Ch 5, 8, 12

Angie Koslowski 78 Fragen

Quiz starten

Fragen in diesem Quiz (78)

  1. 1Which decision making application involves fixed and variable costs?
    1. AFactor Analysis
    2. BBreak even analysis
    3. CNPV analysis
    4. DRegression analysis
  2. 2How many decision alternatives are there in a standard decision table for a problem involving 3 states of nature and 15 payoffs?
    1. A3
    2. B5
    3. C18
    4. Dnone of the others
  3. 3what is the crash slope for a task with normal time of 10 days, a crash time of 5 days, a normal cost of $1000 and a crash cost of $2000?
    1. A1000/day
    2. B200/day
    3. C400/day
    4. D0/day
  4. 4Which project management model is used for time reduction applications?
    1. ACrashing
    2. BRegression
    3. CSlack
    4. DPERT-Cost
  5. 5Which one of the following multiple time distributions are skewed left?
    1. A3, 4, 8
    2. B2, 2, 2
    3. C5, 8, 9
    4. D4, 6, 8
  6. 6The output distribution for a multiple time estimate project is assumed to be?
    1. ABeta
    2. BNormal
    3. CConstant
    4. DUniform
  7. 7In an AOA network the nodes represent?
    1. AEvents
    2. BActivities
    3. CDown time
    4. DSlack
  8. 8In a beta distribution the most likely time is?
    1. ACloser to the most pessimistic time
    2. BCloser to the most optimistic time
    3. CEqual to the expected time
    4. DNone of the above
  9. 9Which variance should be used with a project with multiple critical paths?
    1. AThe smallest variance
    2. BThe largest variance
    3. CThe sum of all variances
    4. DThe average variance
  10. 10 In crashing analysis the crashing cost function is assumed to be?
    1. A Non-linear
    2. BUniform
    3. CLinear
    4. DNormal

Informationen

Beschreibung
stats
Sprache
English
Aufrufe
43
Bewertung
Noch keine Bewertungen
Bewerte dieses Quiz
Bewerte dieses Quiz

Feedback

Worum geht es?

Wie gefällt dir das neue Design?

Dein Eindruck