1A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?- AAsk the experienced members to lead the junior members to facilitate skill transfer.
- BEncourage team members to focus on delivering results with their specialized skills.
- COrganize networking sessions to allow the team members to get to know one another.
- DAsk the team to self-organize and escalate any issues to the project manager.
2In a multinational multi location project with virtual teams a project manager has established a project baseline The project manager discovers that multiple risk elements have appeared. The project manager did not foresee these risks during the planning stage of the project.
What should the project manager calculate to address this critical budgetary situation? (Choose two)- AContingency control in the project and rebaseline
- BMitigation control in the project
- CBenefits management control in the project
- DIntegrated change control in the project
- ECurrency exchange rate
3A project manager just started managing agile projects The project manager realizes that due to the lack of a clear definition of project objectives and definition of done (DoD) their colleague's projects have had many difficulties Sponsors keep asking for more features and the projects have yet to be completed What should the project manager do to avoid these issues?
- AArrange meetings to ensure every necessary task to complete the project is included in the project management plan
- BConvince the project sponsor to incorporate quality experts so the product can be tested and accepted as completed.
- CConvince the product owner to approach the team and look for options to find a solution to the problem
- DSchedule meetings with key stakeholders to build the agile project charter and set clear expectations for the project
4A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.
What should the project manager do to address this issue?- ANegotiate the payments with the supplier and remind them of their long-term association
- BPenalize the supplier according to the contract's service level agreement (SLA)
- CHire another information security supplier and incentivize them for speedy delivery
- DInform the relevant stakeholders of this challenge and seek their support
5A project manager has noticed that a critical team member is consistently arguing with a client. This has started to have a negative effect on the meetings.
How should the project manager address this?- AExplain the impact of the scenario to the project team member.
- BRemove the project team member from all future meetings.
- CTalk to the client privately to highlight the situation.
- DRecommend a performance improvement plan to the project team member.
6A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work How should the project manager approach the situation?- AAttend only the program meetings where the market launch is being monitored
- BProvide an answer via email recommending a division of tasks between both roles.
- CPolitely inform the program manager that attending these meetings is no longer required.
- DSchedule a meeting to discuss the different perspectives and agree on a decision.
7A project team has recently completed the initial sprint for developing an automated payroll system for a company The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two)
- ASprint charter
- BBurndown chart
- CCompany mission and vision
- DProduct backlog
- ESprint goal
8Anew law was published about zoning permits for telecom towers. This may cause cost and schedule overruns for the new network rollout.
What should the project manager do?- AAssess and prioritize the impact of the new law on the project plan.
- BUpdate the project plan because the law is an obligation for the project.
- CMinimize the scope to catch the cost and schedule baseline.
- DMeet the sponsor to ask for additional time and budget increase.
9A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?- AImplement the call center with internal staff to ensure the work is performed according to the company's culture.
- BWork with 50% of the people internally and contract the other 50% to an outside company.
- CDelegate the analysis to the human resources (HR) department in order to organize the call center operations.
- DConduct an alternative analysis to decide whether to hire people directly or contract with a company to do the job.
10A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting What should the project manager have done to avoid this situation?
- AReviewed the communications management plan before inviting an external client representative to the meeting
- BReviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting
- CPerformed a root cause analysis with the external client representative and documented the findings in the lessons learned register
- DSent the presentation slides to internal participants first and then to the external client representative prior to the meeting
11A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay What should the project manager do next?
- AHave a discussion with the sales team to find a solution to the issue
- BValidate the reason and add it as an issue in the issue log
- CDirect the sales team to speak with accounting to resolve the issue
- DEscalate the issue to the functional manager
12A project manager finds it challenging to comply with standardized processes for knowledge transfer. The project teams and stakeholders are scattered around field sites, the office, and remote locations. In addition, some team members have limited access to the electronically shared files.
How should the project manager manage this challenge?- ARequest changes in the processes since it is not suitable for the company environment.
- BCommunicate a strong message to the team explaining the importance of knowledge transfer.
- CStudy the environment and the available resources to determine which approach to use.
- DSend the intended information through email since it is the primary communication tool.
13A globally distributed project team is running behind schedule due to the lack ol team commitment and low morale. In order to bring the schedule back on track, what should the project manager do first?
- ASeek the sponsor's approval to extend the project schedule.
- BSet up a meeting to perform a root cause analysis.
- CUpdate the issue log and communicate it to the team.
- DPermanently colocate the team for better performance.
