GoConqr hat ein neues Design! Sag uns, wie es dir gefällt.

Quiz

Foundation Question 2

faulkner.j 75 Fragen Aktualisiert am 30 Dez 2016

Quiz starten

Fragen in diesem Quiz (75)

  1. 1Which is a recommenced quality review team role?
    1. ASenior User
    2. BPresenter
    3. CProject Support
    4. DProject Assurance
  2. 2Which is a purpose of the Communication Management Strategy?
    1. AIdentify how and by whom the project's products will be controlled and protected
    2. BDefine the method of communication between the project and its stakeholders
    3. CDefine the structure of responsibilities and accountabilities in support of effective decision making in a project
    4. DIdentify the communication required from the Team Manager(s) to the Project Board
  3. 3Identify the missing words in the following sentence.
    Any requests for change, which require Project Board approval,should be recorded in the [?] and monitored by the Project Manager
    1. AProduct Description
    2. BIssue Register
    3. CConfiguration Item Record
    4. DQuality Register
  4. 4If a product fails its quality check, what product should always be updated?
    1. ARisk Register
    2. BIssue Register
    3. CQuality Register
    4. DLessons Log
  5. 5In what product should the Project Manager enter the details of issues that are resolved without using the formal issue and the change control procedure?
    1. AStage Plan
    2. BDaily Log
    3. CConfiguration Item Record
    4. DCheckpoint Report
  6. 6Which of the PRINCE2 principles uses tolerances to establish the limits of delegated authority?
    1. AManage by Stages
    2. BTailor to suit the project environment
    3. CFocus on products
    4. DManage by exception
  7. 7Which is a purpose of the Starting up a Project process?
    1. AEnsuring that the prerequisites for initiating the project are in place.
    2. BEstablishing that the Project Plan can meet the required target dates.
    3. CCreating the Project Initiation Documentation so the project can be initiated.
    4. DConfirming to corporate or programme management that quality expectations will be met.
  8. 8When should the project management team be reviewed?
    1. AAs and when new stakeholders are identified
    2. BWhen planning a quality review
    3. CWhen planning the next stage
    4. DDuring product creation
  9. 9Which is NOT responsibility of the Project Board?
    1. AAllocate tolerances to specialist teams
    2. BTransfer ownership of the Benefits Review Plan to corporate or programme management
    3. CApprove the Project Product Description
    4. DConfirm the required frequency of highlight reports.
  10. 10Who sets the project tolerances?
    1. AProject Board
    2. BCorporate / programme management
    3. CExecutive
    4. DProject Manager

Informationen

Beschreibung
A-Levels PRINCE2 (Question) Quiz am Foundation Question 2, erstellt von faulkner.j am 08/06/2013.
Sprache
English
Aufrufe
303
Verlauf
Erstellt am 8 Jun 2013 · aktualisiert am 30 Dez 2016
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck