Questions in this quiz (114)
11.¿The timebox for a daily Scrum is?
- AThe same time of day every day
- BTwo minutes per person
- C4 hours
- D15 minutes
- E15 minutes for a 4 week sprint, proportionally less for shorter sprints.
2Which statement best describes Scrum?
- AA complete methodology that defines how to develop software
- BA cookbook that defines best practices for a software development
- CA framework within which complex products in complex environments are developed
- DA defines and predictive process that conforms to the principles of Scientific Management
33. What is the primary way a Scrum Master keeps a Development Team working at its highest level of productivity?
- ABy facilitating Development Team Decisions and removing impediments
- BBy ensuring the meetings start and end at the proper time
- CBy preventing changes to the Backlog once the Sprint begins
- DBy keeping high value features high in the Product Backlog
4The CEO asks the Development Team to add a ""very important"" item to the current Sprint.
What should the development team do?"- AAdd the item to the current Sprint without any adjustments
- BAdd the items to the current Sprint and drop an item of equal size
- CAdd the item to the next Sprint
- DInform the product Owner so he/she can work with the CEO.
5Who should know the most about the progress toward a business objective or a release, and be able to explain the alternatives most clearly?
- AThe Product Owner
- BThe Development Team
- CThe Scrum Master
- DThe Project Manager
6What does it mean to say that an event has a timebox?
- AThe event mus happen at a set time.
- BThe event must happen by a given time
- CThe event must take at least a minimum amount of time
- DThe event can take no more than a maximun amount of time
7Which two (2) things does the Development Team do during the first Sprint?
- ADeliver an increment of potentially shippable functionality
- BNail down the complete architecture and infraestructure
- CDevelop and deliver at least one piece of functionality
- DDevelop a plan for the rest of the project
8Development Team members volunteer to own a Sprint Backlog item:
- AAt the Sprint planning meeting.
- BNever. All Sprint Backlog Items are "Owned" by the entire Development Team, even though each one may be done by an individual team member.
- CWhenever a team can accommodate more work
- DDuring the Daily Scrum
9Scrum Master is a "management" position?
- ATrue
- BFalse
10The reason the Scrum Master is at the Daily Scrum is:
- ATo make sure everyone answers the three questions in order of seniority
- BHe or she does not have to be there; he or she only has to ensure the Development Team has a Daily Scrum.
- CTo write any changes to the sprint Backlog, including adding new items, and tracking progress on the burndown.
- DSo he or she knows what to report to management
11The Development Team should have all the skills needed to:
- AComplete the project as estimated when the date and cost are committed to the product owner.
- BDo all the development work, but not the types of testing that require specialized testing, tools, and environments.
- CTurn the Product Backlog items it selects into an increment of potentially shippable product functionality.
12¿What is the maximum length of a Sprint?
- ANot so long that the risk is unacceptable to the Product Owner
- BNot so long that other business events can't be readily synchronized with the development work.
- CNo more than one calendar month.
- DAll of these answers are correct.
13When the Development Team determines that it has over-committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?
- AThe Scrum Master, project manager and Development Team.
- BThe Product Owner and Development Team.
- CThe Product Owner and All stakeholders.
- DThe Development Team.
14The development Team should not be interrupted during the Sprint. The work it selects for a Sprint should not be changed. The Sprint Goal should remain intact. All of these attributes of a Sprint foster creativity, quality and productivity. Based on this, which of the following is FALSE?
- AThe Product Owner can help clarify or optimize the Sprint when asked by the Development Team.
- BThe Sprint Backlog and its contents are fully formulated in the Sprint Planning meeting and do not change during the Sprint.
- CAs a descomposition of the selected Product Backlog items, the Sprint Backlog changes and may grow as the work emerges.
- DThe Development Team may work with the Product Owner to remove or add work if it finds it has more or less capacity than it expected.
15 ¿What is the recommended size for a Development Team (within the Scrum Team)?
- A3 plus or minus 1
- B6 plus or minus 3 ( 3 a 9)
- C9 plus or minus 2
- D15 plus or minus 3
16 ¿Who is required to attend the Daily Scrum?
- AThe Development Team
- BThe Scrum Team
- CThe Development Team and Scrum Master.
- DThe Development Team and Product Owner
- EThe Scrum Master and Product Owner.