14A project manager is assigned to an ongoing complex project. The team is delivering value each iteration However, the deliverables are internal and the customers are unaware of the deliverables.
Which action should the project manager take?- AAsk the internal sales team to keep the customer informed of the delivered value
- BEvaluate various delivery options in order to immediately demonstrate value to the customer
- CInform the customer about the progress and update them on the final deliverables
- DWait for an important milestone to complete and then inform the customer of the progress
15A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project time lines have slipped, and the staff is overwhelmed .
What should the project manager do to help the company meet their financial objectives?- APrioritize the projects, giving higher priority to projects that will increase profit.
- BMake sure the project is fast tracked so that slipped time lines are recovered.
- CRequest that upper management hire additional staff to support the projects.
- DEnsure that all of the projects are of high quality and are delivered on time.
16Ai the start of a project, the sponsor declares that demonstrating benefits from the product will be extremely important. The project sponsor calls a meeting with the project manager and the project leadership team to discuss the best approach because the project has a high degree of uncertainty and many changes are expected.
What should the project manager propose?- ADevelop requirements and designs to support a faster product release.
- BEmphasize the adoption of a predictive approach to minimize ambiguity.
- CRecommend an agile approach so the project can be delivered iteratively.
- DOutsource development of the product to a third party with more experience.
17In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress What should the project manager do first?
- ARevise the project schedule
- BPresent the project to the stakeholder
- CInform the client about the change
- DUpdate the risk register with a new risk
18Important projects in the portfolio backlog need to be delivered Budget estimates are needed to prioritize the projects How should the project budgets be estimated’?
- AThe project is decomposed into features and based on the feature value and the velocity of the team, the team provides the estimate
- BBudget estimates are provided based on the experience of the sponsor, product owner and team facilitator
- CThe team facilitator uses historical data and arrives at an estimate based on the nature of the project.
- DThe product owner obtains all project details and based on the team's experience and velocity provides a budget estimate
19A project team is experiencing delays in completing a task that turned out to be more complex than initially estimated. This is a critical task that could impact current iteration goals What two options will help the team initially address this obstacle? (Choose two)
- AEscalate the issue to the project sponsor.
- BReview and update dependencies
- CSchedule a retrospective.
- DConduct a root cause analysis.
- ECreate a risk management plan.
20The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?
- AIssue log
- BProject management plan
- CRisk management plan
- DRisk register
21A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.
How should these conflicts be resolved?- AInclude the executives in team retrospectives
- BTrain the executives on agile practices
- CNegotiate with the executives and agree on a process.
- DRequest that the executives use agile practices
22During a meeting with a customer, it was determined that participants of the meeting had different draft versions of an important design document. What should the project manager do first to ensure that this does not happen again?
- ARevisit the communication process control.
- BEnsure only the approved version is shared.
- CInvestigate how draft versions were shared.
- DEnsure only the latest version is shared.
23A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?- AProvide a software for instant messaging.
- BDocument all information on the team wiki.
- CPromote the use of remote site syndication.
- DFacilitate regular conference calls.
24A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
- ASchedule training courses to enhance team performance
- BAdd new team members to help the project finalization
- CInitiate rewards and incentives according to assessment results
- DSchedule working lunch meetings until the project is complete
25During the final iteration of the execution phase, the project has a cost performance index (CP!) of 0.9 and a schedule performance index (SPI) of 1.0.
How should the project manager avoid a budget shortfall?- AFollow the risk management plan.
- BReduce the team effort utilization.
- CLook for cost-saving opportunities.
- DSubmit a change request to add to the management reserve.
26A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?
- AModeling directive leadership
- BModeling commanding leadership
- CModeling adaptive leadership
- DModeling servant leadership
27A project manager is assigned to a technical research project. The project team has already been assigned, and the main subject matter expert (SME) sends the project manager a list of the technical skills required for the execution of this project.
What should the project manager do next?- ASend the list to the project team and ask them to get training on the required skills.
- BAsk the functional manager to review the resource pool and recommend the right individuals to join the team.
- CDiscuss the list with the project sponsor to confirm that the resources have the required skills.
- DMeet with the project team to understand their skills and identify potential gaps and training requirements.
28In an agile project, the project owner has repeatedly called for ad hoc meetings with team members. What should the project manager do?
- AAsk the team to focus only on the goal, not on ad hoc meetings.
- BCoach the project owner about the implications of unplanned meetings.
- CDiscuss the issue with the project owner at the retrospective meeting.
- DEscalate the situation to management because it is affecting the team.
29A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?- ATalk to the customer and project team member separately to assess the issue and decide on the next steps.
- BRemove the project team member immediately and assign the pending activities to other team members.
- CTell the customer that they do not have the authority to remove project team members.
- DAsk the project team member to call the customer to apologize for their behavior.
30An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.
What should the project manager do?- AAdd 4 additional weeks to the schedule and request additional resources.
- BAsk the sponsor to obtain a special work perms to continue work.
- CReview the project management plan to see the impact of the possible delay.
- DCrash the resource management plan to keep the schedule on track.
31A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B.
The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?- AWork with the organization's real estate department and reach out to the local government to identify the best location for the store.
- BWork with the local government to build the profiles of employees that will be working in the store.
- CWork with the organization's legal department to identify local regulations to ensure project compliance.
- DWork with the organization's project management office (PMO) to build a project team of residents located in the city.
32The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.
What should the project manager do?- ADetermine the risks and identify a resolution during the retrospective meeting
- BInform stakeholders about the delay during project updates
- CDetermine cross-dependencies and plan a spike in the next spont
- DDiscover the gaps in the communications management plan and address them accordingly
33An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner's system being unavailable which could impact the project negatively What key activity is needed to ensure the project's success?
- ACommunicate to the project stakeholders that full integration may not be possible and that the project will potentially be delayed as a result.
- BEliminate the risk by mandating the partner to change the system settings to facilitate an easier integration with the new solution
- CContinuously monitor the risk of the partner system's unavailability, and put the proper resolution plans in place in case the risk materializes into an actual issue
- DMitigate the risk by developing alternative plans to make the solution ready and available without full integration capabilities
34A company is planning a digitization project. Which action should the project manager take first when defining the project scope?
- AAssess the current state process to define the scope of the digitization.
- BDigitize the current state process exactly as defined.
- CRedefine the current state process to scope the supporting software.
- DDevelop the software that will support the current state process.
35The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.
What is the project manager's priority in this situation?- ARequest that the team member gel the contract signed as soon as possible
- BDetermine a mitigation strategy to move the project forward
- CTake over contract negotiations for the team member to speed up the process
- DAssist with the removal of impediments and blockers so that the project can continue
36During the execution of a financial project, a project manager met with the project team weekly to evaluate the project's progress. However, the sponsor requests that project performance be checked daily. The key team members disagree with this requirement and argue that they do not have enough time to go to daily meetings because they are at an executive level.
What should the project manager do first?- ANegotiate with the key team members to send a daily report and let the sponsor know that the project cost will increase
- BRecommend to the sponsor that performance of the project be reviewed once per week.
- CReview the communications management plan and submit a change request if required.
- DEvaluate the capacity of each team member to attend daily meetings in person or virtually and reduce the time of each meeting.
37A senior manager attends one of the project review meetings and expresses concer that the project will not meet the quality standards. What should the project manager do?
- AEstimate the backlog items to forecast quality.
- BAsk the senior manager to approve the user acceptance testing (UAT) plan.
- CReview the quality management plan with the senior manager.
- DInform the senior manager that there are approved quality standards.
38A newly hired team member just joined the project team and reports directly to the project manager. In the first week, this new member tells the project manager that there is a task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?- AGuide the team member on how to resolve the conflict.
- BAnalyze the project schedule and look for alternatives.
- CPerform crashing and/or fast tracking of the schedule.
- DMeet the team member and try to plan a course of action together.
39During a regular project progress meeting, the CEO informed the project manager that a major stakeholder has been unaware of recent developments on the project. The project manager is sure that the stakeholder was duly identified and classified in the stakeholder register.
Which project document should the project manager review in order to determine the reason for this issue?- ARequirements traceability matrix
- BStakeholder register
- CStakeholder engagement assessment matrix
- DIssue log
40The following table shows the business value created and the development effort required to implement various features in a product
Which feature should the team prioritize first? Enter the feature name in the box below
- AĐáp án ko có
- BĐáp án ko có !
41A project manager is managing a mobile application development project when one of the experienced team members starts missing deadlines. The delays will impact project implementation.
What should the project manager do next?- AMeet with the team member to understand their concerns and/or issues.
- BConvene a team meeting to encourage and motivate the entire team.
- CAssign an additional resource to help the team member with the tasks.
- DAsk the team member's functional manager if there are any known issues.
42The marketing team is transitioning to using hybrid approaches for their projects. The marketing director is not knowledgeable about hybrid methodologies and the project manager needs the director's support as the marketing director is a key stakeholder.
What should the project manager do to obtain the support?- AAsk the marketing director to participate in daily meetings
- BMentor the marketing director on hybrid approaches
- CAsk the marketing team members to coach the director
- DTram the marketing team and keep the director informed
43During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.
What should the project manager do next?- AIncorporate the changes in the last sprint before the first release.
- BCall for an internal meeting to discuss the changes and their value.
- CAsk the product owner to prioritize the backlog with the project team.
- DRequest the scrum team to prioritize the product backlog.
44A project manager recently finished a project and started managing a new project with a different supervisor.
As part of the early project activities, the supervisor from the
original project is assigned to the team as a nonsupervisory resource and immediately begins challenging all decisions made by the current supervisor.
What should the project manager do to resolve this conflict?- AGive the project team time to work through the issues with the new supervisor.
- BEnsure the new supervisor takes the lead when being challenged.
- CImmediately remove the resource from the project team.
- DCommunicate with the resource on the roles and responsibilities of this project.
45The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?
- ASchedule a time to negotiate a trade-off regarding the quality of the product with the customer
- BMeet with the risk manager to identify potential threats related to the schedule delay.
- CSet up a meeting with the project sponsor and submit a change request to the scope of the product
- DStart the project plan for the scope and quality and identify options to deliver and meet stakeholders expectations
46Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration.
Stakeholders are not feeling confident about the project outcome. What should the project manager have done to prevent this situation?- APerformed a stakeholder analysis when the sponsor joined the project
- BHeld a governance meeting to review the project increment
- CConducted a product iteration review with the new project sponsor
- DEscalated the issue to ensure the increment would be approved
47In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?
- AAssign the tasks to another resource, and ask the resource to work double shifts
- BUpdate the schedule to reflect the project's changes in duration
- CAsk human resources (HR) for a replacement, and update the nsk register
- DUpdate the resource management plan and resource allocation chart accordingly
48A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done What kind of leadership style should the project manager use at this stage?
- AA directive style that makes decisions for the group to reach early outcomes
- BA leadership style that coaches people who want help and fosters greater team collaboration
- CA passive leadership style that allows the team to self-organize until the norming stage is reached
- DA democratic style that uses techniques where majority opinion prevails
49During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?
- AIdentify the problem's root causes and define the ground rules with all project team members to minimize interferences
- BHire a coach to help all project teams to improve their abilities to solve problems on their own.
- CReunite with the project team members affected and tell them not to reduce the team's capacity
- DRecommend to the project team members that they should improve their planning and make their stones smaller
50A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the team realizes that it is not possible to deliver all the features in the required time.
What should the project manager do to ensure success?- AIncrease the capacity of the team to deliver the completed backlog on time.
- BAsk the customer to reduce the backlog to meet the launch date.
- CAssist the team in defining a minimum viable product (MVP) by the launch date.
- DSchedule a meeting with the stakeholders to review the contingency plan.
51A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?- AProvide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.
- BInvite the product owner to future demonstrations where they can provide feedback.
- CProvide access to the latest user acceptance test (UAT) environment so they can see the solution.
- DRemind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.
52In an agile project that is about 45% complete, most team members are siloed and lack an understanding of each other's work. What would have most likely caused this communication breakdown?
- AThe sprint review meetings were not held regularly.
- BThe daily standup meetings were not consistently attended.
- CThe project manager failed to develop a communications management plan.
- DThe weekly project status reports were not published regularly.
53A large organization decided to adopt an agile methodology based on the trends seen in the industry. The organization invested a large amount of money in adopting it, but after a few months, the implementation failed.
What should the project manager have done differently to avoid the implementation failure?- AConducted agile training for all employees ranging from the project teams through mid- level to upper-level management.
- BConducted a postmortem and captured the learning in organizational process assets (OPAs) for future use.
- CAssessed the organization's culture, performed a suitability analysis, and determined the future state.
- DHired a third-party agile delivery team to do the implementation.
54A prefeasibility study for a new renewable energy project is nearing approval. To ensure that the project time lines are maintained, activities associated with the feasibility study must continue while the prefeasibility study is being approved.
How should the project manager proceed?- AProceed with both the prefeasibility and feasibility studies in parallel while waiting for (he final approvals
- BInclude the feasibility activities in the prefeasibility study and apply for a change of scope and budget.
