  1. 1 How far away must spoil be kept from the side of a trench?
    1. A1.2 m
    2. B0.9 m
    3. C0.6 m
    4. D0.4 m
  2. 2 Which of the following is used to measure the depth of an excavation?
    1. Agrade stick
    2. Bsurvey transit
    3. Cbatter board
    4. Dstring line
  3. 3 What is the slope ratio to use when excavating Trench walls?
    1. A1 horizontal : 3 vertical
    2. B3/4 horizontal : 1 vertical
    3. C1 horizontal : 1 vertical
    4. D1 horizontal : 3/4 vertical
  4. 4 What is the minimum number of consecutive control points needed when setting up a string line or batter boards?
    1. A1
    2. B2
    3. C3
    4. DThe amount required to effectively align a grade pole with the excavation
  5. 5 What is the name of the traffic control zone just before the work area?
    1. Abuffer zone
    2. Btransition area
    3. Ctermination area
    4. Dadvance warning area
  6. 6 Which one of the following considerations determines whether excavations are done manually or by machine?
    1. Adepth of trench
    2. Bmunicipal regulations
    3. Ctype of pipe to install
    4. Denvironmental impact
  7. 7 Who are traffic control measures designed to protect?
    1. Apedestrians, motorists and operators
    2. Bgeneral public
    3. Cwastewater system operations
    4. Dcrew members
  8. 8 When is it appropriate to use hydraulic jetting or trench sinking as a compaction technique?
    1. AWhen using sand for backfill material
    2. BOn aggregate with low moisture content
    3. CDuring dryer weather conditions
    4. DWhile trenching with a hydraulic excavator
  9. 9 Where should material excavated from the trench be placed?
    1. APiled back at least 0.6 m from the trench
    2. BRemoved from the site
    3. CPiled close along the sides of the trench
    4. DPiled on the street side of the trench whenever possible
  10. 10 At what depth is shoring normally required?
    1. Aover 2m
    2. Bover 1.2 m
    3. Cover 1 m
    4. Dat 0.5 m

Information

Description
Quiz on WWC1 Unit 10 - Construction Methods, created by Cam Llewellyn on 11/04/2025.
Language
English
Views
0
Tags
eocp
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?