Quiz
Earned Value Management Knowledge Test
Dieses Quiz enthält Fragetypen, die sich im gewohnten Player öffnen.
Fragen in diesem Quiz (13)
1You have a construction project to be completed in 12 months and the total cost of the project is $134,567. Six months have passed and you've have spent $65,488 and the schedule says that 50% of the work should be completed. Upon closer review you find that only 42% of work has been completed.
- A$134,567
- B$67,283.50
- C$56,518.40
- D$65,488
- E-$8,9696
- F$10,765.10
- G.84
- H.863
- I$155,929.32
- J$90,441.32
- K-$21,262.32
- L1.13
2You have a construction project to be completed in 36 months and the total cost of the project is $1,534,567. 18 months have passed and you've have spent $869,498 and the schedule says that 50% of the work should be completed. Upon closer review you find that only 56% of work has been completed.
- A$1,534,567.18
- B$767,283.59
- C$859,356.62
- D$869,498
- E-$10,141.38
- F-$92,073.03
- G.99
- H1.11
- I$1,382,492.95
- J$512,994.95
- K$152,074.23
- L1.02
3What is the formula for planned value?
- APlanned % complete x BAC
- BActual % complete x BAC
- CPlanned % complete x EAC
- DPlanned % complete x TCPI
4What is the formula for Earned Value?
- AActual % complete x BAC
- BActual cost spent to date
- CBAC x AC
- D(BAC-EV)/(BAC-AC)
5What is AC?
- APlanned cost at completion of project
- BAnnual Cost
- CActual cost for entire project
- DActual cost to date
6Cost Variance: [blank_start]CV = EV-AC[blank_end]
- ACV = EV-AC
7Schedule Variance: [blank_start]SV = EV-PV[blank_end]
- ASV = EV-PV
8Cost Performance Index: [blank_start]CPI = EV/AC[blank_end]
- ACPI = EV/AC
9Schedule Performance Index: [blank_start]SPI = EV/PV[blank_end]
- ASPI = EV/PV
10Estimated at Completion: [blank_start]EAC = BAC/CPI[blank_end]
- AEAC = BAC/CPI
11Estimate to Completion: [blank_start]ETC = EAC-AC[blank_end]
- AETC = EAC-AC
12Variance at completion: [blank_start]VAC = BAC-EAC[blank_end]
- AVAC = BAC-EAC
13To-Complete Performance Index: [blank_start]TCPI = (BAC-EV)/(BAC-AC)[blank_end]
- ATCPI = (BAC-EV)/(BAC-AC)
Informationen
- Beschreibung
- Project Management Quiz am Earned Value Management Knowledge Test, erstellt von Adam Odd am 27/06/2018.
- Autor
- Adam Odd
- Sprache
- English
- Aufrufe
- 8
- Schlagwörter
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz