1The product life cycle differs fromt he project life cycle in that a project life cycle:
- AProduce multiple projects within it
- BWill differ by industry
- CDoes not use a methodology
- DDictates the project management activities to be used
2A project is:
- AA set of sequential activities performed in a process or system
- BA revenue.generating activity that needs to be accomplished while achieving customer satisfaction
- CAn ongoing endevor undertaken to meet customer or market requirements
- DA temporary endevor undertaken to create a unique product, service, or result
3Project management is:
- AThe integration of the critical path method and the earned value management system
- BThe application of knowledge, skills, tools, and techniques to project activities to meet project requirements
- CThe application of knowledge, skills, wisdome, science, and art to organizational activities to achieve operational excellence
- DA subset of most engeneering and other technical disciplines
4Managing a project includes:
- ABalancing the competing demands for quality, scope, time, and cost
- BIntegrating requirements or profitability, low cost, and legal responsability
- CImplementation of software, gardware, and other system to enhance organizational efficiency
- DSupporting human factors, communications, discipline, and performance management
5A program is:
- AGroup of related tasks lasting one year or less
- BGroup of related projects managed in a coordinated way
- CProjects with a cost over $1 million
- DSequence of steps constituting a project
6Project managers or the organization can divide projects into phases. Collectively, these phases are known as the:
- AProject waterfall
- BProject life cycle
- CProject life stages
- DProjects life quality circle
7In understanding the project envirnonment, all of the following are true except:
- AProject are planned and implemented in a social, economic, and environmental context
- BProjects may have intended positive and/or negative impacts
- CProjects may have unintended positive and/or negative impacts
- DThe project team rarely should consider the political and physical environmental contexts of the projects
8In considering project stakeholders, the project management tema must do all of the folloqing except:
- AAs much as possible, create conflicts among stakeholders to allow the project tema to get its work done
- BIdentify the stakeholders
- CDetermine stakeholders' requirements and expectations
- DTo the extent possible, manage stakeholders' influence in relation to the requirements to ensure a successful project
9The project manager is more likely to have a full-time role in what type of an organization?
- AFunctional
- BWeak matrix
- CStrong matrix
- DSmall capitalization
10Your friend has been hired as a project manager at a new company. She has very little project experience but has been assigned a new project. The organization she will be wotking in is a matrix organization. She can expect communications to be:
- AComplex
- BNon-automated
- COpen
- DEasy
11The term "progressive elaboration" refers to:
- AConstantly changing project scope
- BAdding detail to project deliverables as the project moves from phases to phase
- CLetting team memebers make scope changes without customer approval
- DNone of the above
12Which statement best illustrate the concept of the project management constraints?
- AThe customer change request needs to go through an appropriate approval process
- BThe customer has requested extra features which will increase the time and costs of the project
- CThe customer has prioritized getting the work done quickly over the amount of money needed for the project
- DThe customer needs the project delivered before the end of the fiscal year
13The PMO in your organization has been established to improve project management processes and results. the PMO provides templates and procedures to the projects and periodically validates compliance with the documented procedures. The PMO can best be described as:
- AA directive PMO
- BAn asset to the organization
- CA non-stakeholder group
- DA controlling PMO
14The project management process groups are:
- APlanning, checking, directing, monitoring and recording
- BInitiating, planning, executing, monitoring and controlling, and closing
- CPlanning, executing, directing, closing, and delivering
- DInitianing, executing, monitoring, evaluating, and closing
15All of the following are characteristics of the project management process groups exept:
- AThe process groups are linked by objectives they produce
- BThe output of one process generally becomes an input to another process or is a deliverable of the project
- CAll of the processes will be needed on all projects, and all of the interactions will apply to all projects or project phases
- DWhen a project is divided into phases, the process groups are normally repeated within each phase throughout the project's life to effectively drive the project completion
16Which statement is more accurate:
- ASince management of a project os a finite effort, theinitiating process group begins the project and the closing process group ends it
- BIf a project is dividedinto phases, the process groups will only be utilized once during the project
- CRisk management is considered a process group
- DThe project management framework consists of nine process groups
17The following statements are true about the PMBOK guide, except:
- AThe PMBOK Guide provides and promotes a common vocabulary within the project management profession
- BThe PMBOK Guide is the mandatory methodology for projects
- CThe PMBOK Guide is a guide rather than a methodology
- DThe PMBOK Guide identifies the subset of the project management body of knowledge generally recognized as good practice
18Common inputs to the project management processes include:
- AOrganizational process assets, enterprise environmental factors, work performance information and project management plan updates
- BOrganizational process assets, change requests, project management plan, and enterprise environmental factor
- CProject management plan, project documents, and change requests
- DProject management plan, project charter, organizational process assets, project docuements, work performance data, and enterprise environmental factor
19You have assumed the responsability for a high-risk project that is instrumental to your company's growth. As you begin to evaluate the project, you take into consideration the availability of skilled resources that will be needed for the project. You are considering:
- AThe organizationa process assets
- BThe enterprise environmental factors
- CThe project management plan
- DThe organizational methodology
20You are new to the project organization within your company. You have been asked to develop a project management plan and you have sent an enquiry to the PMO asking for any type of templates or sample plans that may exist. The templates and sample plans:
- AWould be considered enterprise environmental factors
- BWould constitute the need for a scope change request
- Care not the most efficient manner of establishing the project documentation
- DAre oth components of the organization's process assets
21Which of the following is not a data analysis technique?
- ACost of quality
- BMind mapping
- CIteration burndowns chart
- DProposal evaluation
22A key role of the project manager is to manage the project knowlege. Which sequence is most accurate regarding project knowledge management?