1717. ¿Which of the below are roles on a Scrum Team?
- ADevelopment Team
- BUsers
- CCustomers
- DProduct Owner
- EScrum Master
18Which statement best describes the Sprint Review?
- AIt is a review of the team's during the Sprint.
- BIt is when the Scrum Team and Stakeholders inspect the outcome of the Sprint and figure out what to do in the upcoming Sprint.
- CIt is a demo at the end of the Sprint for everyone in the organization to provide feedback on the work done.
- DIt is used to congratulate the Development Team if it did what it committed to doing, or to punish the Development Team if it failed to meet its commitments.
1919. ¿Which statement best describes a Product Owner's responsability?
- AOptimizing the Return on investment (ROI) and the Total Cost of ownership (TCO) of the work the Development Team does.
- BManaging the project and ensuring that the work meets the commitments to the stakeholders.
- CDirecting the Development Team.
- DKeeping stakeholders at bay.
2020. Scrum does not have a role called "project manager"
- ATrue
- BFalse
2121. Which of the following options is MOST accurate about Scrum
- AScrum optimize change
- BScrum optimize quality
- CScrum optimize risk
- DScrum optimize predictability
2222. Which of the following is NOT a characteristic of a Scrum Development Team?
- APosesses all of the skills to creat a product increment
- BDetermines how to turn a Product Backlog item into a product increment after the architecture and requirements are documented
- CAccountability is shared amongst all team members
- DThere are not titles other than Developer
2323. How are the decisions of the Product Owner made visible? (select two)
- ABy the ordering in the Product Backlog
- BBy the number of errors in the delivered product
- CBy the quality of the delivered product
- DBy the content in the Product Backlog
2424. Scrum Teams deliver products ________________ and _________________
- AIteratively, at lower costs
- BIteratively, incrementally
- CIteratively, without mistakes
- DIteratively, waterfall way
2525. What are the risks of making a Sprint too long? (select two)
- ARisk may increment
- BFocus increase
- CComplexity may increase
- DAll of the above
2626. What does the Product Backlog management include?
- AClearly expressing Product Backlog items
- BAuthoring Product Backlog items
- COrdering Product Backlog items by size and risk
- Dall
2727. What is the result of Sprint Review?
- AA revised Product Backlog
- BCritique on the development product increment
- CA completed Sprint Backlog
- DThe Scrum Master´s documentation on the Sprint statistics
2828. During which Scrum event is the Sprint Goal crafted?
- ADaily Scrum
- BSprint Retrospective
- CSprint Review
- DSprint Planning
2929.What optimizes the Development Team's overall efficiency and effectiveness?
- ABeing focused on only small increments at a time
- BDetermining how they will complete a given Product Backlog item
- CDetermining which Product Backlog item to pick each Sprint
- DWorking in an agile development framework
3030.Please select which statement is the MOST accurate
- ANo one outside of the Scrum Team should be invited to the last session of Sprint Planning
- BThe development team may invite other people to the last session of Sprint Planning
- CThe Product Owner may invite other people to the last session of Sprint Planning
- DThe Scrum Master may invite other people to the last session of Sprint Planning
3131.The Scrum Master serves the organization in all of the following ways EXCEPT
- AHelping employees and stakeholders understand and enact Scrum and empirical product development
- BWorking with other Scrum Masters to increase the effectiveness of the application of Scrum in the organization
- CLeading and coaching the organizations in its Scrum adoption
- DTracking Scrum implementations within the organization
3232.How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
- AAs much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of done
- BAs much as it can fit into the Sprint
- CAll development work and at least some testing
- DAnalysis, design, programming, testing and documentation
3333.Development Team membership should change:
- AEvery Sprint to promote shared learning.
- BNever, because it reduces productivity
- CAs needed, while taking into account a short term reduction in productivity
- DAs needed, with no special allowance for changes in productivity.
3434.During a Sprint, a Development Team determines that it will not be able to finish the complete forecast. Who should be present to review and adjust the Sprint work selected?
- AThe Scrum Master, the project manager and the Development Team.
- BThe Product Owner and the Development Team.
- CThe Product Owner and all stakeholders
- DThe Development Team.
3535.Who is responsible for managing the progress of work during a Sprint?
- AThe Development Team.
