the project's success may be uncertain
- CAvoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.
- DHold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue
66A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget What should the project manager do?
- ARequest to use the management reserve to keep the schedule
- BMitigate risks associated with the workaround to avoid project delays
- CProceed with the approved risk response plan.
- DDiscuss the options with the client as part of the change control process
67A project team member wants to select specific challenging tasks in the subsequent iteration. How can the project lead help the team member in the next iteration?
- AAssign the challenging tasks to the team member.
- BAsk the product owner to assign the challenging tasks.
- CReprioritize the challenging tasks to future sprints.
- DCoach the team member to pick up the challenging tasks.
68A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to take action in advance to ensure the project succeeds.
What should the project manager do?- AEvaluate the project risk and add external experts to address the potential risks.
- BInform the project sponsor about the risk and try to convince them to withdraw from the project.
- CContinue executing the project as planned and add more resources if they are required.
- DReview the lessons learned on similar projects so that they do not fall back into the same pattern.
69In the middle of an iteration a team member suggests a new method of doing things The method provides no value to the end customer, however it may help the team to work more efficiently The change may require several days of work to implement How should the project manager respond to the suggestion?
- AThe change should be considered and immediately added to the product backlog.
- BThe change should be considered and presented to the project sponsor for approval
- CThe change should be considered because rt will help the team work more efficiently
- DThe change should not be considered because it adds no value to the end customer
70A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
- ADevelop new procedures that are easy for the team to follow.
- BEscalate the issue to the CEO and the board members.
- CInstruct the team that the procedures should always be followed.
- DInitiate a review of the procedures with the CTO and the team.
71A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, Io their knowledge, the project does not seem to have any compliance requirements in their country.
What should the project manager do in this situation?- ARequest expert advice from the compliance leader to confirm if there are any compliance requirements for the project.
- BCheck with The national compliance agency to determine if the project has any compliance requirements in this country
- CTrust in the expertise of the sponsor and believe that there are no compliance requirements for this project.
- DConduct independent research regarding the data protection policy of the country for legal and regulatory compliance.
72A project manager is leading a progress review meeting when some stakeholders who are new to the project express concerns about not having access to previously shared deliverables. What should the project manager do?
- ADocument the new stakeholders' concerns in the meeting minutes.
- BSchedule an ad hoc meeting with the new stakeholders to discuss concerns.
- CUse social media environments to share the project information
- DUse the project management information system (PMIS) to share information.
73A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist from the team was average.
What should the project manager do to help the new compliance specialist improve?- AEscalate this situation to the manager of the area for a possible solution.
- BProvide time for the specialist to adjust to the pace of the project.
- CCoordinate a one-to-one meeting with the specialist to assess the situation.
- DContact the human resources (HR) manager about the team's feedback.
74A project to develop a banking product is in the execution stage New regulations from the government are significantly affecting product development. Stakeholders are concerned about whether the planned benefits are still valid and achievable What should the project manager do first?
- AReforecast and revalidate the benefits baselines and targets
- BEscalate the issue to the sponsor and request more funding.
- CShowcase progress toward the targets and revalidate a project work plan.
- DOptimize alignment between the stakeholder needs and project objectives.
75A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?
- AFollow the organization's process and deliverables for predictive projects, even if they compromise the agility and performance of the project.
- BUse the risk register to document all of the compliance vulnerabilities generated by the project so that all decisions are well documented and approved by stakeholders.
- CMeet with the project management office (PMO)/compliance entity to work on process tailoring to ensure that the agile deliverables support the compliance requirements of the organization.
- DCoach upper management on agile practices, explaining that an agile project is concerned with value delivery, and negotiate a way out of the compliance requirements.
76A company made several changes recently, which resulted in a positive change in the company culture. A project manager was just assigned to report to a new project supervisor whose leadership style is about getting things done quickly regardless of employee and operational impacts. Some employees are complaining about this.
What should the project manager do?- AClarify expectations by explaining the company culture with the supervisor.
- BAsk senior management to move the supervisor to a different project.
- CRevisit the company's organizational culture.
- DInstruct the employees to listen to the supervisor.
77A project has been running for 2 months and now requires approval for a supplier to begin some execution tasks. The project team has evaluated several suppliers and selected their top two preferred suppliers. The project sponsor requested that another supplier who has lower costs be added to the list. However, the project manager is aware that this supplier does not always fulfill the project requirements.
What should the project manager do?- ASet up a requirements review session and obtain agreement for selection criteria.
- BRecommend to the team to add the sponsor's preferred supplier to the list.
- CChoose the sponsor's preferred supplier for the project to avoid conflict between the team and sponsor.
- DRecommend to the sponsor to review the results of the team's supplier evaluation.
78A project team member is struggling to deliver an assigned task. In a team meeting, the project manager determines that there are other members on the team who have more experience with similar tasks.
What should the project manager do?- AAsk one of the more experienced team members to support the team member with the task.
- BReassign the task to one of the more experienced project team members for a faster completion of the assigned task.
- CAsk the experienced team members to produce a manual on how to complete the task.
- DInform the project management office (PMO) of the issue and request a replacement for the less experienced team member.
79A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
- ACheck if the budget can cover the enhancement
- BAccept the request because it came from the project sponsor
- CRefuse the project sponsor's request because it is out of scope
- DValidate the proposed change's impact on the project.
80A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up. What should the project manager do?
- AMeet with this team member.
- BReview this method with the team.
- CAccept this task-based estimation.
- DReject this task-based estimation.
81A project manager is working with a colocated agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to colocate.
What should the project manager do to keep the team performing as effectively as possible?- AAsk the project sponsor and executive stakeholders to encourage the team to maintain their performance
- BTransition the team from an agile approach to a predictive approach for better performance central.
- CProvide the team with virtual collaboration software and training on the software to minimize disruption
- DEvaluate project performance and step in if performance decreases to. an unacceptable level
82A project stakeholder has expressed concern that the established success criteria for the project are not being met. What should the project manager do next?
- AReview the established project benefits tracking metrics.
- BUpdate the project business case document.
- CDocument the agreed-upon ownership of benefits realization.
- DCreate a project benefits management plan.
83A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.
What is the most likely reason for the engineer's refusal to work on the project?- AThe engineer did not feel welcome or enjoy working with the other project team members.
- BThe project manager did not follow the normal hiring process with the engineer's functional manager.
- CThe engineer has "project burnout" from working long hours and solving difficult problems.
- DThe project manager did not sufficiently support and recognize the engineer's professional growth.
84A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.
What should the project manager do?- AUse an agile approach and engage a vendor that delivered well in a previous organization.
- BConsult the product owner and engage a vendor that is recommended by them.
- CConsult the development team and engage a vendor that is recommended by them.
- DUse a formal approach using procurement policies, procedures, forms, and work instructions.
85A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.
Match the roles for the team on the left to their corresponding responsibilties on the right.
- AĐáp án

- BĐáp án ở trên
- AĐáp án
86A project manager in a matrix organization has been assigned to a system solution project with tight time lines.
There are two resources assigned as part of the solution
team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.
What should the project manager do next to deliver a reliable solution?- AMeet with the resources and agree that the more experienced resource's approach has proven to be effective in the past.
- BMeet with each resource's functional manager and arrive at a common approach that is appropriate for the project's constraints.
- CMeet with the entire project team and decide on a further course of action based on team consensus.
- DMeet with the resources together and find common ground on viewpoints to compromise on an approach.
87A project is approaching its project closure phase, and the project manager receives an email from a key stakeholder who complains that the project documentation and artifacts have not been updated. The project manager assigns a project specialist to support the project management office's (PMO) effort to update the project documentation and artifacts.
Which three actions should the project manager ask the project specialist to take? (Choose three)- ACreate a quality assurance plan for the documentation.
- BIdentify the components of the project documentation.
- CArchive only the initial and draft versions of the documents.
- DEnsure that the documents are in an easily retrievable form.
- ECollect the documents at the time of their creation.
88During an iteration demo, a customer noticed an enhancement they would like to make to the product. What should the team do next?
- ARefine and estimate the enhancement so the size is known.
- BAdd it to the product backlog to be completed in the future.
- CStart working on the enhancement for the customer immediately.
- DAsk the product owner to prioritize the item with the customer.
89A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?
- AReview lessons learned from previous projects that used the same team
- BReview the organizational culture, structure, and governance
- CCoordinate a meeting to understand the situation and resolve any conflicts.
- DCoordinate a meeting with regional managers to ask for support
90During project execution, a project manager discovers that the budget at completion has shifted significantly and is higher than expected.