- AOnce work performance information is analyzed it becomes work performance data. The work performance data is used to create the work performance reports
- BThe work performance report provides the work performance information and data
- CWork performance information is used to create the work performance reports. Work performance data is analyzed to become work performance information
- DThe work performance information is raw, and it is analyzed to create work performance data. The work performance data is used in the work performance report
23The difference between the project management plan and the project charter can be best described as:
- AThe project management plan is optional whereas the project charter is mandatory
- BThe project charter provides guidance to the leadership of the organization regarding the project whereas the project management plan provides guidance to the stakeholders
- CThe project management determines whether the project charter or the project management plan are needed on the project
- DThe project charter provides the project manager with authorization to complete the work of the project whereas the project management plan describes how the work will be defined, managed, and controlled
24Your team has submitted three change requests: Rquest #1 is to changethe status report due date from Friday to Thursady. Request #2 is to add an extra page to the new website that is under development. Request #3 is to replace the more expensive resource with a less expensive resource as the project is trending over budget. Which statement is most accurate?
- AOnly change request #2 would change the project baseline
- BAll three change requests would require a change to the project baselines as they are changing the project
- CChange requests #2 and #3 would require a change to the project baselines as they reflect material changes
- DNone of the change requests would require a change to the basiles, as the baselines are frozen and should not be updated
25Your customer unexpectedly the job-site and found a number of problems with the interior work in the building. Upon evaluating the identified problems, you agree that they need to be addressed. You:
- ASubmit defect repair change requests to the change control board without updating the project baselines
- BCreate a corrective action change requests and determine the impacts to the project baselines
- CYou have your team fix the problems without involving formal change control
- DWith your foreman, you re-baseline the project to incorporate the problems being resolved
26The bridge between project management processes are best described by the following:
- AThe processes are in order of importance
- BOne process must finish before the other process begins
- CThere is no bridge or correlation
- DProcesses are linked by the outputs that are produced
27The PMBOK Guide is:
- AThe guide for managing all projects consistently
- BThe standard for managing most projects most of the times
- CUsed only in the IT industry
- DNone of the above
28All of the following may be included in the project management plan exept:
- ASubsidiary plans
- BPerformance baselines
- CProject status reports
- DThe definition of project phases
29As PM you are evaluating the various stakeholders that will be involved in the project. You have identified the key players and are now considering their role and impact on the project. What tool would be most beneficial to develop next?
- AA risk register
- BA stakeholder register
- CA control chart
- DA stakeholder engagement matrix
30You have recently assumed the management of a high-profile, but confidential, projects for your organization that has been underway for more than six months. Unfortunately, the previous project manager left the company abruptly and there was no opportunity for training, transition, or handover. In order to get up-to-speed as quickly as possible:
- AYou notify the sponsor of the risk associated with the previous project manager'sexit to ensure they are aware of implications
- BYou request a copy of the project charter from the procurement lead to understand the benefits of the project
- CYou leverage the project management plan toget an understanding of the management approach for the project
- DYou request a meeting wich each team memeber to understand their role on the project
31The performance measurement baselines that are included in the project management plan are:
- AChange, quality, budget
- BScope, configuration, technical
- CQuality, time, budget
- DScope, schedule, cost
32In a stakeholder engagement matrix, stakeholders can be classified as all of the following except:
- AUnaware
- BDirecting
- CNeutral
- DLeading
33You have been assigned a new project with your consulting agency. You will be working with a number of internal teamsto develop an intranet to provide easy access to company information. Which statement is most accurate?
- ABecause it is internal project, you will not need a project charter but should have an agreement in place
- BBecause you work in a consulting agency, you must have an agreement in place
- CA project charter would be required but the agreement is not required
- DTo ensure the project has properly authorized, you will need to ensure there is both a project charter and an agreement in place in order to begin
34To initiate a project properly, business documents shouldbe created and/or evaluated to ensure that the project is worth the investment and should be pursued. Those business documents may include:
- AA business case and a benefits management plan
- BA charter and an agreement
- CA charter and a business case
- DA stakeholder agreement and a risk register
35One of your stakeholders has approached you with concerns about your current project. She was reviewing the business case and saw that the net present value (NVP) was only $280,000. However, the project is going to take four years to complete. Because the project is going to take four years, she is concerned that it is only going to have a $70,000 benefit. What statement is most accurate?
- AIf the organizational threshold for project profitability is more than $70,000 than the stakeholder is justified in being concerned
- BBecause the NVP is below the stakeholder's comfort level, the project should be cancelled
- CThe NVP is already discounted for the duration, indicating a $280,000 value, well aove the level of concern for the stakeholder
- DAs project manager, you are responsible for escalating the stakeholder's concern to the project sponsor
36The ____________ process creates the ________________ as an output, which documents the project conditions that are believed to be true and the project constraints.
- ADevelop project charter, assumption log
- BDevelop project management plan, subsidiary plan
- CIdentify stakeholders, stakeholder register
- DDevelop project charter, project charter
37These are action-based meetings attended by pre-qualified stakeholders or representatives to gather feedback:
- AFacilitated workshops
- BChartering sessions
- CMeetings
- DFocus groups
38Directions of stakeholder influence include all of the following, except:
- ASideward
- BInward
- COutward
- DDownward
39This stakeholder classification grid evaluates stakeholders based on their active involvement and their ability to effect changes to the project:
- AStakeholder cube
- BInfluence / Impact grid
- CPower / Interest grid
- DPower / Influence grid
40How is mind mapping used in planning stakeholders engagement?
- AIt is used to create a visual representation of the stakeholders and their relationships to each other and to the organization
- BIt is used to create an understanding of the root causes of the issues anticipated to occur with the stakeholders
- CIt is used to understand the minds, thoughts, feelings, and emotions of the project stakeholders
- DIt is used to illustrate the current state of the organization and the future state of the organization once the project is complete
41Which of the following would not be considered an input to evaluating and planning stakeholder engagement?