- BThe Scrum Master
- CThe Product Owner
- DThe Project Manager
3636.When multiple teams work together on the same product, each team should maintain a separate Product Backlog.
- ATrue
- BFalse
3737.The maximum length of the Sprint Review (its time-box) is:
- A15 minutes
- BAs long as needed.
- C4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
- D1 day
3838.The purpose of the Sprint is to produce a done increment of working product.
- ATrue
- BFalse
3939.The time-box for the Sprint Planning meeting is?
- A8 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
- B4 hours for a monthly Sprint. For shorter Sprints it is usually shorter.
- CMonthly
- DDaily
4040.When is a Sprint over?
- AWhen all Product Backlog items meet their definition of done
- BWhen the Product Owner says it is done.
- CWhen all the tasks are completed.
- DWhen the time-box expires
4141.When does the next Sprint begin?
- AEvery week
- BImmediately following the next Sprint Planning
- CWhen the Product Owner is ready.
- DImmediately after the conclusion of the previous Sprint.
4242.How is management external to the Scrum Team involved in the Daily Scrum?
- AThe product Owner represents their opinions.
- BThe Scrum Master speaks on their behalf.
- CThe Development Team self-manages and is the only management required at the Daily Scrum
- DManagement gives an update at the start of each Daily Scrum.
4343.Choose two responsabilities of a self-organizing Development Team.
- ADo the work planned in the Sprint Backlog.
- BPull Product Backlog items for the Sprint.
- CIncrease velocity
- DReport daily progress to stakeholders
4444.What is the tactic a Scrum Master should use to divide a group of 100 people into multiple Development Team.
- ACreate teams based on their skills across multiple layers(such as database, UI, etc.)
- BAsk the Product Owner to assign the people to teams.
- CAsk the developers to divide themselves into teams.
4545.In accordance with Scrum theory, how should a group of 100 people be divided into multiple Development Teams
- ACheck with the allocation department to see who has worked together before and make these the first teams.
- BIt doesn't really matter because you can rotate the teams every Sprint to spread knowledge
- CCreate a matrix of skills, seniority, and level of experience to assign people to teams.
- DUnderstanding the product, the product vision and the rules of the Scrum framework, the group divides itself into teams.
4646.What are three ways Scrum promotes self-organization?
- ABy the Development Team deciding what work to do in a Sprint.
- BBy not allowing documentation.
- CBy removing titles for Development Team members.
- DBy being a lightweight framework.
- EBy preventing stakeholders from entering the development room
4747.Which two of the following are true about the Scrum Master role?
- AAt the Sprint Review, the Scrum Master identifies what has been "done" and what has not been "done".
- BThe Scrum Master assigns tasks to Development Team members when they need work.
- CThe Scrum Master is responsible for updating the Sprint Burndown.
- DThe Scrum Master helps those outside the team interact with the Scrum Team.
- EThe Scrum Master teaches the Development Team to keep the Scrum meetings to their timebox.
4848. As the Development Team starts work during the Sprint, it realizzes it has selected too much work to finish in the Sprint. What should it do?
- AFind another Scrum Team to give the excess work to.
- BInform the Product Owner at the Sprint Review, but prior to the demonstration.
- CAs soon as possible in the Sprint, work with the product owner to remove some work or Product Backlog items.
- DReduce the definition of "Done" and get all of the Product Backlog items "done" by the new definition.
4949. Which of these may a Development Team deliver at the end of a Sprint?
- AFalling unit tests, to identify acceptance tests for the next Sprint.
- BAn increment of working software that is "done".
- CAn increment of software with minor known bugs in it.
- DA single document, if that is what the Scrum Master asked for.
5050. How often should Development Team membership change?
- AEvery Sprint to promote shared learning.
- BNever, because it reduces productivity
- CAs needed, while taking into account a short term reduction in productivity
- DAs needed, with no special allowance for changes in productivity.
5151. Which are properties of the Daily Scrum?
- AIts location and time should remain constant.
- BIt is facilitated by the team lead.
- CIt consists of the Scrum Master asking the Team members the three questions.
- DIt is fifteen minutes or less in duration.
- EIt is held first thing in the morning.
- FIt is free form and designed to promote conversation.
5252. The length of a Sprint should be:
- AShort enough to keep the business risk acceptable to the Product Owner.
