NCC Vol 1 – Section A QUIZ #3: FRLs
Fragen in diesem Quiz (10)
1How are FRLs determined?
- AIt is identical with a prototype that has been submitted to the Standard Fire Test and has become certified.
- BIt differs in only a minor degree from a prototype tested by the Standard Fire Test and has become certified.
- CIt is designed to achieve the FRL according to the appropriate AS (depending on the material).
- DAny of the above.
2If the fire-resisting covering of a steel column is lightweight construction, the construction must do what?
- AComply with requirements from Section C.
- BHave materials of a high FRL covering it.
- CBe surrounded by masonry.
- DComply with requirements from Section F
3If a non-loadbearing element is able to be used for a purpose where the Deemed-to-Satisfy Provisions prescribe an FRL, what does this mean for the non-loadbearing element?
- AIt doesn't need to comply with the structural adequacy criterion.
- BIt doesn't need to comply with the integrity criterion.
- CIt doesn't need to comply with the insulation criterion.
- DIt doesn't need to comply with any of these criteria.
4Which of the following criteria do fire-resisting levels (FRLs) grade?
- AStructural adequacy
- BIntegrity
- CInsulation
- DCladding
5What does FRL stand for?
- AFire-rating level
- BFire-resistance level
- CFire-response level
- DFire-requirement level
6Given the following FRL, 90/90/90; what does each 90 mean?
- A90 minutes
- B90 joules
- C90 newtons
- D90%
7Given the following FRL, 240/240/240; what criteria does the first '240' stand for?
- AStructural adequacy
- BIntegrity
- CInsulation
- DCladding
8Given the following FRL, 180/180/180; what is the correct order for the criteria?
- AIntegrity/Structural Adequacy/Insulation
- BStructural Adequacy/Insulation/Integrity
- CStructural Adequacy/Integrity/Insulation
- DInsulation/Integrity/Structural Adequacy
9Given the following FRL, 120/–/–; what do the dashes stand mean?
- AThere is no requirement for this criterion.
- BThe requirement has not been set for this criterion.
- CDashed criterions are the same as the number before it.
- DIt requires the highest possible level for that criterion.
10Given the following FRL, 120/120/120; what criteria does the third '120' stand for?
- AStructural adequacy
- BIntegrity
- CInsulation
- DCladding
Informationen
- Beschreibung
- Test on FRLs, outlined in Section A of Volume 1 of the National Construction Code (Australia). [Taken from 2012 edition of the NCC]