- AProject charter
- BAgreements
- CBenchmark study
- DProject management plan
42Your PMO has indicated that a WBS is recommended for all projects that are longer than three months in duration or are estimated to cost more than $100,000. The following statement is true about the WBS
- AThe WBS is another term for Gannt chart
- BEach descending level of the WBS represents an increasingly detailed definition of the project work
- CWork not in the WBS is usually defined in the scope statement of the project
- DThe WBS shows only the critical path activities
43As project manager, you are defining the project scope in association with your stakeholders and team members. As such, you are decreasing the probability of scope creep. The scope creep is:
- AA type of residual risk
- BAn activity that needs to be included in the project schedule
- CUnmanaged changes to the project scope
- DNone of the above
44As project manager, you are careful to follow the recommended guidelines for developing the WBS for your project. In the WBS, the total of the work at the lowest levels myst roll up to the higher levels so that nothing is left out and no extra work is completed. This is calles:
- AThe 80/20 Rule
- BThe WBS Rule
- CThe Hierarchical Rule
- DThe 100% Rule
45Which of the following statements is true about the WBS?
- AThe WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables
- BThe WBS is an unstructured list of activities in chart form
- CThe WBS is the same as the organizational breakdown structure
- DThe WBS refers to the bill of materials
46You have just been made the Project Manager of the ABC project. Your are trying to read the WBS and are unable to understand some of the WBS components. WHat would be your first step to understand this?
- ARefer to the WBS dictionary
- BRefer to the scope statement
- CRefer to the project charter
- DContact the previous project manager
47All of the following are true about the project scope statement except:
- AIt describes the project's major objectives
- BIt provides a common understanding of the project scope among all project stakeholders
- CIt describes, in detaile, the project's deliverables and the work required to create those deliverables
- DIt is an output of the validate scope
48What is the WBS typically used for?
- ATo organize and define the total scopeof the project
- BTo identify the logical person to be project sponsor
- CTo define the level of reporting the seller provides the buyer
- DAs a record of when work elements are assigned to individuals
49Which of the following is not true of the project scope management plan?
- AIt provides guidance on how project scope will be defined and documented
- BIt provides guidance on how project scope will be verified
- CIt provides guidance on how project scope will be managed and controlled
- DIt is separate from the project management plan
50Upon evaluating the work breakdown structure (WBS), you observe that work package 6.2.3 is included in the 6.2 and 6.3 control accounts. What is the next thing you should do?
- ABreak it down into two work packages, one for each control account
- BDo nothing as work packages can be related to multiple accounts
- CSubmit a scope change with an associated baseline update
- DEvaluate the workpackages in a QFD session
51The scope baseline includeallof the following except:
- AWBS dictionary
- BProject charter
- CScope statement
- DWBS
52The lowest level of a WBS isknown as a(n):
- AActivity
- BTask
- CControl account
- DWork package
53You have worked with the assigned business analyst to capture and document the requirements from the stakeholders. What is the next thing you do?
- ASeek sponsor approval on the requirements
- BDecompose the work into work packages to create the WBS
- CSubmit the changes to the steering committee to ensure alignment
- DAnalyze the requirements to determine what will be included in the project and create the project scope statement
54ABS Corp hase recently expanded its project management team as the company has been experiencing significant growth and acquiring many new clients for their software offerings. Upon being assigned your first project, the PMO contact has requested that you provide her with the requirements documentation once it is complete. Your project will be using the Scrum approach to product development. Which statement is most accurate?
- ABecause your project is an iterative life cycle, you will only have incremental requirements
- BThe requirements documentation for your project will be in the form of a product backlog
- CThere are no requirements documents in agile projects
- DGiven the approach that you are using, your project will have a requirements traceability matrix along with the requirements documentation
55The scope statement differs from the project charter, in that the scope statement:
- AMay be progressively elaborated as more information becomes known
- BDetails the milestone schedule
- CIs typically created by the project sponsor
- DWill include the sponsor name, authority level, and the project manager assigned to the project
56An output of the define scope process is the:
- AWBS
- BRBS
- CProject scope statement
- DSchedule delays control plan
57Your are in the process of developing your project schedule. Your determine that you are able to leverage a one-day lead foractivity 7.2.9. Which statement is least accurate?
- AThe successor activity ca start one day before the predecessor activity is completed
- BThe predecent activity can start one day before the subsequent activity
- CThe predecessor/successor activities have a finish-to-start relationship
- DThere is a preferred relationship between the predecessor/successor activities
58Which statement is most accurate regarding agile release planning?
- AThe roadmap drives the release plans which establish the iterations
- BThe features drive the product vision which establishes the tasks
- CThe iterations drive the tasks which establish the release plan
- DThe tasks drive the iterations which establish the prodcut vision
59The PERT estimate is nine hours. The best-case estimate is four hours and the worst-case estimate is 18 hours. Whatis the most-likely duration estimate for a beta distribution?
- A11 hours
- B9 hours
- C8 hours
- D5 hours
60The window installation is dependent upon the delivery of the windows. This is considered what type of a dependency
- AInternal
- BSoft logic
- CMandatory
- DPreferential
61When crashing a task, the project team needs to focus on:
- ANon-critical tasks
- BAs many tasks as possbile
- CAccelerating performance of those tasks on the critical path
- DAccelerating performance by minimizing costs
62The "fast-tracking" method of schedule compression involves:
- AThe use of industrial enegineerig techniques to improve productivity, thereby finishing the project earlier than originally planned
- BPerforming activities in parallel, thereby increasing risk
- CGoing on a "mandatory overtime schedule" in order to complete the project earlier
- DAssigning "dedicated teams" to the critical path activities
63The critical path is established by calculating the following sates:
- AStart-to-start, start-to-finish, finish-to-finish, finish-to-start
- BEarly start, early finish, late start, late finish
- CPredecessor-to-successor, predecessor-to-predecessor, successor-to-successor
- Dprimary-to-secondary, primary-to-finish, secondary-to-secondary, finish-to-sinish
64The precedence diagramming method provides project managers with knowledge of:
- AAll levels of the WBS
- BActivities likely to be involved in the project integration and resource allocation functions
- CA graphical representation of interdependencies of activities
- DThe project completion date
65A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:
- ACrashing
- BPERT
- CPredecence diagramming method
- DFast tracking
66Analogous duration estimating is:
- ABottom-up estimating
- BFrequently used to estimate project duration when there is a limited amount of detailed information
- CSimilar to multiple duration estimating
- DDeductive estimating
67Activity 9.2.1 has 7 days of free float. The early start of the successor activity, 9.2.2 is day 29. If activity 9.2.1 is delayed by 12 days, what is the adjusted early start of activity 9.2.2?