- BNo more than one calendar month.
- CShort enough to be able to synchronize the development work with other business events
- DAll of these answer are correct
5353. Who owns the Sprint Backlog?
- AThe Scrum Master
- BThe Scrum Team
- CThe development Team
- DThe Product Owner
5454. The Product Owner is not collaborating with the Development Team during the Sprint.What are two actions for a Scrum Master to take?
- AStop the Sprint, send the Product Owner to a course and restart
- BBring up the problem in the Sprint Retrospective.
- CCoach the Product Owner in the values of Scrum and incremental delivery.
- DInform the Product Owner's functional manager.
- ENominate a proxy Product Owner.
5555. A Scrum Team is only allowed to meet with stakeholders during Sprint Review
- ATrue
- BFalse
5656. What is the best suited structure for Development Teams in order to produce integrated Increments?
- AEach Development Team works only on one technical layer of the system(e.g. GUI, database, middle tier, interfaces)
- BEach Development Team develops functionality from beginning to end throughout all technical layers
5757. A Scrum Master is working with a Development Team that has members in different physical locations. The Development Team meets in a variety of meeting rooms and has much to do logistically(for example, set up conference calls) before the Daily Scrum. What actions should the Scrum Master take?
- AAllow the Development Team to self-manage and determine for itself what to do.
- BSet up the meeting and tell the Development Team that is how it will be done.
- CInform management and ask them solve it
- DAsk the Development Team members to alternate who is responsible for meeting setup.
5858. How should a Development Team deal with non-functional requirements?
- AEnsure every Increment meets them
- BHandle them during the Integration Sprint preceding the Release Sprint.
- CMake sure the release department understands these requirements, but it is not the Development Team's responsibility.
- DAssign them to the lead developers on the team.
5959. Which outcome is expected as Scrum Teams mature?
- AA Scrum master is no longer needed since they are a mature team now
- BThey will improve their definition of "Done" to include more strongent criteria
- CThe Sprint Retrospectives will grow to be longer than 4 hours.
- DThere is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
- ESprint Reviews will no longer be needed.
6060. Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the other teams.What should the Scrum Master do?
- AVisit the five teams each day to inspect that their Sprint Backlogs are aligned.
- BCollect the Sprint tasks from the Teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint.
- CTeach them that it is their responsibility to work with the other teams to create an integrated increment
- DTeach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint
6161. Which of the following are true about the length of the Sprint?
- ASprint length is determined during Sprint Planning, and should hold the time it will take to code the planned features in the upcoming Sprint, but does not include time for any testing
- BAll Sprints must be 1 month or less.
- CThe length of the Sprint should be proportional to the work that is done in between Sprints.
- DSprint length is determined during Sprint Planning, and should be long enough to make sure the Development Team can deliver what is to be accomplished in the upcoming Sprint
- EIt is best to have Sprints of consistent length throughout a development effort.
6262. What does it mean for a Development Team to be cross-functional?
- AThe Development Team includes not only developers but also business analysts, architects, developers and testers
- BThe Development Team includes cross-skilled individuals who are able to contribute to do what is necessary to deliver an increment of software
- CDevelopers on the Development Team work closely with business analysts, architects, developers and testers who are not on the team.
- DThe Development Team is a virtual team drawing from separate teams of business analysts, architects, developers and testers
6363. A Sprint Retrospective should be held :
- AAt the end of each Sprint
- BAt the beginning of each Sprint
- CAt the end of the last Sprint in a project or a release
- DOnly when the Scrum Team determines it needs one
6464. How should Product Backlog items be chosen when multiple Scrum Teams work from the same Product Backlog?
- AThe Scrum team with the highest velocity pulls Product Backlog items first.
- BThe Product Owner decides.
- CThe Product Owner should provide each team with its on Product Backlog
- DEach Scrum Team takes an equal number of items.
- EThe Development Teams pull in work in agreement with the Product Owner
6565. The Product Owner determines how many Product Backlog items the Development Team selects for a Sprint
- ATrue, accordingly to what was committed to the stakeholders.
- BTrue, but only after confirmation by the resource manager that the Team has enough capacity
- CVERDADERO
- DFalse, the Scrum Master does That
- EFalse
- FFalse, capacity and commitment are the Project manager's responsibility.
6666. Scrum is a methodology that tells in detail how to build software incrementally
- ATrue
- BFalse
6767. Who determines how work is performed during the Sprint?
- AArchitects
- BDevelopment Team managers
- CThe Development Team
- DThe Scrum Master
- ESubject matter experts
6868. Which statement best describes the Sprint Backlog as outcome of the Sprint Planning
- AIt is the Development Team's plan for the Sprint
- BEvery item has a designated owner
- CIt is ordered by the Product Owner.
- DIt is a complete list of all work to be done in a Sprint
- EEach task is estimated in hours.
6969. Who can abnormally terminate a Sprint?
- AThe Stakeholders
- BThe Development Team or its members
- CThe Product Owner
- DThe Scrum Master
7070. The Product Owner must release each Increment to production.
- ATo make sure the Development Team is done every Sprint
- BWhen it makes sense
- CWhenever the product is free of defects.
- DWithout exception
7171. During the Sprint, the Scrum Master's role is to do which two of the following :
- AFacilitate the inspection and adaptation opportunities as requested or needed
- BMonitor the progress of the Development Team
- CRemove Impediments
- DAssign tasks with the Scrum Team
- EEnsure the Product Owner attends all Scrum events
- FEscalate team conflicts to functional line managers.
7272. When might a Sprint be abnormally terminated?
- AWhen the Development Team feels that the work is too hard
- BWhen the sales department has an important new opportunity
- CWhen the Sprint Goal becomes obsolete
- DWhen it becomes clear that not everything will be finished by the end of the Sprint
7373. If two Scrum Teams are added to the development of a product that previously had only one will be the immediate impact on the productivity of the original Scrum Team?
- AIts productivity is likely to decrease
- BIts productivity is likely to stay the same
- CIts productivity is likely to increase
7474. What best describes the Product Backlog
- AIt contains all foreseeable tasks and requirements from which the Scrum Team can develop and mantain a complete project plan
- BIt is baselined to follow change management processes
- CIt provides just enough information to enable a Scrum team to start the design phase of a product
- DIt is allowed to grow and change as more is learned about the product and its customers
7575. Which of the following are true about the Product Owner role?
- AThe Product Owner is accountable for ordering the Product Backlog.
- BThe Product Owner is one person.
- CMultiple people can share the Product Owner role on a Scrum team
- DThe Product Owner role can be played by a committee or a team of people
- EThe Product Owner can be influenced by a committee
7676. Who must do all the work to make sure Product Backlog items conform to the Definition of "Done"?
- AThe Development Team
- BThe Scrum Team
- CThe Product Owner
- DQA Specialists
- EThe Scrum Master
7777. If burndown charts are used to visualize progress, what d they track?
- AAccumulated cost
- BIndividual worker productivity
- CWork remaining across time
- DAccumulated business value delivered to the customer
7878. The Scrum master observes the Product Owner struggling with ordering the Product Backlog. What is an appropiate action for the Scrum Master to take?
- APresent the Product Owner with an ordered Product Backlog to use
- BOffer the Product Owner help in understanding that the goal of ordering the Product Backlog is to maximize value.
- CSuggest that the Development Team does the ordering to be sure that it is a feasible ordering of work
- DSuggest the Product Owner extend the Sprint, so he can have more time to order the Product Backlog
- EEncourage the Product Owner to work with the Development Team to see which items technically are be to implement.
7979. What happens if the Development Team cannot complete its work by the end of the Sprint?
- AThe Sprint is extended and Future Sprints use this new duration
- BThe Sprint is extended temporarally. Lessons are taken to ensure it doesn't happen again.
- CThe Sprint length holds and the Development Team continuosly learns what is actually possible to do within a Spring of this length.
8080. When is implementation of a Product Backlog item considered complete?
- AAt the of the Sprint
- BWhen the item has no work remaining in order to be released
- CWhen QA reports that the item passes all acceptance criteria
- DWhen all work in the Sprint Backlog related to the item is finished
8181. When can a Development Team cancel a Sprint?
- AIt can't Only Product Owners can cancel Sprints.
- BWhen the Product Owner is absent too often.
- CWhen functional expectations are not well understood.
- DWhen The selected Product Backlog items for the Sprint become unachievable
- EWhen a technical dependency cannot be resolved.
