Quiz
PMP exam 1
Create a free account to finish this quiz
Save your progress and see your final score.
Already have an account? Sign in
Questions in this quiz (100)
1A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project.
The sponsor says the project is small and simple so there is no need for a project charter. What should the project manager do?- ASpeak with peers about the need for a project charter
- BDevelop the project charter and send it for approval
- CExplain that a project charter is necessary to ensure agreement on scope and deliverables and to define the project manager's responsibilities
- DAgree that the project does not require a project charter, especially since the deliverables and milestones are included in the project management plan
2A company is transitioning from a predictive to an agile approach. During the last two sprint reviews, the product owner complained about the development team, indicating that the increments do not meet the acceptance criteria defined in the user stories. The development team complained about the product owner, who is defining sprint backlog items, because the backlog items cannot be delivered during the 2-week sprints agreed to at the beginning of the project.
How should the project manager resolve this situation in their new role as servant leader?- AReview the organizational process assets (OPAs) to find similar situations and review the resolution actions taken
- BRequest that the team use the next sprint to complete all technical debt remaining from the previous sprints
- CExtend the sprints to 3 weeks to allow the work requested by the product owner to be completed
- DEncourage the whole team to be empowered and accountable for the decisions made according to their roles
3project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
- ACoercion
- BConflict resolution
- CEmotional intelligence
- DNegotiating
4During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.
What two actions should the project manager take to prevent the team from being unqualified? (Choose two)- AExclude the activities from the roadmap
- BEncourage working in pairs and knowledge sharing
- CTeach the entire team the new skill.
- DFacilitate a training event with an external trainer
- EIncrease the time estimates on the activities that require such abilities
5A project manager has been selected to deliver one of an organization's key flagship solutions Critical success factors include agility, market adaptation, and a quick response to market offerings What is one of the key activities that the project manager should undertake to ensure company success?
- AReview the project objectives with the project sponsor to agree on more realistic and achievable project plans and deliverables
- BRequest more funding from the project sponsor to hire additional skilled resources and to incorporate additional quality in the project delivery approach and outcome
- CConduct periodical reviews of the project plans, objectives, and deliverables to ensure all relevant data are captured to continue making informed project decisions
- DCreate a business case after performing a market review, and then submit it to the sponsor to modify the project deliverable to meet the newly defined objectives
6A labor union contract negotiation is delaying the completion of a project to build a new manufacturing plant. Because the labor contract was due for renewal this year, the project manager documented the negotiation process as a risk to the project. The project was about to start the first phase of equipment installation at the plant when the negotiation began.
How should the project manager address the situation?- AMeet with the project team to determine options for risk mitigation.
- BLog the issue and follow the planned actions in the risk response plan.
- CAcquire contract resources and submit a change request for the cost impact.
- DEscalate the issue to the steering committee to ask for mitigation support.
7A project manager has just finished initiating a project. While planning the project manager notes that several essential team members do not have the required skills for key tasks later in the project.
What should the project manager do first?- ADevelop the resource management plan and ensure adequate training
- BReplace the current project team members
- COutsource the task to be completed by a specialized vendor
- DUpdate the issue log to account for the lack of team member qualifications
8During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?
- AUpdate the issue log and act to minimize the impact
- BUpdate the schedule to include the delay
- CAdd the risk and the delay to the risk register
- DEscalate to the management team for delay approval
9A software project using an agile approach is facing quality issues with every release, generating many production problems. What should the project manager do to fix the problem and improve the quality?
- ASeek extra funding approval with the sponsor to replace junior team members for more experienced ones
- BCreate a reward system granting incentives to the team members who are able to catch more defects
- CHire an external company to add an additional layer of testing, making sure that the final product is well inspected before releasing.
- DUse the retrospective meeting to better understand the root cause of the quality problems and put together a plan with the team to address the problems
10During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain feedback from on project deliverables. What should the project manager do?
- AShare a template the stakeholder to receive feedback on deliverables.
- BAsk the project sponsor to arrange a meeting the stakeholder.
- CUse networking skills to approach the stakeholder.
- DUpdate the stakeholder engagement plan for the stakeholder.
11An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?- AProduct backlog, budget, resource management plan
- BBudget, minimum viable product (MVP), retrospective notes
- CResource management plan, retrospective notes, backlog grooming
- DBacklog grooming, product backlog, minimum viable product (MVP)
12A key project stakeholder does not attend any of the project meetings and is providing false information that the project team is not delivering on time. What should the project manager do to address this situation?
- ACreate a new communication artifact for the key stakeholder.
- BEmail the latest status report to the key stakeholder.
- CShare the meeting recordings with the key stakeholder.
- DDiscuss communication needs with the key stakeholder.
13A large construction project is progressing well as per the project objectives. The project manager would like to report the project's value to the project sponsor and seek the next phase of funding closure.
What should the project manager do?- AEnsure a measurement system is in place like earned value analysis (EVA) to track project value for the project sponsor.
- BSubmit a detailed report on the cost budget vs. the cost actuals as the project sponsor will want to know more about finances.
- CCreate a detailed project report on successes and challenges for the project sponsor.
- DArrange a site visit to show the project sponsor the construction progress in person.
14After difficult negotiations, a customer committed to pay the cost for changes to the project scope. The team seems unhappy as the project completion time will take longer than previously scheduled.
- AMotivate the team and deploy the necessary resources.
- BFind a way to maintain the project schedule.
- CImpose authority on the project.
- DRequest additional resources from the sponsor and motivate the team.
15A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.
What should be the project manager's next steps?- AConduct a proof of concept to make sure there are no problems in the revised design
- BAmend the design specifications and pass them to the development team for reprogramming
- CMake a change request and get format approval from the projeci owner
- DInform the client of the problem and follow the change request process
16An agile team has started a new project. When should the project manager organize their first team retrospective?
- AWhen the team completes a release of a monumental increment
- BWhen the team reaches a major milestone
- CWhen more than a few weeks have passed
- DWhen the work is progressing well through the team
17The project manager is experiencing delays with two critical tasks that are to be executed by two different teams The project manager realizes that the functional managers of these two teams have an unsolved conflict and they are not communicating properly.
What should the project manager do?- AArrange a meeting with the managers and try to reach an agreement.
- BCommunicate with the project sponsor regarding the need to resolve the conflict between the managers.
- CEvaluate the impact of the delay on the project and look for alternatives to create a remediation plan
- DMeet with both teams and their managers and try to figure out the root cause of the conflict
18A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs How should the project manager ensure the work continues smoothly?
- APostpone the required work on the project until school holidays begin
- BAdvise the school to close (or the duration of the project work
- CContinue the work as planned and inform the school when the project team arrives on- site
- DLiaise with the school to include nonworking project hours during school start and finish times
19A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?
- APropose a phased project approach with multiple small interactions and build trust with the stakeholder through frequent value delivery.
- BDocument the request and escalate to upper management to consider a modification of the project charter.
- CAgree on a predictive approach, but apply agile concepts under the project management umbrella.
- DEnsure the stakeholder that an agile approach will deliver all of the expected results in a shorter period of time.
20An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?
- AAsk for additional team members to maintain the velocity
- BImplement a checkpoint in the iteration to verify if the team is on track
- CConduct a focused retrospective to help the team to discover the root cause
- DAsk the team to have a lower commitment for the next iteration
21An IT company's office is closed abruptly due to a new government restriction. All employees are now working remotely. Project team A has a critical project delivery due in 2 weeks. The project manager, apprehensive about this sudden change, instantly emails the customer explaining that the project delivery will be delayed. The customer is unhappy with this and has escalated the issue to senior management.
What should the project manager have done differently?- ACommunicated a new delivery date to the customer along with the news about the delay
- BDisclosed to senior management in confidence, then communicated the delay to the customer
- CAssessed the situation with the project stakeholders first and communicated the impact to the customer
- DSpoken to the customer on the phone and explained the reason for the delay instead of writing an email
22A project manager needs the team to define the steps and identify the risks of migrating data to a new system.
What type of leadership should the project manager use to accomplish this?- ALaissez-faire
- BTransformational
- CDynamic
- DServant
23A project manager is leading a hybrid project. The self-organizing teams are continually late in delivering their demos, resulting in low morale. The steering committee is familiar with the reporting and planning associated with a predictive approach and is concerned about the project because it is unclear if the expected value will be delivered.
What should the project manager do?- AEmphasize to the teams the importance of reaching the agreed deadlines and value.
- BRequest to coach the team to ensure motivated project team members are on board.
- CUpdate the project schedule with a buffer to reflect the expected delays being incurred by the team.