- A42
- B22
- C29
- D34
68Activity 7.1 is 5 days, Activity 7.2 is 9 days, Activity 7.3 is 4 days, Activity 7.4 is 11 days, and Activity 7.5 is 6 days. The predecessor for Activity 7.2 is Activity 7.1. The predecessor for Activity 7.3 is Activity 7.2. The predecessor for Activity 7.4 and 7.5 is Activity 7.3. What statement is the most accurate?
- AThe total duration is 35 days
- BActivity 7.5 is a critical activity
- CThe total duration is 29 days
- DIf activity 7.2 gets delayed 3 days, there will be 5-day delay on the project
69You are working with your work package owners to determine the activity cost estimate. An activity cost estimate includes all of the following resource categories except:
- ALabor
- BMaterials
- CEquipment
- DTime shortages
70Your team lead has suggested that you evaluate various estimating techniques in order to provide the mosr comprehensive estimate possible. You decide to use parametric estimating. Parametric cost estimating involves:
- ADefining the parameters of the project life cycle
- BCalculating individual cost estimates for each work package
- CUsing a statistical relationship between historical data and other variables to calculate a cost estimate
- DUsing the actual cost of a similar project to estimate total project cost
71The previous project manager of your newly assigned project leveraged analogous estimating to determine the project costs. Analogous estimating:
- AUses bottom-up estimating techniques
- BUses the actual cost of previous, similar projects as the basis for estimating the cost of the current project
- CIs used more frequently in the later stages of a project
- DSummarizes estimates for individual work items
72Your project is etting ready to kick-off and your sponsor has requested updated cost estimates. Which of the following is not true about cost estimates?
- AAre generally expressed in units of currency (dollars, euro, etc...)
- BThe costs for schedule activities are estimated for all resources that will be charged to the project
- CThey do not generally consider information on risk responses
- Dinvolve developing an approximation of the costs of the resourced needed to complete each schedule activity
73You have been assigned a project that you have minimal experience with in the past. Unfortunately, the organization has also not persued this type of initiative previosuly. The leadership team is asking for an estimate of costs. Based on your limited knowledge, what type of estimate would you most likely provide?
- AParametric
- BPhased
- CAnalogous
- DRough order of magnitude
74You are gathering the cost estimates for the renovation project. Upon reviewing cost data on previous projects, you find that for 20-members team, the avarage equipment cost was $3,800. You anticipate a 15-person team. Which statement is more accurate?
- AA parametric estimate would be $2,850
- BAn analogous estimate would be $2,850
- CThe estimate would not be able to be determined due to pricing increases
- DA budgetary estimate would be $2,850
75The difference between the cost baseline and the total project budget can be best described as:
- AThey are synonymous
- BThe total project budget includes management reserve and the cost baseline does not
- CThe cost baseline includes management reserve and the total project budget does not
- DThe total project budget is managed by the project manager and the cost baseline is managed by the team
76Given the launch of the new system, you need to take into consideration the cost of associated hardware and software. Your IT team lead anticipates the cost to be approximately $18,000. However, if an upgrade is necessary, it could cost as much as $30,000. There is a chance that existing hardware can be used, which would bring the costs as low as $7,000. What is the best estimate?
- A$17,167
- B$18,170
- C$18,330
- D$18,750
77Successful adoption of the CIS project is going to be dependent upon a thorough training program for the service representatives. In order to develop your sizing, you review the documentation from the financial system roll-out last year. To provide the same population with classroom training for that project cost $37,500. In addition, IT recently provided all users with trouble-shooting manuals for a similar system, at a cost of $12,000. Troubleshooting manuals will be used for this project as well. Which statement is most accurate?
- AThe parametric estimate would be $49,500.
- BThe analogous estimate would be $49,500.
- CThe budgetary estimate would be $49,500.
- DThe three-point estimate would be $49,500.
78During the pilot of the CIS project, 1000 customer records were updated and added to the new system. The cost from the vendor was $500. You know that for the full launch you will need to update and transfer 500,000 additional customer records. What will be the best estimate for the full launch?
- A$250,00
- B$250,500
- C$500,000
- D$200,000
79The tools and techniques for this process include financing, cost aggregation, and funding limit reconciliation:
- ADetermine budget
- BEstimate costs
- CCost budget estimating
- DPlan cost management
80Your $85,000 project is estimated to take 12 weeks and you are 30% complete. What will the planned value (PV) be at the end of the project?
- AUnable to determine until the project is 100% complete
- B$59,500
- CThe budget at completition (BAC)
- D$7,083
81The work package owners and other team members have provided the cost estimates for their components of the project. You have evaluated the estimates provided and assessed the contingency requirements. What should you do next?
- ASeek approval on the cost estimates
- BEstimate the need for management reserve
- CReview the cost estimates with the sponsor and key stakeholders
- DUsing the scheduling of the work packages and the activities, determine the project budget
82On a particular component, the work package owner leveraged a triangular 3-point estimate, calculated at $128,333. If the optimistic estimate was $98,000 and the most likely estimate was $112,000, what was the pessimistic estimate?
- A$112,778
- B$175,000
- C$223,998
- D$112,389
83The project has been underway for six months and the team has made considerable progress. As you move inti the phase ofdeliverable development, your team has discovered a significant quality problem. What sould you do next?