8282. A new developer is having continuing conflicts with existing Development Team members and creating a hostile environment. If necessary, who is responsible for removing the team member?
- AThe Development Team is responsible, and may need help from the Scrum Master
- BThe hiring manager is responsible, because he/she hired the developer
- CThe Scrum Master is responsible, because he/she remove impediments.
- DThe Product Owner is responsible, because he/she controls the return on investment(ROI).
8383. What are three benefits of self-organization?
- AIncreased creativity
- BIncreased self-accountability
- CIncreased accuracy of estimates
- DIncreased commitment
- EIncreased rule compliance
8484. Who should make sure everyone on the Development Team does his or her tasks for the Sprint?
- AThe Scrum Master
- BThe Development Team
- CThe Project Manager
- DThe Product Owner
- EAll of the above
8585. Multiple Scrum Teams working on the same project must have the same Sprint start date.
- ATrue
- BFalse
8686. Which two things are appropiate for a Scrum Master to do if the Development Team doesn't have the engineering tools and infrastructure to completely finish each selected Product Backlog item?
- ARefocus the current Sprint on establishing the Development Team's infrasstructure instead of delivering increment.
- BEncourage the Product Owner to accept partially done increments until the situation improves.
- CDeclare the Development Team not ready for Scrum.
- DHave the Development Team establish a Definition of Done that is actually possible to achieve given current circumstances.
- ECoach the Development Team to improve its skills, tools and infrastructure over time and adjust the Definition of Done accordingly.
8787. Who determines when it is appropiate to update the Sprint Backlog during a Sprint?
- AThe Scrum Team
- BThe Project Manager
- CThe Development Team
- DThe Product Owner
8888. Which two things should the Development Team do during the first Sprint? (select two)
- ADevelop at least one piece of functionality
- BAnalyze, design, and describe the complete architecture and infrastructure
- CMake up a plan for the rest of the Project
- DAnalyze, describe and document the requirements for the subsequent Sprints.
- ECreate an Increment of potentially releasable software
8989. When should a Sprint Goal be created?
- ADuring Sprint Planning
- Bit should have been created in the previous Sprint during Product backlog refinement
- CIt must be established before Sprint Planning in order to begin planning
- DAt any time during the Sprint
- EA Sprint Goal is not mandatory in Scrum
9090. What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity?
- ABy facilitating Development Team decisions
- BBy removing impediments that hinder the Development Team
- CBy ensuring the meetings start and end at the proper time
- DBy Keeping high value features high in the Product Backlog.
9191.When does the second Sprint start?
- AImmediately after the first Sprint
- BOnce the architectural changes for the second Sprint have been approved by the senior architect
- CAfter the customer completes acceptance testing of the first Sprint
- DAfter the Product Backlog for the second Sprint has been selected
9292.What is included in the Sprint Backlog?
- ATasks
- BUse Cases
- CUser Stories
- DTests
9393.What are two responsibilities of testers in a Development Team (select two)
- AEveryone in the Development Team is responsible for quality
- BScrum has no "tester" role
- CFinding bugs
- DTracking quality metrics
9494.One of the Scrum events is the Daily Scrum. What are two intended outcomes of the Daily Scrum? (select two)
- AA status report for the upper management
- BNew impediments for the Scrum Master to take care of
- CA shared understanding of the most important work to be undertaken next to achieve the best possible progress toward the Sprint goal
- DAn updated Scrum board to make Sprint progress transparent for the stakeholders
9595.When many Development Teams are working on a single product, what best describes the definition of Done?
- AEach Development Team defines and uses its own. The differences are discussed and reconciled during a hardening Sprint
- BAll Development Teams must have a definition of "Done" that makes their combined work potentially releasable
- CEach Development Team uses its own but must make their definition cleat to all other teams so the differences are known
- DIt depends
9696.A Development Team is required to deliver a done increment by the end of a Sprint. Select two statements that explain what "done" means (select two)
- AAll work the Development Team is willing to do
- BWhatever the Product Owner defines as quality
- CEach Development Team uses its own but must make their definition cleat to all other teams so the differences are known
- DNo work left from the definition of "Done"
9797.When a Development Team is having trouble delivering a working increment because they don't understand the functional requirement, what should they do?
- APartially complete the functionality
- BCollaborate with the Product Owner to determine what is possible and acceptable
- CAdd a specialist to the Development Team
- DDefer the work to a more appropriate Sprint
9898.When a Development Team determines that it has over committed itself for a Sprint, who has to be present when reviewing and adjusting the Sprint work selected?
- AThe Development Team
- BThe Product Owner and the Development Team
- CThe Scrum Master, project manager and Development Team
- DNobody
9999.Which answer best describes the topics covered in Sprint Planning?
- AHow conditions have changed and how the Product Backlog should evolve
- BWhat to do and who will do it
- CWhat can be done and how to do it
- DWho is on the team and what team member roles will be
100100.Why is the Daily Scrum held at the same time and same place?
- AThe Product Owner demands it
- BThe consistency reduces complexity
- CRooms are hard to book and this lets it be booked in advance
- DThe place can be named
101101.Who is responsible for tracking the remaining work of the Sprint?
- AThe Product Owner
- BThe Development Team
- CThe Scrum Master
- DThe Project Manager
102103.During a Sprint Retrospective, for what is the Product Owner responsible?
- ASummarizing and reporting the discussions to the stakeholders
- BThe Product Owner should not take part in Sprint Retrospective
- CCapturing requirements for the Product Backlog
- DParticipating as a Scrum Team member
103104.Which are not appropriate topics for discussion in a Sprint Retrospective? (select two)
- AHow the team does its work
- BTeam relations
- CDefinition of "Done"
- DSprint Backlog for the next Sprint
104105.The Product Backlog is ordered by:
- ASize
- BRisk
- CImportance, where the most important items are at the top at all times
- DItems are randomly arranged
105106.What activities would a Product Owner typically undertake in the phase between the end of the current Sprint and the star of the next Sprint?
- ARefine the Product Backlog
- BThere are no such activities. The next Sprint starts immediately after the current Sprint
- CUpdate the project plan with stakeholders
- DWork with the QA departments on the increment of the current sprint
106107.During the Daily Scrum, the Scrum Master's role is to:
- AMake sure that all 3 questions have been answered
- BTeach the Development Team to keep the Daily Scrum within the 15 minute time-box
- CLead the discussions of the Development Team
- DAll of the above
107108.Every Scrum Team must have a Product Owner and Scrum Master
- AFalse. A Scrum Master is only required when asked for by the Development Team
- BTrue. Outcomes are affected by their participatioin and availability
- CTrue. Each must be 100% dedicated to the Scrum Team
- DFalse. A Product Owner can be replaced by a business analyst in the Development Team.
108109.Which does a self-organizing Development Team choose?
- ASprint length
- BStakeholders for the Sprint Review
- CHow to best accomplish its work
- DProduct Backlog ordering
109110.What is the accountability of the Product Owner during Sprint 0?
- AMake the complete project plan to commit date, budget and scope to the stakeholders
- BGathering, eliciting, and analyzing the requirements that will be inserted into the Product Backlog
- CThere is no such thing as Sprint 0
- DMake sure enough Product Backlog items are refined to fill the first 3 sprints
110111.Which of the following might the Scrum Team discuss during a Sprint Retrospective?
- AMethods of communication
- BIts Definition of done
- CThe way the Scrum Team does Sprint Planning
- DAll of the above
111112.For the purpose of transparency, when does Scrum say a new increment of working software must be available?
- AAt the end of every Sprint
- BBefore the release Sprint
- CAfter the acceptance testing phase
- DEvery 3 sprints
112113.Which three of the following are timeboxed events in Scrum?
- ASprint Planning
- BSprint 0
- CSprint Retrospective
- DDaily Scrum
113114.When is the Sprint Backlog created?
- ADuring the sprint
- BDuring the Sprint Planning meeting
- CAt the beginning of the project
- DPrior to the Sprint Planning meeting
114115.Why should the Product Owner be present at the Daily Scrum?
- ATo hear about impediments in functionality
- BHe/She doesn't need to be there
- CTo participate as a Scrum Team member
- DTo represent the stakeholders's point of view
Information
- Description
- Test Exam Quiz on ExamTest, created by jameslimon Lim on 21/03/2016.
- Author
- jameslimon Lim
- Language
- Español
- Views
- 14
- Tags
- Rating
- No ratings yet Rate this quiz
More on Scrum Framework and Principles