  1. Schedule management plan

    • The plan list any methodologies or tools you planned to use when sequencing.
  2. Activity list

  3. Activity attributes

    • This include information about each activity, including known predecessors and successors.
  4. Milestone list

  5. OPAs

  6. EFFs

  7. Project scope plan

  8. Precedence diagram methods (PDM)

    • Network diagram with dependencies
    • leads and lags
  9. External dependencies

  10. Discretionary dependencies

    • Por su naturaleza tengo la opcion de decidir en que momento hacerlo
  11. Mandatory dependencies

  12. Internal dependencies

  13. Project schedule network diagram

  14. Project document updates

    • You don't need to know exactly which documents change as an output to this process. All you need to know is that project document updates are an output.
    • Activity attributes
    • Risk register
    • Activity list
      • If you find a new activity while sequencing updates need to be made to the activity list.
  15. IMPORTANTE estas 3

    • Esta no viene en el examen

Bilder und Dateien der Mindmap

  • SAB#53_Seq_Activities
  • SAB#53_Seq_Activities
  • SAB#53_Seq_Activities

Informationen

Beschreibung
Certificacion TIME MANAGEMENT Mindmap am SAB#53_Seq_Activities, erstellt von Maria Gonzalez am 11/04/2015.
Erstellt von
Maria Gonzalez
Aufrufe
4
Verlauf
  • Erstellt von Eric Martinez · 11 Apr 2015
  • Kopiert von Maria Gonzalez · 11 Apr 2015
Bewertung

Mehr zu Activity Sequencing and Dependencies

Feedback

Worum geht es?

Was sollen wir als Nächstes hinzufügen?