- AEscalate the situation to the sponsor for notification
- BDevelop an Ishikawa diagram to determin root causes of the quality issue
- CRefer the issue to the quality team for resolution
- DContinue with the project to see if the probelm continues to appear
84One of the fundamental tenets of modern quality management is:
- AQuality is planned and inspected in
- BQuality does not cost
- CQuality is planned, designed, and built in - not inspected in
- DQuality requires constant inspection
85Precision and accuracy can best be described as
- APrecision means the values of repeated measurements are consistent while accuracy means the values are very close to the true value
- BPrecision means the values are very close to the true value while accuracy means the values of repeated measurements are consistent
- CPrecision and accuracy both mean that the values of repeted measurements are consistent
- DPrecision is the degree to which characteristics fulfill requirements and accuracy is the category assigned to products having the same functional use but different technical characteristics
86You have assumed the management of a large, multi-location project. You are evaluating the quality costs associated with the project. The cost of quality will include all of the following except:
- ATraining of the project team
- BProduct returns
- CInconsistent results
- DFacilities management
87Quality and grade are different in that grade:
- AMay or may not be an indicator of how well the product fulfills the customer's requirements
- BIs the measurement of how close the product is to the target value
- CIs the degree to which the product meets the customer's requirements
- DIs the category assigned to products that have the same technical characteristics but different functional uses
88Your organization has conducted an extensive benchmarking study. Which statement is less accurate regarding benchmarking:
- ACan determine what approaches to use
- BCan determine what product life cycle to use
- CCan determine what products or services to offer
- DCan determine what standards to achieve
89Inspection:
- AIs not a cost-effective way to build quality into a product
- BIs the best method to create quality products
- CIs only effective if is done at random intervals in a production process
- DIs never an appropriate tactic during quality assurance
90A control chart has all of the following characteristics except:
- AIt illustrates how process behaves over time
- BIt is used to determine whether or not a process is stable or has predictable performance
- CIt illustrates how various factors might be linked to potential problems or effects
- DIt can be used to monitor any type of output variable
91Regarding effective quality management, which statement is least accurate?
- AIdeally, QA finds the defects versus QC fixing the process
- BIdeally, quality is built into the product versus QC finding the defect and fixing it
- CIdeally, QC finds the defect versus the customer finding the defect
- DIdeally, a quality culture is implemented versus quality is built into the project
92Your development team is producing switch mechanisms for the new product. After each batch is produced it is checked through quality control to validate the mechanisms function appropriately. This would be considered an example of:
- AVariable sampling
- BRandom sampling
- CAttribute sampling
- DCommon sampling
93The PMO in your organization has implemented a policy that all active projects must undergo quality audits. Which statement is least accurate regarding quality audits?
- AQuality audits identify inefficient and ineffective policies, processes, and procedures that are in use
- BQuality audits may confirm the implementation of approved change requests and their effectiveness
- CQuality audits must be scheduled on a set basis to determine full effectiveness
- DQuality audits determine whether project activities comply with organizational policies and procedures
94Your project team has completed the first deliverables for the project. What do you do next?
- AEvaluate the deliverables through QA
- BReview the deliverables with the customer in the validate scope process
- CProvide a report to the sponsor
- DEvaluate the deliverables through QC
95Which statementis most accurate regarding project quality management?
- AThe manage quality process is employed only when the project is producing a product
- BWork performance information is used in the plan quality management process to evaluate if the quality standards are being met
- CContinuous process improvement should not be confused with quality assurance
- DQuality control measurements are used in the manage quality process to evaluate if the results are in alignment with metrics prescribed in the quality management plan
96The Responsability assignment matrix (RAM)
- AIs used for development of the project budget
- BIs developed at the activity level and used to closely link project roles and responsabilities to project network activities
- CIs used to show the connetions between work that needs to be done and project team members. It can show responsabilities at various levels of detail
- DIs used to identify accountabilities in individual performance appraisals
97The five stages of team development (Tuckman's ladder) are:
- AForming, storming, norming, conforming and adjourning
- BForming, storming, norming, performing and adjourning
- CMeeting, assignments, work progession, reporting, and disbanding
- DAcquisition, assignment, status reporting, results, and re-assignments
98An OBS:
- AIs a graphical, hierarchical depiction of the client's organizational departments
- BDepicts all of the obstructions anticipated by the performing organization
- CIs arranged according to an organization's existing departments, units, or teams, with the project activities or work packageslisted under each department
- DIs a mandatory component of the requirements documentation
99Which statement is true about team-building activities?
- AThey should only be conducted when the project is nearing completion
- BOnly top performers should participate
- CThey must be facilitated by project manager
- DThey can range from brief agenda items to extended off-site activities
100Allison has recently assumed the project management of the office relocation project, which has been underway for a number of months. As Allison becomes familiar with the existing team members on the project, she observes their interactions and notices that they seem to be working independently and not collaboratively. When Jummy offered a suggestion to streamline the tear-down of the cubical walls, Esmeralda, the facilities manager, became very defensive and shut the idea down quickly. In what stage of the team development is the office relocation project team?
- AStorming
- BNorming
- CForming
- DPerforming
101Which of the following is not an objective of developing the project team?
- AImprove knowledge and skills of team members in order to increase their ability to complete project deliverables, while lowering costs, reducing schedules, and improving quality
- BDevelop a permanent team structure that can stay in place and perform well despite organizational changes
- CImprove feelings of trust and agreement among team members in order to raise morale
- DCreate a dynamic and cohesive team culture to improve both individual and team productivity
102Three types ofhierarchical chartsthat may be used to plan resource management include all of the following except:
- AResource breackdown strucuture
- BOrganizational breackdown strucuture
- CWork breackdown strucuture
- DRisk breackdown strucuture
103Whyis observation and conversationa a reccomended rechnique for managing the project team?
- ABy observing and talking to the team, the project manager may become aware of issues and concerns that are not evident through noninteractive communication
- BIt is mandatory for a project manager to have interactive communication with all team members
- CInteraction with the team will improve their trust in the project manager
- DThe project manager will be able to more quickly identify quality control issues
104Tools and techniques to acquire the resources include all of the following except:
- APre-assignment
- BMulticriteria decision analysis
- CStaffing management plan
- DNegotiation
105Questions that may arisewhen planning the acquisition of project team members generally include all of the following except
- AWhether the human resources come from within the organization or from external, contracted sources
- BThe costs associated with each level of expertise needed for the project
- CSenior executives compensation
- DThe extent of assistance that the organization's human resource department can provide to the project management team
106In a RACI RAM, the "R" stands for what, respectively?
