PMP Midterm 2 Fifth 20 Q

abdulaziz zaid 21 questions

Take the quiz

Questions in this quiz (21)

  1. 1If you want to reduce the number of quality inspections and thus reduce the cost of quality control for your project, which technique should be used?
    1. ARun Chart
    2. BDefect Repair Review
    3. CStatistical Sampling
    4. DPareto Chart
  2. 2Which of the following documents will help trace the requirements to product design?
    1. ARequirements traceability matrix
    2. BDesign traceability matrix
    3. CProject scope statement
    4. DProduct traceability matrix
  3. 3You have just received notice that the organization you’ve been working for as a project manage has gone bankrupt. All employees have been given 72 hours notice of termination. What is the best course of action for the two projects you are managing?
    1. AFollow company directives.
    2. BConduct a project closeout meeting.
    3. CLeave the office today.
    4. DRaise a claim for and on behalf of all the employees and contractors who were participating in the project
  4. 4A project manager is estimating the project duration and finds that the only information available to him is a previous project that was quite different from the current one. However, some portions of the previous project were similar to the current one. Which of the following tools is the project manager likely to use?
    1. AAnalogous estimating
    2. BProgram Evaluation and Review Technique (PERT)
    3. CThree-point estimates
    4. DParametric estimating
  5. 5A management control point where scope, budget, actual cost and schedule are integrated and compared to earned value for performance measurement is called a:
    1. ACode of accounts
    2. BControl packages
    3. CControl account
    4. DAccount Plan
  6. 6As part of the Plan Risk Management process, a project manager is looking at the activity of preparing a risk management plan. Which of the following is true about risks?
    1. AA risk may have one or more causes and, if it occurs, may have one or more impacts.
    2. BA risk usually has a single cause and, if it occurs, may have one or more impacts.
    3. CA risk usually has a single cause and if it occurs usually has a single impact.
    4. DA risk usually has more than one cause, and if it occurs, may have one or more impacts.
  7. 7A project manager was assigned to a project as the project charter was being developed. Which of the following is an input that the project manager will utilize to develop the project charter?
    1. AMake-or-Buy analysis
    2. BOrganizational Process Assets
    3. CProject Acceptance Criteria
    4. DProject Scope Statement
  8. 8You are working in an Information Technology project as a project manager to develop a shopping website for your customers. Some key stakeholders in the project suggested scope changes to improve the look and feel of the website. Your team has analyzed the impact of these changes and presented to the change control board for approval. What should be your next step if the change control board accepts all proposed changes?
    1. AImplement the change request and update stakeholders
    2. BReview change control board decisions and inform stakeholders for their input
    3. CConduct a team status meeting to update the progress on change requests
    4. DRevise cost estimates, schedule dates, resource requirements and planning documents
  9. 9Which of the following is neither an input nor an output of the Direct and Manage Project Work process?
    1. AApproved change requests
    2. BChange requests
    3. CApproved deliverables
    4. DDeliverables
  10. 10Jane is managing a software development project. During one of the project update meetings, one of the key stakeholders raised a serious concern about the new project management approach being applied on the project. The rest of the stakeholders are comfortable with the new project management approach being used. What should Jane do?
    1. AUse coercive power to convince the stakeholder to accept the new approach.
    2. BRequest stakeholders to vote for the right approach.
    3. CHave a separate one-to-one meeting with the stakeholder if the issue is not resolved during the update meeting.
    4. DRemove the troublesome stakeholder from the stakeholder register.

Information

Description
Fifth 20 Q
Language
English
Views
320
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?