Work-site marker boards, the RT3199 work-site certificate, suspending a work site and what the ES agrees with each COSS and IWA.
Updated 17 November 2026 for the rules in force now and the 5 December change
Key rules
See all 20 key rulesThe ES must confirm the line, exact WSMB mileages, any trains around which the work site will be taken, and arrangements for every level crossing within it.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
A WSMB is placed in the four-foot at each end of a work site.
GERT8000-T3 Possession of a running line for engineering work, Indicating each work site
A WSMB must be at least 100 metres from the WSMB of another work site.
GERT8000-T3 Possession of a running line for engineering work, Indicating each work site
WSMBs are not needed if there will be no engineering train or on-track plant movements within the possession.
GERT8000-T3 Possession of a running line for engineering work, Indicating each work site
Only the ES can authorise a train to pass a WSMB displaying two red lights and enter the work site.
GERT8000-T3 Possession of a running line for engineering work, Indicating each work site
Only the PICOP can authorise a train to pass a WSMB displaying two yellow lights and leave a work site.
GERT8000-T3 Possession of a running line for engineering work, Indicating each work site
When authorised to set up a work site, the ES may allow WSMB placement duties and ac method isolation duties by an isolation COSS.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
Before an isolation COSS starts work, the ES must give a work-site briefing and record the required information in Appendix B of RT3199.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
The ES must not allow other work to start until the PICOP says the work site has been granted.
GERT8000-HB12 Duties of the ES in a possession, Setting up the work site
The ES must tell the PICOP when the WSMBs at each end of the work site are in position.
GERT8000-HB12 Duties of the ES in a possession, When the work site is set up / 4.1
The PICOP dictates the work-site details, including every level-crossing arrangement, for the ES to record on RT3199 and read back.
GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
When satisfied the details are in order, the PICOP gives the ES their full initials and authority for work to start.
GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
Sample questions
1. Under the rules in force until 4 December 2026, the ES confirms both WSMBs are in position. How are the details entered on the RT3199?
- The PICOP dictates them and the ES reads them back.
- The ES dictates them and the PICOP reads them back.
- The PICOP completes the certificate and the ES checks it.
- The ES completes the certificate and reads it to the signaller.
Answer: A. The PICOP dictates them and the ES reads them back.
The PICOP dictates the details for the ES to enter on the RT3199. The ES then reads the details back to the PICOP.
- The ES dictates them and the PICOP reads them back: The PICOP dictates; the ES reads back.
- The PICOP completes the certificate and the ES checks it: The ES fills in the certificate, not the PICOP.
- The ES completes the certificate and reads it to the signaller: The ES reads the details back to the PICOP, not the signaller.
Source: GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
2. Under the rules in force until 4 December 2026, the ES has read back the RT3199 details, including the level crossing arrangements. You are satisfied everything is in order. What must you give the ES when authorising work to start?
- Your surname and the possession reference.
- Your first initial and the work-site reference.
- Your full initials and authority to start work.
- Your surname and the authority to remove the WSMBs.
Answer: C. Your full initials and authority to start work.
Once satisfied that all details are in order, the PICOP gives the ES their full initials and authorises work to start. The PICOP must also record the details on the RT3198.
- Your surname and the possession reference: The PICOP must give full initials, not just a surname.
- Your first initial and the work-site reference: One initial is not sufficient; full initials are required.
- Your surname and the authority to remove the WSMBs: The authority is to start work, not to remove the boards.
Source: GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
3. An ES tells you their work site is suspended but its WSMBs will remain in place. What must you record on your RT3198?
- Only the time the boards were erected.
- The details of the suspension.
- Only the next planned train movement.
- The details when the boards are eventually removed.
Answer: B. The details of the suspension.
The PICOP must record the details when an ES reports a suspension with the WSMBs remaining in place. This keeps the RT3198 updated with the work-site situation.
- Only the time the boards were erected: The suspension details must be recorded, not just the erection time.
- Only the next planned train movement: The requirement is to record the suspension details, not just a movement.
- The details when the boards are eventually removed: The suspension details must be recorded when reported, not deferred until removal.
Source: GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
4. A work site is suspended and its WSMBs remain in place. A movement needs to enter the site. What must you do?
- Allow it past the board after confirming the site is suspended.
- Allow it past the board if the ES has finished work.
- Do not allow it to pass the board into the site.
- Allow it past the board after recording the movement.
Answer: C. Do not allow it to pass the board into the site.
The PICOP must not allow a movement to pass a WSMB into a suspended work site. Suspension does not make the board available for a movement to pass.
- Allow it past the board after confirming the site is suspended: Confirming the suspension does not permit entry past the board.
- Allow it past the board if the ES has finished work: The rule prohibits entry into the suspended site past a WSMB.
- Allow it past the board after recording the movement: Recording a movement does not permit it to enter past the board.
Source: GERT8000-HB11 Duties of the person in charge of the possession, Allowing work to start inside the work / 6.4 When a work site is suspended
5. You are about to act as ES. What evidence of competence must you have with you?
- A valid certificate of competence issued by the PICOP
- A copy of the possession notice issued by your employer
- A valid certificate of competence issued by your employer
- A copy of the work-site certificate issued by the PICOP
Answer: C. A valid certificate of competence issued by your employer
An ES must have a valid certificate of competence issued by their employer with them. This applies when acting as ES.
- A valid certificate of competence issued by the PICOP: The certificate must be issued by your employer, not the PICOP.
- A copy of the possession notice issued by your employer: A possession notice does not replace the certificate of competence.
- A copy of the work-site certificate issued by the PICOP: A work-site certificate does not replace the certificate of competence.
Source: GERT8000-HB12 Duties of the ES in a possession, Definitions / 2