- AResponsable, responsability
- BResource, responsable
- CResponsible, resource
- DResponsibility, responsible
107This theorist presented the hierarchical needs, starting with physiological needs and the top being self-actualization
- AOuchi
- BMcClelland
- CMaslow
- DMcGregor
108This output from the plan resource management process captures the team values, agreements, and operating guidelines.
- ATeam rules
- BResource management plan
- CGround rules
- DTeam charter
109Bottom-up estimating, analogous estimating, and parametric estimating may be used in what resource process?
- AEstimate resource costs
- BEstimate activity durations
- CEstimate activity resources
- DEstimate resource durations
110To ensure the best outcome for your project with the small team , you will be relocating the team members to a war room set-upso that they are co-located. This is also known as:
- ARisk avoidance
- BA tight matrix
- CPeer-to-peer work
- DAgile project management
111An opportunity is also known as:
- AA realized benefit
- BA coincidence of the project
- CA strong project outcome
- DA positive project risk
112The risk management plan has been completed and approved by the key stakeholders. You are working with your team to identify risks to the project and are performing a quantitative risk analysis. The objective of the qualitative risk analysis is to:
- AAssess the impact and likelihood of identified risks
- BPrioritize the identified risks for further analysis or for response
- CDetermine if the risk responses have been implemented as planned
- DSelect alternative strategies fordealing with risks
113 Which statement is most accurate regarding risk identification?
- AIdeally, as many people as possible are involved, within and outside of the project team
- BIdeally, it should be limited to the immediate project team
- CIdeally, is hould happen after the project kick-off meeting
- DIdeally, only the project manager is involved
114There was a software risk associated with the infrastructure project. To mitigate the risk, you leveraged a software provider that has been known to be compatible with your organization's systems. However, upon install, you realize the new software is causing a major problem. What is the next thing you do?
- AImplement the contingent response strategy
- BImplement the residual risk plan
- CImplement the riskmitigation strategy
- DImplement the fallback plan
115You are the project manager of the ABC project. The project is being executed in an earthquake-prone area. To take careof thisyou buy insurance for earthquakes. This is an example of:
- ARisk mitigation
- BTransfer of risk
- CRisk contingency planning
- DAccepting the consequences passively
116You are the PM of ABC project. Oneof the risks that have been identified is attrition of team members. Mid-way through the project you notice that the morale and motivation of the team members is going down. You think that this is a precursor to people leaving the organization. For this risk, low motivation is an example of:
- AWork-around
- BTrigger
- CRisk monitoring
- DRisk planning
117You are managing the project of planning a party for your company employees. There is a risk that the employees will not come to the party. You decide to not take any action against this as the likelihood of this is low. Which risk response strategy are you following?
- AAcceptance
- BAvoidance
- CMitigation
- DTransfer
118Which statement is true about project risks?
- AIf a risk is identified in a risk response plan, then that means that risk has already happened
- BOnce a risk has happened, you refer to the risk management plan to determine what action needs to be taken
- CA risk that was not planned but has happened is called trigger
- DRisk identification happens in all phases of the project
119The organization is very sensitive to any risk impacting the project budget or schedule. You are working with your team and subject matter experts to conduct a quantitative risk analysis on the identified risks. Which statement is least accurate?
- AThe output of a quantitative risk analysis techniques are typically probability distributions
- BA Monte Carlo simulation takes into consideration both costs and schedule risks
- CA tornado diagram only represents schedule risk data
- DDecisions trees are used for both schedule and cost risks
120This is the process of analyzing the effect of identified risks on overall project objectives, assigning a numerical rating to those risks individually or evaluating the aggregate effect of all risk affecting the project, and presents an approach to making decisions in the presence of uncertainty
- APerform qualitative risk analysis
- BPerform quantitative risk analysis
- CControl quality
- DPerform quality management
121There is a meeting in Europe for the organization's senior leadership team. To reduce the risk associated with having the executives all on one plane, you send no more than two executives on the same flight. What risk strategy are you using?
- ARisk avoidance
- BRisk transfer
- CActive risk acceptance
- DRisk mitigation
122There is a potential opportunity if your product is first to market. You decide to team up with another business in order to increase the chances that you will make it to market first. What risk strategy are you using?
- AEnhancement
- BSharing
- CExploitation
- DTeaming agreement
123Mitigation is to threats as _________________ is to opportunities
- AEnhancement
- BExploitation
- CAcceptance
- DTolerance
124Which statement is least accurate about tornado diagram?
- AA tornado diagram is developed during a quantitative risk analysis
- BA tornado diagram only depicts cost risk data
- CA tornado diagram is a typeof sensitivity analysis
- DA tornado diagram is also known as hurricane chart
125Upon discussion with the work package owner you learn that based on the vendor used, there are four potential durations for the work. There is a 20% chance of using a local vendor, with a duration of 12 days; a 30% chance of using a domestic vendor, with a duration of 18 days; a 10% chance of using an international vendor, with a duration of 27 days; the remaining possibility is to do the work in-house, with a duration of 15 days. What is the best estimate to use?
- A16 days
- B17 days
- C10.5 days
- D11 days
126Interpersonal and team skills used to plan communications management include all of the following except:
- ACommunication styles assessment
- BStakeholder engagement assessment matrix
- CPolitical awareness
- DCultural awareness
127Listening to unserstand versus listening to respond is considered:
- AActive listening
- BEmotional intelligence
- CNetworking
- DCultural awareness
128A key output of the manage communication process is:
- AWork performance data
- BProject deliverables
- CProject communications
- DCommunication management plan
129The components of the communication model include all of the following except:
- ASender and receiver
- BEncode and record
- CNoise
- DMessage and medium
130You have updated the knowledge repository that that contains general information forthe stakeholders. What communication method was used?
- APull
- BPush
- CInteractive
- DMeeting
131You have a number of time-sensitive issues on which you need information from your stakeholders. What would be the most appropriate communication method?