- CObtain approval to proceed with the feasibility study as a parallel activity while the prefeasibility study is approved
- DSecure approval of the prefeasibility study before proceeding with the feasibility activities.
55A project is in the execution phase During a few planning sessions the team brought up dependencies and risks based on their knowledge of other project. The project manager also received questions from the company in terms of how and when the team planned to perform acceptance testing and training activities. What should the project manager do next?
- ADocument the project management plans and share them with the company and all team members via email for review
- BCreate a log to track risks assumptions issues and dependencies and establish a periodic review with the stakeholders
- CAdd contingency m the schedule to account for dependencies and risks then review rt with the team
- DEngage with the company and the project team to determine the best course of action
56A key stakeholder who is frustrated by the lack of transparency of IT projects declines an invitation to participate in the new project meetings.
What should the agile project manager do to engage the stakeholder in the project?- APresent the project management plan to the stakeholder and reassure them that they will receive regular project updates.
- BIntroduce the stakeholder to the project team and invite them to the next iteration review meeting with the IT team.
- CBuild trust with the stakeholder by keeping project commitments and use demo sessions to gather feedback and realign goals.
- DUse stakeholder mapping to document the level of influence and interest for the next iteration planning meeting.
57A project manager is managing a new development program to automate some technical functions. During project kickoff, the project manager expresses the need for a technical architect to support the project for a moderate amount of time. The project sponsor informs the project manager about an existing technical architect who possesses valuable knowledge but is already assigned at the portfolio level.
What engagement model should the project manager use for the technical architect role to ensure project success?- AHire a new technical architect who would be solely dedicated to the current project.
- BShare the existing technical architect so they can be allocated to the current project and other projects.
- CHire a new technical architect who would be shared between the current project and other projects.
- DAssign the existing technical architect to solely be dedicated to the current project.
58During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?- AInclude additional mitigation actions against feature defects and update the risk management plan.
- BAssess the relevance of the feature and then analyze the submission of a change request to descope it.
- CImprove the control quality process by implementing additional testing to minimize the defects before the go-live milestone.
- DDetermine if business value will be delivered without this feature. and try to fix the defects after the go-live milestone.
59A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment What should the project manager do?
- AEscalate the issue with an impediment to the project sponsor
- BUse the contingency budget to implement schedule compression
- CImplement the mitigation plans listed in the organizational process assets (OPAs)
- DReassess the issue as part of monitoring and controlling
60A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager do to get this information?
- AOrganize a one-on-one conversation with each stakeholder.
- BRequest stakeholders articulate their motivations at the kick-off meeting.
- CEmail project objectives to all stakeholders and ask for endorsement.
- DIdentify each stakeholder's motivations from the business case.
61On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices.
What should the project manager do next?- AUpdate the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.
- BHire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.
- CRequest that the offices in overseas locations work overtime to mitigate schedule slippages.
- DUpdate the schedule to reflect the holidays and notify the project sponsor of the delayed completion.
62A project is delayed due to an undelivered component, which was caused by a conflict between the procurement lead and the contracts manager. The project manager schedules a meeting with the two stakeholders to resolve the issue.
What role does the project manager play in this situation?- AAccommodator
- BMediator
- CArbitrator
- DConciliator
63A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
- AUse the project's contingency budget
- BCreate a change request with the scope of the new internal projects.
- CInfluence the client to initiate a new project.
- DCreate a work breakdown structure (WBS) of the new scope with the internal projects
- EManage the quality of the delivery
64A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented What should the project manager do?
- AAsk the team member to learn the new system as on-the-job training
- BIssue a change request to extend the project schedule
- CEscalate the team members performance to the project sponsor
- DAssign an experienced resource to support the team member
65A financial company is developing a new application for mobile banking using a hybrid approach The project is delayed as the product concept has not yet been developed to the key stakeholder s satisfaction despite multiple design iterations. The key stakeholder has now started participating in all daily standups. The project manager has observed that the key stakeholder's presence has had a negative impact on the team's morale, while also impacting productivity How should the project manager ensure that the stakeholder s issues are addressed effectively without impacting the team?
- ASet up a meeting with the stakeholder to address their concerns directly
- BMove to a predictive design-and-requirements gathering approach
- CTalk to the team separately to address the stakeholder's concerns
- DSchedule a team retrospective and invite the stakeholder
66A project manager Is transitioning from a predictive We cycle project to a new agile project How should the project manager manage and control the scope for the new project?
- ACreate a scope baseline and put the rest as backlog activities.
- BEstimate the work the team can complete and define story sizes to keep the project under control.
- CDevelop a plan to complete more work In less time.
- DSpend a short amount of time defining the scope and building prototypes to refine the requirements.
67A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the project?
- AConfer with team members.
- BReview with security experts.
- CSchedule regular project audits.
- DDiscuss with the customer.
68A project manager is working on an enterprise resource planning (ERP) initiative that contains stakeholders spanning numerous business lines. The project manager begins to identify, evaluate, and categorize the stakeholder relationships to the program.
What is the purpose of this process?- AIdentify all stakeholders who can negatively affect the project.
- BIncorporate the needs of all stakeholders into the communications management plan.
- CIncorporate only primary stakeholders into the communications management plan.
- DIdentify all stakeholders who can positively affect the project.
69The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .
What should be the priority order in the product backlog?
- ARisk3, Risk 1, Risk2, Requirements, Requirement 1. Requirement2
- BRequirement 3, Risk 3, Requirement 1, Requirement 2, Risk 2
- CRequirements, Requirement 1, Requirement2
- DRequirement 3. Requirement 1, Risk 3, Requirement 2, Risk 1, Risk 2
70A project team is globally distributed with team members living and working in different time zones. The project manager is trying to get the team to collaborate effectively.
Which three actions should the project manager take to accomplish this goal? (Choose three)- ARequire the team to have daily mandatory meetings with the project management office (PMO).
- BRecommend the use of formal written documentation in all project communications.
- CReview the communications strategy with the team regularly with a view for continuous improvement.
- DSend out a survey to review the preferred method, time frequency for communications.
- ECompile a communications management plan with input from all stakeholders and distribute for review and approval.
71An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.
What should the project manager recommend?- AEnsure the product owner determines the priority based on a product roadmap. release plan, and iteration plan.
- BAsk the team to prioritize the high-priority items based on what they feel is a logical sequence to build.
- CAsk the team to prioritize the high-priority Items based on the release plan and what allows tor testing most effectively.
- DDiscard the current categorization of requirements as high, medium, and low and prioritize numerically.
72An agile team has completed an iteration and delivered the agreed features to the customer. In a surprise to the team, the features are not accepted by the customer. The project team conducts a root cause analysis.
What should the project manager do to avoid this situation in the future?- AEnsure that customer requirements do not change from the start of the project.
- BEnsure that the definition of done (DoD) is well defined and complete for future iterations.
- CEnsure that the development and quality assurance team members implement the feature correctly.
- DEnsure that the team facilitator allocates tasks correctly to team members.
73A project manager is reviewing the requirements of a large program. Which requirements should the project team prioritize to avoid getting fines?
- ADeveloping new product lines
- BComplying with new regulations
- CEstablishing company processes
- DCertifying sustainable products
74A newly appointed product owner is working with a project team that is using agile for the first time. The product owner is constantly disrupting various team members throughout the day to discuss progress. This has resulted in the team feeling micromanaged and frustrated because of the constant disruptions.
How should the project manager proceed?- AInvite the product owner to attend daily standup meetings so they can assess progress.
- BSet up a feedback session with the product owner once a week so they can assess progress.
- CInstruct the team to refer the product owner to the project manager for information.
- DInvite the product owner's functional manager to a feedback session to escalate the issue.
75A final iteration is underway and a project team is about to complete development Planning tot the product release is about to start. One stakeholder raised a concern about the product not being compatible with a new technology that has been adopted in the market How should the project manager address this issue?
- AAssess the business value impact and review the product roadmap to include any changes
- BSchedule a retrospective to understand why the new requirement was not included in product backlog previously
- CStop the product release and start adding new user stones to the product backlog for any new requirements
- DProceed with product delivery as planned and start a new requirement analysis for the next iteration
76A project manager is overseeing a project as part of a program geared toward a major technology disruption.
The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past. However, the team complained that they previously experienced a lack of direction during project execution and are a traid of the same issue in this project.
Which two actions should the project manager take to ensure that this issue does not occur in this project?
(Choose two)- AKeep the team engaged and focused on the project's direction.
- BEncourage the team to do a brainstorming session and provide a mitigation plan.
- CFocus on the resource management plan and track project progress,
- DSet a clear vision for the project and ensure it is visible to all stakeholders.
- EOrganize a team-bonding activity and invite an external manager to speak to the team.
77A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project.
The customer warns that previously, this defect negatively affected the project schedule. What should the project manager do first?- AUpdate the risk management plan.
- BExtend the timeline of the project.
- CCheck the organizational process assets (OPAs).
- DAcquire knowledgeable resources.
78A project manager has been authorized to begin a project and realizes that an effective high- performing team is needed to finish the project successfully. What should the project manager do next?
- ASelect members for their skill or potential.
- BEstablish the project scope and set clear team objectives.
- CSet performance standards and direction.
- DHold early kick-off meetings and regular weekly meetings.
79The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log How should this complaint be addressed?
- ARequest that the issue be included in the next board of directors meeting to explain all of the needs
- BAdd the complaint to the product backlog to be addressed in the next sprint
- CAsk the operations director to define the acceptance criteria to make clear the delivery is correct
- DInvite a member of the operations team to be part of the validation and sprint meetings
80A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.
What should the project manager do?- AAdvise the teams to follow the company's existing project management approach.
- BFlow the teams to continue using their approaches and gradually adapt to a hybrid model.
- CLet a senior team member select the approach that is appropriate.
- DInsist the teams both follow either a predictive or agile approach.
81During a system demo, a project stakeholder rejects the features completed from the most recent user stories.
According to the stakeholder, the product does not meet the quality standards required by regulations.
What should the project manager have done to avoid this?- AReviewed with the product owner that all the stories worked on in the iteration were in the project backlog
- BEnsured that the project sponsor understood the scope of the project to avoid any future complaints
- CReviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration
- DEnsured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks
82A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?- AIncrease the project budget by 10% for team-related activities and awards.
- BPlan to implement team-building strategies throughout the project.
- CAsk the functional manager to motivate the team outside of the project.
- DColocate the team to encourage more motivational team activities.
83A team member is always late to work. The project manager is concerned that this may affect the motivation of other team members The project manager tells the new team member to align with the team's principles and arrive on time What kind of conflict resolution did the project manager apply in this situation?
- ASmooth/accommodate
- BCompromise/reconcile
- CCollaborate/problem solve
- DForce/direct
84A project manager is managing multiple teams. One team member complains to the project manager about the favoritism shown by a team lead to another team member and cites multiple instances.
Risk Response Strategies Analyze if someone else could contribute Record the observations and move ahead Check for options to exclude the stakeholder What should the project manager do to resolve the team member's concerns?- AUse the withdraw/avoid technique to allow the individuals to resolve the issue between themselves.
- BUse a problem-solving approach and set up a discussion with the team lead and team member.
- CEstablish guidelines for team leads to ensure that all team members are appropriately treated.
- DProvide direction to the team lead on how to resolve the issue with the team member directly.
85Many issues have been encountered in a project due to the low competence of the team members. These issues might lead to poor project performance and potentially to project termination.
What should the project manager do?- AOrganize a brainstorming session with the project team to address the issue.
- BAdvise the project team on the importance of team engagement,
- CInvest in coaching and training for all project team members.
- DEscalate the issue with the human resource (HR) department to take action,
86In experienced project manager has never managed an agile project until now. Due to the uncertainty of the project, the project manager is struggling with the definition of the project scope and is taking a long time trying to define it.
What should the project manager do?- ASubmit a change request to leverage previous experience and manage the project using a predictive approach
- BSchedule a daily project definition meeting with the team to define the project scope before starting the execution.
- CStart executing the project as the scope will be defined and redefined throughout the project.
- DObtain partial approval from the product owner to baseline the project scope plan before starting the execution.
87In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.
How should the project manager handle this situation?- AReview the iteration backlog because the product definition has changed and needs to be reassessed before continuing the project.
- BContinue work and ask the product owner to assess the changes and add/remove the stories as needed in the backlog.
- CAsk a business analyst to assess the changes and then add/remove the stories in the backlog and prioritize them by business value.
- DAsk the product owner to add new changes to the bottom of the backlog in order to handle the modifications as a change request.
88A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion. What should the project manager do?
- AAssume the role of the product owner while the product owner gets familiar with the product.
- BSchedule time to share insights with the new product owner about the product and project information.
- CWork with the project management office (PMO) manager to generate an onboarding plan for the new product owner.
- DOrganize a team-building activity and ask the team to respect the opinions of the new product owner.
89During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
- AReview the project time line and find opportunities to reduce the project schedule.
- BReview the budget with the project sponsor and ask for an increase to the budget
- CReview the backlog and find opportunities to reprioritize the work and reduce the project scope
- DReview the resource management plan and find opportunities to reduce project costs.
90A team has been struggling with various issues during the course of an iteration. The project lead facilitates a discussion of the issues and the team forms new team agreements. During the next iteration, some of the same issues appear again What should the project lead do next?
- ANotify senior management of the issues and have them review the importance of agreements with the team
- BChallenge the team to determine if the issues surfaced again because agreements were not followed
- CPost the agreements in a conspicuous place where all of the team members can see them.
- DLet the team self-organize and determine the best means to prevent the issues from occurring again
91An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.
What should the project manager do to avoid this situation in the future?- ACreate a team incentive program with prizes, allowing the team members to work overtime to find defects.
- BReduce the release cycle and invest more time on stabilizing the current features instead of releasing new ones.
- CHire a quality assurance specialist and integrate a second phase of testing into the current project life cycle.
- DUse the next retrospective to understand the root cause of the quality issues and have the team come up with an action plan.
92A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?- AAsk the client how the project will affect the client's organization and recommend that all impacted parties be involved.
- BInvolve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.
- CPerform an independent analysis to determine the stakeholders from the client's organization.
- DDefer to the judgment of the client's executive sponsor since they will determine whether the project is a success.
93A project manager gas been asked by the project manager office (PMO) to select the appropriate project management approach for three upcoming projects. Match the projects on the left with the approach that should be used on the right.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
94A project manager is new to hybrid project management and is worried about the project because it has a high level of requirements uncertainty. The team has experience with hybrid projects, performs daily standups, and is committed to the project. The project manager is concerned about losing control of the project and would like to have a more central role.
How should the project manager address this issue?- AModify the daily standup meetings to include project status reporting.
- BEscalate the issue to the change control board (CCB) and ask for advice.
- CAdopt the role of supporting and empowering the project team to do the work.
- DChange the approach for the project to a predictive approach.
95An executive sponsor of a predictive project asked a project manager experienced in agile to assess if a project could be executed using an agile approach What factor should the project manager consider when determining if the project is suitable for an agile approach?
- AThe project is an information technology project and has minimal impact to the organization
- BThe project scope can be decomposed into smaller parts, the first representing a minimum viable product (MVP).
- CThe project scope is well defined and the requirements are prioritized
- DThe project team has a colocated space and is capable of working together
96An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply Which two actions should the project manager take? (Choose two)
- AAsk the team members to analyze the impact of including this regulation
- BAsk the stakeholders about the priority of this regulation
- CAsk the product owner to include the requirements in the product backlog
- DAsk the security department for details about regulations
- EAsk the team members to include the requirements in the next iteration
97An organization started the process of a digital transformation and is trying to change its culture from a predictive to a more agile approach. The project manager leading the change management process identified some knowledge gaps of key team members, which could prevent the transformation from happening as planned.
What should the project manager do?- AProvide mentoring for the key team members on agile practices and support the team with training and encouragement.
- BCreate an agile conduct guideline and ensure that all team members follow the rules stated in the document.
- CReplace the key team members with new resources who are already aware of the agile mindset.
- DProvide directions to the team members on how to accelerate the company's transformation, bringing the project back on track.
98A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task What should the project manager do to obtain the information required by the developer?
- ARequest direction from the project sponsor
- BWrite an email to the client requesting clarification
- CWeek support from the development manager.
- DWork with the product owner to clarify the requirement
99The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)- AInform the customer that moving the milestone has a very high impact on project cost.
- BEscalate the Issue to senior management so they can impose a solution on the customer.
- CConvince the customer to keep the requirements as is and not move the milestone.
- DReview the customer's priorities regarding the desired requirements for the milestones.
- EDiscuss which requirements can be delivered faster with the project team.
100During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version How can the project manager prevent this outcome in the new project?
- AHire a team of external users to perform acceptance testing on the product.
- BDefine a user focus group as external stakeholders with a high influence on outcomes
- CHire a consultant to perform a benefit analysis as an input to the project charter.
- DDefine a high-level risk and plan mitigation after completing the work breakdown structure (WBS)
Information
- Description
- Công nghệ số Quiz on PMP exam 12, created by Lê Hiếu on 16/08/2022.
- Author
- Lê Hiếu
- Language
- English
- Views
- 23
- Tags
- Rating
- No ratings yet Rate this quiz