What should the project manager do?- AAdjust the original budget estimates with the current cost variance.
- BNegotiate the project changes and adjust stakeholder expectations.
- CPerform a root cause analysis of the project performance.
- DReview the activity duration to reforecast the project completion date.
91A new project manager has been assigned to an environmental project. After reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.
Why is this situation problematic?- AInjury or loss incidents could delay project deliverables.
- BIt is imperative that established performance metrics are met.
- CThe project manager is obligated to comply with the project location's regulatory requirements.
- DThe project manager must follow their employer's organizational process assets (OPAs).
92The marketing team is moving from predictive to hybrid approaches for their projects. The marketing director is not familiar with hybrid approaches and does not support the new direction. What should the project manager do?
- AAdvise the marketing director to receive formal training.
- BAsk the marketing team members to coach their director.
- CTrain the marketing team and keep their director informed.
- DMentor the marketing director on the approaches.
93An agile project is 25% complete when the product owner changes The new product owner does not show interest in the project s success, and one of the sprints 901 delayed as the deliverable was not approved on time What should the project manager have done to avoid this delay?
- AUpdated the stakeholder engagement plan to reflect a change in the product owner
- BCommunicated the status of the project more frequently with the product owner
- CUpdated the communications management plan to reflect a change in the communication needs
- DReevaluated the new product owner's needs for better engagement
94At the daily project meeting, team members are complaining about receiving emails from their functional managers to support other nonproject-related tasks. This is having a negative impact on the team's productivity.
What should the project manager do next?- AAsk the product owner to speak with the functional managers to ensure future requirements come through the product owner.
- BLog this as a risk in the risk register and continue to monitor the issue at subsequent meetings.
- CAddress this concern with the functional managers to ensure there will be no further delays.
- DSchedule a meeting with all of the functional managers to resolve the resource conflicts.
95Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information should the project manager provide so that senior management can get a broader view of the project?
- ARisk register information
- BHigher-level activities completed
- CMilestones status report
- DResource breakdown structure (RBS)
96A project manager was recently appointed to an agile project. The project will have a lot of visibility and impact for the company, so the project management office (PMO) manager wants to ensure that the project manager manages the risks correctly.
What should the project manager do?- AImplement the agile risk manifesto to ensure the proper tracking, analysis, and remediation of the project risks.
- BAsk the product owner to act as a risk manager to assist with the remediation of risks.
- CImplement the role of an agile risk manager to take care of the risk management process.
- DFollow the risk management process while ensuring that risks are identified, analyzed, and managed during each iteration.
97During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?
- AInform the functional manager that self-organization includes task allocation.
- BConfirm with the team members that the functional manager is responsible for the delivery.
- CAsk the product owner to clarify the roles and responsibilities of the project team.
- DInform the functional manager that task allocation is the responsibility of the product owner.
98At the end of a third planning meeting, the client and a functional manager requested additional meetings to add more features to the product.
- AAllow the sponsor to determine how long the planning phase should last.
- BAllow the client ta determine how long the planning phase should last.
- CAsk the functional manager to work with the team to finalize planning and begin building the product.
- DExplain that more features can be planned in upcoming Iterations and begin building the product.
99A company has made multiple staff and operational changes over the last several years, significantly improving the company culture. A project manager was recently assigned to report to a new project supervisor. The project manager notices the supervisor's style of leadership is about getting the job done in the shortest possible time regardless of operational and worker impacts. This is causing some complaints from workers.
How should the project manager handle this situation?- ADiscuss the company culture with the supervisor to clarify expectations.
- BReview the overall organizational culture of the company again.
- CRequest that the new supervisor be assigned to another project.
- DExplain to the workers that they need to listen to the supervisor.
100A project manager has been assigned to a new project that is similar to a project that was closed last year.
There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?- AAdopt the same timeframe as the closed project for the current project.
- BInform the sponsor that the activity list is not adequate for creating a schedule baseline.
- CCreate a draft schedule based on the activity list and the historical data from the closed project.
- DEvaluate each activity duration and build a new project schedule.
Information
- Description
- Công nghệ số Quiz on PMP exam 7, created by Lê Hiếu on 30/07/2022.
- Author
- Lê Hiếu
- Language
- English
- Views
- 25
- Tags
- Rating
- No ratings yet Rate this quiz