- APush
- BPull
- CInteractive
- DOn-line meeting
132project intranets and home pages are examples of _____________ communication:
- AOpen access
- BFree will
- CPull
- DPush
133Effective meeting management should include all of the following except:
- ARecording all action items and follow-ups
- BDistributing the agenda prior to the meeting
- CAllowing only one team member to speak during the meeting
- DStarting and finishing the meeting online
134Your project has kicked off and you are evaluating different communication technology options as proposed by the PMO. Your team is minly a virtual team, spanning five different countries. You are expecting the project to last at least a year. Which factor shouldn't you consider when selecting the appropriate communication technolgy?
- AYour previous organization's communication tools
- BThe lenght of the project
- CThe team members desire and willingness to engage with or learn a new technology
- DThe availability of technology within the organization
135The biases and perspectives that may interfere with the communication's receiver's interpretation of the message
- ANoise
- BStatic
- CConditions
- DInterference
136Which of the following is not a focus direction for communication?
- AUpward
- BHorizontal
- CLateral
- DDownward
137A fundamental attribute of effective communication activities and artifacts:
- ACreating a centralized website
- BDefining the purpose of the communication
- CEnsuring that everyone in the organization receives identical communication
- DValidating all communications with the sponsor
138One of your team members has approached you regarding her concerns with some of her team members. the majority of the team members for her particular piece of the project are located out of the country. She feels that based on their emails to her they are notunderstanding the project costraints. What technique would you reccomend that she useto address the situation?
- AA stakeholder engagement assessment matrix
- BObservation and conversation
- CThe project management information system
- DCo-location
139Presentations
- AWill be successful when the content and delivery meets the audience's expectations and needs and the needs and objectives of the project and project team
- BAre best handled by the project sponsor
- CAre not used in adaptive environments as the team is working on sprints
- DShould be scheduled once per month to provide project status updates
140Requested but unresolved changes within a contractual relationship:
- AMust be added to the risk register
- BCan only be resolved through mediation
- CDo not involve the project manager, only senior leadership of the organization
- DCould be considered a constructive change to the contract that may be disputed by one party and lead to a claim against the other party
141The contract change control system:
- AIs a component of the integrated change control system
- BIs administered by an individual with procurement authority
- CManages changes to the contract with the end-user
- DIs separate from the integrated change control system
142Your sponsor over the very complex project has requested that if a vendor will be necessary, the lowest risk contract that would allow the vendor to deliver on all of the terms and conditions must be used. A such, you know you will need to use:
- AFirm fixed price
- BNo vendor
- CTime and material
- DCost plus fixed fee
143Which of the following is false about advertising as a tool and technique of the conduct procurement process?
- AIt is something required on governemnt projects
- BIt can often be used to expand the existing lists of potential sellers
- CIt can cause public pressure resulting in bid disputes
- DIt can be placed in general circulation publications, such as newspapers, or in specialty publications, such as professional journals
144Evaluation criteria are developed and used to rate or score proposals. These criteria have all of the following characteristics except:
- ATheuygenerally require specification of the name of the transportation organization responsible for delivery of procured items
- BThey can be limited to purchase price if the procurement item is readily available from a number of accptable sellers
- CThey can be subjective, such as, "The proposed project manager needs to have documented previous experience with similar projects"
- DThey can be objective, such as, " The proposed project manager needs to be certifies Project Management Professional (PMP)
145The primary goal of a bidder's conference is:
- ATo ensure all prospective sellers have a clear and common understanding of the procurement
- BTo allow certain bidders to receive preferential treatment
- CTo determine if certain information in the procurement request was missing
- DTo determine which sellers will be responding to the procurement request
146What contract type has the lowest risk for the buyer yet allows flexibility in the form of an incentive for achieving defined performance objectives?
- ACPIF
- BFFP
- CFPEPA
- DFPIF
147If someone in the organization has been delegated procurement authority it means that the individual is:
- AAuthorized to maintain an intellectual property database containing information concerning the performance of sellers on prior projects
- BAuthorized to initiate and conduct negotiations with prospective sellers
- CAuthorized to contractually bind the organization
- DAuthorized to review and approve payment on billings submitted by sellers
148You are developing the SOW that will be provided to the selected vendor. Which statement is least accurate regarding the procurement SOW?
- AIt defines the portion of the project scope that will be included with the related contract
- BIt will include a description of any collateral service required
- CIt will be used to solicit proposal from prospective sellers
- DIt will include sufficient detail to allow prospective sellers to determine if they are capable of providing the product or service
149Generally, a bid differs from a proposal in that the term:
- AProposal is used when source selection will be based on price
- BProposal is used when the project time frame is limited
- CBid is used when source selection will be based on price
- DProposal disregards price consideration
150A CPFF contract has all of the following charcateristics except:
- ASeller is reimbursed for allowable costs for performing the contract work
- BSeller receives a fixed fee payment calculated as a percentage of the actual project costs
- CSeller receives a fixed fee payment calculated as a percentage of the estimated project costs
- DThe fixed fee does not vary with actual costs unless the project scope changes
151Jansen Bros Construction has been selected as a contractor for the downtown construction project. The costs for equipment rental, manpower, and other supplies will be included in the contractor price. If the final costs are higher or lower than anticipated, Jansen Bros will split the difference with the buyer 50/50. In addition, Jansen Bros will receive $30,000 for each day they complete their job prior to the scheduled delivery date. What type of contract are they working under?
- ACPFF
- BFPIF
- CCPAF
- DCPIF
152The seller is working under a cost reimbursable contract with 70/30 split. As an incentive from the buyer, the vendor will receive $1500 for each day they deliver the final product early. The original cost estimate on the project was $750,000. The vendor delivered the product six days early at a final invoice of $810,000. What is the contract value?
