Kaplan - CDs 2009 [Conditions of the Contract for Construction] Chapter Quiz Questions
Dieses Quiz enthält Fragetypen, die sich im gewohnten Player öffnen.
Fragen in diesem Quiz (15)
1According to AIA documents, which of the following are NOT considered a part of the construction contract documents?
I. Specifications
II. Addenda
III. Shop Dwgs
IV. Owner-Architect Agreement
V. Supplementary Conditions- AA. IV only
- BB. II and III
- CC. I and V
- DD. III and IV
2A [blank_start]performance bond[blank_end] assures an owner that the contractor will execute the work in accordance with the contract.
- Aperformance bond
3During the course of construction, liability insurance should be maintained by which of the following?
I. The mortgagee
II. Trade unions
III. The surety company
IV. The owner
V. The contractor- AA. IV only
- BB. I and V
- CC. IV and V
- DD. II and III
4Where would provisions for liquidated damages be found?
- AA. Owner-Contractor Agreement
- BB. General Conditions of the Contract for Construction
- CC. Additive Alternates to the Contract
- DD. Proposal For and Instructions to Bidders
5A change during construction in the location of underground lines from that shown on the site utilities plan should be reflected in
- AA. record drawings.
- BB. architectural drawings.
- CC. field sketches.
- DD. shop drawings.
6Architects are responsible for preparing which parts of a Project Manual?
I. Specifications
II. General Conditions
III. Supplementary Conditions
IV. Owner-Contractor Agreement- AA. I only
- BB. I and III
- CC. II and III
- DD. I, II, III, and IV
7Which of the following are responsibilities of the owner under the provisions of the AIA General Conditions (remember to answer per the A201 as stated in the question, not your own experience.)?
I. Provide access to the construction site.
II. Make payment to the contractor.
III. Make payments to the subcontractors.
IV. Obtain necessary easements.
V. Provide necessary copies of the construction documents.- AA. II only
- BB. II and III
- CC. I and IV
- DD. II, IV, and V
8Which of these statements is true? Contract time
- AA. is measured in working days.
- BB. ends at substantial completion.
- CC. The general warranty period is one year.
- DD. Warranties are worthless without bonds to back them up.
9Under the conditions of the A201 General Conditions, which of the following statements is true?
- AA. Warranty periods begin at substantial completion.
- BB. Warranty periods begin at final completion.
- CC. The general warranty period is one year.
- DD. Warranties are worthless without bonds to back them up.
10An architect issues certificates for payment for work performed by the contractor. For what reasons might an architect legitimately nullify all or party of a previously issued certificate for payment?
I. The architect discovers defective work.
II. The owner's lender refuses to release funds.
III. The contractor fails to pay subcontractors.
IV. A pedestrian walking past the project site is injured by a falling piece of lumber and sues the owner.
V. The contractor persistently fails to comply with the contract documents.- AA. I, II, III, IV, and V
- BB. I only
- CC. I, III, IV, and IV
- DD. III and V
11Which of the following statements concerning payments to a contractor is FALSE?
- AA. Payments are based on a schedule of values.
- BB. Title to materials and equipment passes to the owner upon payment.
- CC. The owner must pay the contractor within 21 days after the architect issues the certificate for payment.
- DD. Payments do not normally cover materials in transit.
12Which of the following parties are responsible for workers' safety on a construction site?
I. The owner
II. The architect
III. The general contractor
IV. The contractor's surety company- AA. III only
- BB. I only
- CC. I, II, and III
- DD. I, II, III, and IV
13An architect, under the provisions of the AIA documents, inspects a project how often during the construction phase?
- AA. Never. The architect *observes* construction.
- BB. At intervals appropriate to the progress of the construction work.
- CC. Once, at final completion.
- DD. Twice, at substantial completion and at final completion.
14Which of the following is NOT a prerequisite for final payment to the contractor?
- AA. Final inspection by the architect.
- BB. Owner's receipt of the certificate of final completion from the architect.
- CC. Owner's receipt of the contractors affidavit or payment of debts.
- DD. Owner's receipt of consent of the contractor's surety company.
15Which of the following parties must *approve* shop drawings according to the AIA General Conditions? Check all that apply.
- AA. Architect
- BB. Contractor
- CC. Owner
- DD. Engineers
- EE. Subcontractors
Informationen
- Beschreibung
- Quiz am Kaplan - CDs 2009 [Conditions of the Contract for Construction] Chapter Quiz Questions , erstellt von Tiffany Brown am 27/06/2016.
- Autor
- Tiffany Brown
- Sprache
- English
- Aufrufe
- 52
- Schlagwörter
- Bewertung
- Noch keine Bewertungen Bewerte dieses Quiz