1John is the Product Owner, during the Daily he realized that the work is delayed. What should he do?
- ANothing
- BNotify the CEO
- CNegotiate a reduction of the scope, guiding the team to focus on the goal
- DCancel the sprint and change the team of developers
2Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
- ANothing
- BDo not accept cancellation as this is your prerogative
- CAgree with Scrum Master
3Peter is a developer, tested in the user story and noticed a problem. Which action should Peter
- ACancel user history
- BNotify the development team and fix the problem
- CNotify the test team
4Is Product owner and Scrum master possible in the same person for the same project?
- ARichtig
- BFalsch
5According to the Scrum guide, can we use parts of Scrum?
- ARichtig
- BFalsch
6Can we change the size of the sprint during its execution?
- ARichtig
- BFalsch
7The best scenario for using Scrum is?
- APredictive
- BComplex and adaptative
- CComplex and predictive
- DAll of these answers are correct
8The maximum length of the Sprint Retrospective(its time box) is:
- A3 hours for a monthly Sprint, proportionally less for shorter Sprints
- B4 hours for a monthly Sprint, proportionally less for shorter Sprints
- CAs long as needed
- D1 day
9How many meetings are defined in Scrum?
- A1
- B2
- C3
- D4
10What is the purpose of the daily meeting?
- ATeam meeting for inspection and adaptation
- BA formality of Scrum
- CTo inform the Product Owner
- DNone of the given answers
11When does the development team create the sprint backlog?
- Adaily
- Bplanning
- Creview
- Dretrospective
12At the end of the sprint is a product increment that will go into production?
- ARichtig
- BFalsch
13After the start of the sprint, what product owner will do?
- AEstimate the tasks
- BSupport the team in the current sprint and detail the next sprint
- CAnswer the three questions on the daily
14Is it true that the Scrum Master is responsible for the ROI of the product?
- ARichtig
- BFalsch
15What is the role of the project manager in the Scrum framework?
- AControl the timeline
- BDelegate tasks
- CThere is no such role in the framework
16When to cancel a sprint?
- AWhen dev team can not deliver
- BWhen sprint ends
- CWhen the goal does not make more sense
17Scrum master ensures that Scrum is being applied correctly?
- ARichtig
- BFalsch
18How does the product owner help the development team?
- ADetailed all product backlog
- BClearing up doubts about backlog items
- CWith the help of requirements analyst
- DHe does not help the team.
19When a backlog item was set to high priority, for what situation should it be considered?
- ADefinition of done
- BDefinition of Timebox
- CDefinition of ready
- DNone of the answers
20Does the development team need to be multifunctional?
- ARichtig
- BFalsch
Informationen
- Beschreibung
- Quiz am Scrum Master - Simulado 3 - Inglês, erstellt von canaldevbr com am 08/05/2018.
- Autor
- canaldevbr com
- Sprache
- Português
- Aufrufe
- 154
- Schlagwörter
- Bewertung
- 5,0 von 5 · 1 Bewertung Bewerte dieses Quiz