- A$810,00
- B$801,00
- C$852,00
- D$783,000
153You have assumed the management of a project that was well underway. One of your team members lets you know that the primary vendor working on the project was hired based upon being a solo source. You know that this means:
- AThe vendor was the least expensive vendor
- BThe vendor had the highest technical proposal score
- CThe vendor is on the qualified sellers list
- DThe vendor submitted a proposal without competition
154Creeping scope is a major concern of any project. The person responsible for safe-guarding customer change requests is:
- AFunctional manager
- BProject manager
- CProject sponsor
- DPresident
155An approved change request impacting project scope is:
- AAny modification to the agreed-upon project scope baseline, as defined by the approved project scope statement, WBS, and WBS dictionary
- BAny change in the project personnel
- CAny change in the project authorization
- DAny modification in the technical specifications as defined in the WBS
156A Change Control Board (CCB) is:
- ACharged with making sure no changes are made to project baselines
- BA group of experts external to the project
- CDesignated by a steering committee
- DA group of stakeholders who are capable of evaluating change requests and are responsible for approving or rejecting change requests
157Change requests:
- ACan come from anyone
- BMust be documented
- CMust be subjected to an integrated change control process
- DAll of the above
158Which is an acceptable cause for "re-baseling" a $10 million project?
- AThe client has authorized a $100,000 additiona to the scope of the project
- BThe contractor's company has instituted a quality program in which it has pledged to spend one million dollars during the next year
- CThe productivity in the drafting departmente is lower than anticipated, which has resulted in 1000 additional hours over what was budgeted
- DThe engeneering department has converted to a new $200,000 CAD system
159This process is performed from project inception through completion and includes multiple change management activities.
- APerform integrated change control
- BManage project execution
- CMonitor and control project work
- DManage configuration
160Which statement is most accurate?
- ATacit knowledge includes beliefs and insights whereas explicit knowledge can be easily codified and conveyed
- BTacit knowledge involves tactile driven activities whereas explicit knowledge follows a checklist
- CTacit knowledge can be codified and taught whereas explicit knowledge is only learned through training
- DTacit knowledge is easy to transfer to another person whereas explicit knowledge cannot be shared or transferred
161The perform integrated change control process includes all of the following change management activities except:
- AReviewing and approving requested changes
- BResource leveling
- CMaintaining the integrity of baselines by releasing only approved changes for Incorporation into project products or services, and maintaining their related configuration and planning documentation
- DControlling and upadting the scope, cost, budget, schedule, and quality requirements based upon approved changes, by coordinating changed across the entire project
162Which of the following best describes configuration management?
- AManagement and control of the physical and functional characteristics of the product, service, result, or component
- BManagement and control of the project requirements
- CThe description of the product to be developed
- DThe management of quality as it relates to the project scope
163What is the most appropriate approach to handling an unapproved change request that's already been implemented?
- AIdentify the individual responsible for implementing the unapproved change request and provide feedback
- BReverse the change
- CDo nothing as the change has already been implemented
- DEvaluate the change through the integrated change control process
164A team member made a change to the design of the deliverable based on verbal feedback received from one of the customers. The completed deliverable was rejected by the customer as it did not meet the documented requirements. What type of request would be needed to modify the completed deliverable?
- AScope change
- BDefect repair
- CCorrective action
- DNo change request required
165This is the process of communicating and working with stakeholders to meet their needs and address issues as they occur:
- AManage stakeholder engagement
- BDistribute information
- CCorrective action
- DConduct stakeholder analysis
166Which of the following is a tool and technique in the control scope process?
- AVariance analysis
- BReplanning
- CInspection
- DConfiguration management system
167A schedule performance index (SPI) of 0,8 suggests that the project is:
- AAhead of schedule to date
- BBehind schedule to date
- COn schedule
- DNon of the above
168A project that has a negative cost variance and an SPI less than 1, means that the project is:
- AOver-budget and ahead of schedule
- BUnder- budget and behind of schedule
- COver-budget and behind of schedule
- DUnder- budget and ahead of schedule
169A cost performance index (CPI) of 0,8 suggests that the project is:
- AUnder-budget to date
- BOver- budget to date
- COn budget
- DNon of the above
170The $450,00 is 75% complete as of month six. The budget was allocated at $50,000 per month for nine months and the invoices paid-to-date are $350,000. What is the TCPI of this project?
- A0,9
- B1,11
- C($12.500)
- D$12.500
171The cost performance index (CPI) is calculated as follows:
- AEV/AC
- BEV/PV
- CEV-AC
- DEV-PV
172The PV is $250,000 and the EV is $300,000, the SV is:
- A$25,000
- B($25,000)
- C$125,000
- D$575,000
173The integrated process tracks, reviews, and reports overall progress to meet the performance objectives defined in the project management plan:
- ADirect and manage project work
- BManage project knowledge
- CMonitor and control project work
- DControl scope
174The team is working in two-weeks sprints and the project has been underway for 12 weeks. The team has completed 450 story-points worth of work. What is the team velocity?
- A37.5 story points
- B75 story points
- CIt is too early in the project to calculate
- D2700 story points
175The estimate at completion for the $200,000 project is $185,000. The estimate to complete the project is $65,000. As such:
- AThe variance at completion is ($15,000)
- BThe earned value is $120,000
- CActual costs are $120,000
- DThe variance at completion is ($50,000)
176A chart used on agile projects to track the work that remains to be completed:
- AIteration burndown chart
- BSprint histogram
- CDaily stand-up chart
- DControl chart
177The schedule variance is $10,000, the cost variance is $3,000, and the actual costs are $12,000. A such:
- AThe earned value us $7,000
- BThe project is over budget and behind schedule
- CThe planned value is $15,000
- DThe earned value is $5,000
178The performance report details tha following: the $180,000 project is 60% complete. Actual costs to-date have been $105,000. Estimated remaining costs are $80,000. What is the variance at completion?
- A$5000
- BUnable to calculate
- C($5000)
- D$185,000
Informationen
- Beschreibung
- Project Management Quiz am CAMP Exam, erstellt von Valeria Gilardoni am 15/03/2021.
- Autor
- Valeria Gilardoni
- Sprache
- English
- Aufrufe
- 4
- Schlagwörter
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz