Project Management Tools Quiz

Beschreibung

Quiz on project management
Niamh Ryan
Quiz von Niamh Ryan, aktualisiert more than 1 year ago
Niamh Ryan
Erstellt von Niamh Ryan vor fast 7 Jahre
74
0

Zusammenfassung der Ressource

Frage 1

Frage
A critical activity has...
Antworten
  • Negative slack time
  • Zero slack time
  • Positive slack time

Frage 2

Frage
Critical path: The path of activities which represent the [blank_start]longest[blank_end] total time required to complete the project. A delay in an activity on the critical path causes a delay in the [blank_start]entire project[blank_end].
Antworten
  • longest
  • shortest
  • entire project
  • preceding activity
  • parallel activities

Frage 3

Frage
Finish to start lag: The minimum amount of time that must pass between the [blank_start]finish[blank_end] of one activity and the [blank_start]start[blank_end] of its successor(s)
Antworten
  • finish
  • start
  • finish
  • start

Frage 4

Frage
The variance in the project completion time can be calculated by [blank_start]summing[blank_end] the variances in the completion times of the activities in the critical path
Antworten
  • subtracting
  • summing
  • multiplying

Frage 5

Frage
The normal distribution assumption holds if the number of activities in the path is large enough for the [blank_start]central limit theorem[blank_end] to be applied.
Antworten
  • central limit theorem

Frage 6

Frage
The following times for completion an activity have been estimated. Optimistic time: 4 days Most likely time: 7 days Pessimistic time: 10 days. The variance in the expected time is [blank_start]1[blank_end] days.
Antworten
  • 1

Frage 7

Frage
When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between [blank_start]8[blank_end] and [blank_start]80[blank_end] hours of work.
Antworten
  • 8
  • 80

Frage 8

Frage
When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as [blank_start]work packages[blank_end].
Antworten
  • work packages

Frage 9

Frage
High level elements in the WBS should match, word for word, nouns used to describe outcomes in the [blank_start]scope statement[blank_end].
Antworten
  • scope statement

Frage 10

Frage
The current activity has an Early Start of March 1st and a duration of 3 days. The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is [blank_start]3[blank_end] days.
Antworten
  • 3
Zusammenfassung anzeigen Zusammenfassung ausblenden

ähnlicher Inhalt

Expertise in Project Management
tonesha_g
PMP® Pre-Test by Coursefountain.com
Team Coursefountain
Ch1 - The nature of IT Projects
mauricio5509
Introduction notes on SCRUM Project management framework.
Wesley Thomson
Project Management: Week 1
Sharon Ott
Summary of Definitions/Key Terms for the PMP Exam
Andrea Leyden
PMP Prep quiz
Andrea Leyden
06 PROJECT TIME MANAGEMENT
miguelabascal
Project Scope Management Process
neeshar
Project Management Integration
craigmag
PMP Executing, Monitoring and Controlling Processes
myrdenafrancis