CMA Part 1 Budgeting methodologies: practice questions

The different ways of building a budget.

9 questions · 10 key rules

Updated 19 November 2026 for the ICMA outline effective 1 September 2024

Key facts

Sample questions

Tap a question to see the answer and the rule behind it.
  1. Budgeting methods1. A manufacturer expects sales of 8,000 units next year. It plans to start with 1,000 finished units and end with 1,500. How many units should its production budget include?
    1. 7,500 units
    2. 8,000 units
    3. 8,500 units
    4. 9,500 units
    Show answer and explanation

    Answer: C. 8,500 units

    Budgeted production equals expected sales plus desired ending inventory minus beginning inventory: 8,000 + 1,500 − 1,000 = 8,500 units. This tests Part 1, B.4 Budgeting methodologies.

    Why the others are wrong

    • 7,500 units: 7,500 reverses the inventory adjustment.
    • 8,000 units: 8,000 ignores the planned increase in inventory.
    • 9,500 units: 9,500 adds ending inventory without subtracting beginning inventory.

    Source: Outline topic: Budgeting methodologies

  2. Budgeting methods2. A retailer expects strong annual profits but must determine whether it can pay suppliers each month. Which master budget component best addresses this concern?
    1. Sales budget
    2. Production budget
    3. Cash budget
    4. Budgeted income statement
    Show answer and explanation

    Answer: C. Cash budget

    The cash budget estimates the timing of cash receipts and payments, helping the retailer identify months with potential cash shortages. This tests Part 1, B.4 Budgeting methodologies.

    Why the others are wrong

    • Sales budget: The sales budget forecasts sales, not monthly cash available for payments.
    • Production budget: The production budget plans units to produce, not cash availability.
    • Budgeted income statement: The budgeted income statement estimates profit, not the timing of cash flows.

    Source: Outline topic: Budgeting methodologies

  3. Budgeting methods3. A manufacturer wants to build its budget around the activities required to meet forecast demand. Which approach best fits activity-based budgeting?
    1. Start with last year's spending and add a percentage
    2. Set a fixed spending limit for each department
    3. Estimate demand for activities and the resources they require
    4. Prepare budgets only for projects already approved
    Show answer and explanation

    Answer: C. Estimate demand for activities and the resources they require

    Activity-based budgeting estimates the activities needed to meet forecast demand, then budgets the resources needed to perform them. Part 1, B.4 Budgeting methodologies.

    Why the others are wrong

    • Start with last year's spending and add a percentage: A. Adjusting prior spending is an incremental approach.
    • Set a fixed spending limit for each department: C. Department limits alone do not identify activity demands.
    • Prepare budgets only for projects already approved: D. Approved projects alone do not establish an activity-based budget.

    Source: Outline topic: Budgeting methodologies

  4. Budgeting methods4. A manufacturer forecasts 800 production batches. Each batch requires 2 inspections, and each inspection is budgeted to cost $15. Under activity-based budgeting, what is the budgeted inspection cost?
    1. $6,000
    2. $12,000
    3. $18,000
    4. $24,000
    Show answer and explanation

    Answer: D. $24,000

    Budgeted inspection cost equals forecast batches multiplied by inspections per batch and cost per inspection: 800 × 2 × $15 = $24,000. Part 1, B.4 Budgeting methodologies.

    Why the others are wrong

    • $6,000: A. This understates the number of inspections.
    • $12,000: B. This omits the second inspection per batch.
    • $18,000: C. This understates the total cost of the required inspections.

    Source: Outline topic: Budgeting methodologies

  5. Budgeting methods5. A department is preparing a zero-based budget for next year. How should it determine its spending requests?
    1. Justify proposed activities and their costs
    2. Adjust last year’s spending for inflation
    3. Fund each activity at last year’s level
    4. Set spending equal to this year’s revenue
    Show answer and explanation

    Answer: A. Justify proposed activities and their costs

    Zero-based budgeting requires managers to justify proposed activities and the resources needed for them, rather than automatically carrying forward prior spending. This tests Part 1, B.4 Budgeting methodologies.

    Why the others are wrong

    • Adjust last year’s spending for inflation: An inflation adjustment uses prior spending as the starting base.
    • Fund each activity at last year’s level: Prior-year funding is not automatically continued under zero-based budgeting.
    • Set spending equal to this year’s revenue: Revenue does not by itself justify the cost of each activity.

    Source: Outline topic: Budgeting methodologies

Sign up free

Other CMA Part 1 topics

GoConqr Original practice questions. Think a question is wrong? Use 'Report' under it.

Independent revision resource. Not affiliated with IMA, ICMA or any CMA course provider.

© Visual Maths Resources Ltd