- DSuggest to the teams to limit the scope of work per iteration so they will start to deliver more reliably.
24A project manager is performing earned value management (EVM) for a cross-country pipeline project. The project manager has determined the ratio of earned value (EV) to actual cost (AC) for the project and has found the calculated result to be 0.9024.
What does this value mean for the project?- AThe project has started exceeding the planned cost
- BThe project is earning less value an was planned.
- CThe project has earned more value than planned.
- DThe project is close to exceeding the planned cost.
25A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed To what type of communication is the team member referring?
- AMass communication
- BPush communication
- CPull communication
- DInteractive communication
26According to the project contract the delivery date is approaching However one important material is still not on site The construction work will have to stop and wait for this special material, delaying the project.
What should the project manager do?- ARecord it in the risk register
- BAsk the client to help solve the problem
- CStart procuring this material from another supplier.
- DEngage the project team to look for alternatives to find a solution
27A project manager is reviewing the status of a large project with team members in different countries. Through the status review, the project manager notices that one team is consistently behind schedule and their work often needs to be corrected.
What should the project manager do to improve the quality of this team's work?- AEvaluate the issue with the team to determine if they have the necessary skills to perform assignments.
- BReview the issue with the project sponsor and work to reduce the scope for that team.
- CGuide all team members and bring in external consultants to complete the work.
- DAsk a local subject matter expert (SME) to assist the team in reviewing the project requirements.
28A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.
What should the project manager have done differently?- AInvited the customer to the daily meetings
- BChanged the A project is implementing an agile strategy, and a minimum viable product (MVP) was agreed upon. After the first iteration review, the customer explained that the first deliverable is not of great value.
What should the project manager have done differently? - CHelped the team redefine the MVP
- DChanged the duration of iterations to deliver more value
- EValidated the iteration goals with the customer
29A project manager is working with a team that is new to agile. One of the more influential stakeholders struggles with the nature of agile. The project manager knows that this stakeholder is needed as an advocate and wants to do everything possible to make the stakeholder comfortable with the project.
What should the project manager include in the status report to illustrate the project's performance?- AResults of the MoSCoW assessment
- BCost-benefit analysis
- CReturn on investment (ROI) analysis
- DEarned value analysis (EVA)
30A project manager has been asked to participate in the procurement process for a software application that allows customers to buy online e-learning courses. The project manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?- AEnsure that the requirements for the project are understood and that the objectives are verified before approval of an agreement.
- BInform the project sponsor that once the agreement has been signed, there cannot be any changes to the scope of the project.
- CNotify the project sponsor that the project manager cannot be involved in the agreement negotiation
process. - DAsk the project sponsor to involve the legal department in the negotiation for the project agreement.
31After completion of a project with specific users in various countries, the project manager's supervisor asks if the project users are satisfied with the way the project was run. What two actions should the project manager take? (Choose two)
- APrepare the lessons learned from the project phase.
- BObtain official approval on the new process from the various countries
- CSend a questionnaire to the project participants and seek their feedback.
- DRefer to the communications management plan
- EDeliver the project materials to the users and see if they have any comments
32A project manager was recently assigned to a new project that is about to start. The organization has already signed a fixed-cost contract with the customer detailing the scope and final delivery date, but the project manager has identified several internal constraints and conditions that will certainly prevent the project from being completed in the number of iterations initially planned.
What should the project manager do next?- ACreate an issue log template that will be used to identify and track impediments.
- BCreate a contingency plan in case the project deviates from the initial plan.
- CCreate a schedule management plan to ensure the project meets the delivery date.
- DCreate an assumption log and map assumptions to impediments based on the impact to the project value.
33A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues. What should the project lead have done initially to avoid this situation?
- AReviewed the project management plan
- BCreated a detailed operations manual
- CIncreased support hours for the hours of operation
- DInvolved operations stakeholders during planning
34A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members.
The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?- AReview the work allocation and reassign some tasks to shorten the critical path.
- BMaintain the task assignments as planned and compress the other tasks to keep the project on schedule.
- CAsk the team members to work overtime to finish the tasks on time according to the schedule.
- DKeep the task assignments unchanged since the project management plan has been approved.
35On a recently completed prefect a project manager noticed that some of the subcontractors approached the client directly with questions. These subcontractors had a previous direct reporting relationship with the client.
The project manager is now in the initial stage of a new project with the same subcontractors and client.
How should the project manager set up communications?- AInform the client that all communications moving forward will go through the project manager
- BEnsure that the communications management plan covers contractual obligations
- CConsult the communications management plan from a recent project that has been closed
- DUpdate the communications management plan to allow the subcontractors to communicate directly with the client
36A supplier was supposed to mobilize a government-issued, licensed piece of equipment two days ago, but did not. The procurement manager was informed that the supplier failed to check the validity of the license, which expired last week. The supplier had already submitted an application to the authorities, but it generally takes one to three weeks to process the application, which will affect the critical path.
Which action should the project manager take?- AUpdate the project team on the delay so that resources can be utilized elsewhere.
- BAnalyze the schedule and look for fast tracking and crashing alternatives.
- CReview the terms of the contract in order to determine next steps.
- DUpdate the lessons learned register to serve as an input for future material transactions.
37A company's project management office (PMO) has been trying to implement an adaptive approach in the project management framework and a project manager has been asked to use adaptive tools in their next project This is not the first time the request has been made and the previous project failed when adaptive tools were implemented What should the project manager do?
- APrepare a change request and seek approval from the steering committee regarding the new project framework
- BConduct individual interviews with key stakeholders in order to understand all concerns, then prepare a communications management plan
- CBring in a third party company to develop and implement a hybrid framework for this specific project.
- DRecommend to the PMO that it is not the right time to start implementing adaptive tools in projects
38During project completion, a project manager receives a request from the customer for a reduced cost of goods. The customer's request will affect the sales department's budget and forecast.
In order to reach a consensus and have a successful project completion, what should the project manager do first?- AAnalyze the bounds of the negotiation for agreement with both parties
- BIdentify and satisfy both parties' underlying wants.
- CComply with the customer's request to achieve the project mandate.
- DInitiate a change request to accommodate the revised cost of goods
39A team member is openly criticized by others during a standup meeting for failing to complete yesterday's tasks. What should the agile coach do first to address the situation?
- AEmphasize the ground rules and then focus on today's activities and impediments.
- BLet the discussion go on as it is important that the team is clear on priorities for the day.
- CAddress the team members involved during the next sprint retrospective.
- DAvoid the discussion by referring to the team charter.
40A product owner has added new high-priority work to the backlog, A project manager is working with a dedicated agile team that does not specialize in this specific area of work. The team reviewed the work and wants to accept it but acknowledges it may not have the same level of efficiency as another team having specialization in this area.
What should the project manager do In this scenario?- AAdd temporary members the specialized skill set to the team to accomplish the work with a high level of confidence.
- BAssess the impact of a possible delay to the project and encourage the team to take the work if the impact is tolerable.
- CAccept the work and outsource to another team that has the specialized skill set; then integrate the solution
- DReject the work from this team's backlog and ask the product owner to add It to another team's backlog.
41During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables How should the project manager mitigate this risk without compromising the completion date?
- AReview the integrated change control process to restrict the number of changes
- BFocus on delivering incremental value through multiple smaller deliveries
- CRequest sponsor support to get buy-in from the users and stakeholders
- DRestart the stakeholder engagement process by collecting user requirements again
42A new member was included on a project team in an ongoing software project. This team member was the only available resource but does not have the proper experience to accomplish the activities.
What should the project manager do to ensure this team member's lack of experience does not negatively impact the project?- ASchedule a training course for the new team member to fill in their gaps in experience.
- BLog this as an issue in the project issue log and speak with the resource manager.
- CProvide weekly feedback to all project team members, including the new member
- DEnsure that coaching meetings are in place for this team member within the project timeline.
43A project manager was just assigned to a project as the leader of an experienced agile team. How should the project manager influence the team to accomplish the project objectives?
- AExpress trust in the team's ability to fulfill the necessary deliverables.
- BAssert judgment over the team.
- CUse a plan-driven approach in order to demonstrate control over the project.
- DIncrease the amount of subject matter experts (SMEs) to get better results.
44A project manager is leading a project which shows a trend to exceed the cost baseline What should the project manager do first to manage the budget?
- AAsk the project sponsor for assistance in getting the budget back on track
- BMeet with the project team to analyze the actual cost to determine deviations
- CInform the stakeholders that the project will be finished over budget.
- DIssue a change request including the analysis to increase the budget
45A company is changing their current business model The change requires implementing a complex project using multiple agile teams.
What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)- AIndependent personal testing
- BSecurity and performance testing
- CAn experimental approach to cover all possible choices
- DStory testing
- ETests based on behavior and test-driven development
46A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to reduce conflicts in the company's internal tracking system. With over 1,000 people in the company who will benefit from the software, the project manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide upon the most effective way to communicate progress.
What should the project manager do?- ASend weekly emails to each stakeholder providing them with the project's progress.
- BAsk the project sponsor to disseminate project progress across the organization's stakeholders.
- CSet up an intranet site and allow stakeholders to access the relevant project information.
- DDivide up the organization among the project team to provide direct project updates.
47A company has always acquired very specialized services from local companies for its projects. During the planning stage for a regulatory project, the project manager is informed that local vendors would not be able to operate due to an unexpected major event. There is an option to hire the same services from companies in other countries.
What should the project manager do in this situation?- APlan to execute the procurement tasks in a virtual environment.
- BReview organizational process assets (OPAs) for similar projects
- CCreate a change request to extend the duration of the project.
- DAsk the project sponsor to put the project on hold.
48A subcontractor informs the project manager that they are unable to supply a key component to the project. What should the project manager do?
- ADiscuss the issue with the project sponsor and request extra time and budget to obtain the component from a different supplier.
- BRaise a new risk in the risk register, perform a risk assessment, and convene SMEs and relevant stakeholders to plan a risk response
- CSubmit a change request to the change control board (CCB) for changes to the performance measurement baseline to obtain the component from a different supplier.
- DRaise a new issue in the issue log and convene subject matter experts (SMEs) and relevant stakeholders to identify alternatives to address the problem.
49Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects How should a project manager solve this issue?
- APropose implementing a new project management information system (PMIS).
- BRequest a meeting with senior management to escalate the situation
- CPromote adoption of the communications management plan with the project team.
- DHost a team-building event to develop team cohesion and improve communication
50A project manager has been assigned to lead a project to deploy a new system. The stakeholders disagree on the project objectives and approach.
What should the project manager do?- ACreate a roles and responsibilities matrix based on the project charter and ask the sponsor to share it all stakeholders to provide credible authority
- BConduct scoping workshops the project team to create a work breakdown structure ABS), assign tasks to various entities share this all stakeholders, and ask the team to complete their tasks as scheduled
- CConduct a general meeting all stakeholders and review and address a list of activities for each of them
- DBreakdown the situation to identify the root causes for the disagreement and then work each stakeholder and participating entity on their exact roles and responsibilities
51A project manager has been moved to a new division and is in charge of an existing project in an unfamiliar domain When attempting to gain an understanding of the risks for this agile project what is the primary tool the project manager should employ?
- AProbability assessments
- BCollaborative discussions
- CWorkshops for risk avoidance
- DInterview with the project champion
52In a hybrid project, 100 new base stations are being added to a 4G mobile network every month. At the end of the first month, the team is behind the target and the operator is losing money. The stakeholders are requesting information on when the base stations can go live and begin to bill.
What should the project manager do to take the schedule back and accelerate the return on investment (ROI) of the project?- AChange the project approach to predictive.
- BIncrease reporting to the business.
- CClarify the agile and predictive modules.
- DReconsider necessary schedule reserves.
53Two functional managers disagree on key features of one deliverable during the planning of a project The project manager discovers that each manager included requirements that contradict each other The functional managers do not want to meet with each other to find a solution This situation has been escalated to the sponsor who requests a meeting with them What strategy should the project manager use to resolve this conflict in the meeting?
- AExplain to the managers that the contradicting requirements are being considered for implementation in the project
- BExplain to the managers that only one of the two requirements can be implemented, and submit a change request,
- CEnsure that both managers understand the requirements and search for a solution that best satisfies this deliverable
- DRequest that the managers explain why each requirement must be implemented and decide by considering the cost and benefits
54A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between:
+ Test the product
+ Release to customer
According to the quality management plan, the product must be tested before being released
How should the project manager enter this dependency?- AFinish to start
- BStart to start
- CStart to finish
55A company is undergoing a digital transformation and is changing its project portfolio to an agile approach. As a result, the leadership is looking to update the performance measuring system for the workforce.
What should the project manager propose?- AKeep the performance management as is and focus on the achievement of scope, cost, and schedule indicators.
- BPropose an approach based on value measurement, such as the use of objectives and key results.
- CMaintain focus on cost indicators, but remove scope and schedule as they are flexible with an agile approach.
- DMaintain the focus on schedule indicators, but remove scope and costs as they are flexible with an agile approach.
56A project manager wants to ensure that the project acceptance criteria are met for all project deliverables.
What should the project manager do to accomplish this?- ASchedule regular meetings with project stakeholders to make sure they are satisfied.
- BInclude project stakeholder expectations and needs while creating project acceptance criteria.
- CCreate a statement of work (SOW) and ensure it remains unchanged during the project life cycle.
- DDiscuss project acceptance criteria with the project sponsor before the execution phase.
57A project manager's new employer decided to use an agile delivery approach to implement a new accounting system. The chief financial officer (CFO), who is also the project sponsor, is committed to a new way of working but does not have experience as a product owner. The project manager's background includes a couple of years' experience as an agile practitioner working as a scrum master.
What should the project manager do at the start of the project?- ACollaborate with the development team to help the project sponsor acquire the relevant skills.
- BAssume the product owner role until the project sponsor is ready to take over the product owner role.
- CDelay the build of the system until the project sponsor is ready to take over the product owner role.
- DWork with and assist the project sponsor in building and prioritizing the product backlog.
58Team morale is at an all-time low after an incident involving one of the team members. Which two actions should the project manager take to resolve the situation? (Choose two)
- AHost a special meeting to talk about what happened.
- BEscalate the issue to human resources (HR).
- CReview the lessons learned document with the team.
- DConduct a team-building workshop.
- EDiscuss this incident in the project review meeting.
59A project manager has been assigned to lead a major project in a government organization. There are no policies and procedures for project management since there is no project management office (PMO) The managers involved are unaware of their responsibilities for the project What should the project manager do?
- AStart planning the project and then request that a PMO be implemented in the organization
- BRequest that the implementation of a PMO be executed in parallel with the project
- CProvide project management training to only the internal team involved m the project
- DProvide project management training to the stakeholders and explain their responsibilities
60A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.
What should the project manager have done to prevent this?- AMonitored progress in achieving the business value throughout the project
- BAsked for additional time to achieve the project goal and increase business value
- CIncreased the number of project resources to ensure attainment of the business value
- DReviewed previous projects' lessons learned and applied them to this project
61A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.
Which activity should be considered as a priority?- AMark the product backlog completion status and update the communications management plan.
- BEnsure that knowledge transfer activities are executed as planned
- CRelease the resources and plan for a project completion celebration.
- DHold a steering committee meeting to inform them of the project completion
62The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible What three actions should the project manager take to address this situation? (Choose three)
- ADefine team ground rules
- BPerform a retrospective session
- CImplement daily team meetings.
- DRequest a manager performance review
- EConduct an annual review.
63A developer who has almost completed a required product feature for a prototype leaves the company in the middle of an iteration. What should the project manager do?
- AReview the backlog to reschedule the deliverable for a later iteration.
- BEngage with stakeholders directly to review the iteration process.
- CDetermine whether other cross-functional team members are able to take over the work.
- DGo to management and ask to hire a new external developer.
64A company starts implementing Scrum About halfway through the first sprint, communication issues develop Some project team members are not in sync with other team members What is the cause for this communication gap?
- AThe project sprint board has not been updated
- BDaily standup meetings were not held or enforced
- CThe project status dashboard has not been updated
- DThe communications management plan has not been developed
65During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?- ADiscuss approval of the change request in the next project meeting
- BPerform a risk assessment on the required change request.
- CEvaluate the change request against the project scope statement
- DAsk the sponsor for more funds to cover the change request
66A project manager is in rapid development mode on a joint application development module The company wants delivery to occur in two weeks The module needs to be integrated with other modules on a similar timeline, but release management has a three-week backlog What should the project manager do?
- APush the team to deliver more so that the modules are developed and rolled out according to management's request
- BSpeak to the stakeholders to resolve the bottleneck and see how the entire process can be streamlined
- CHave the team work toward the tighter deadline so that integration will be easier.
- DSpeak to the team and slow the current pace to ensure the team is in alignment with the release date
67A project manager receives a request for proposal (RFP) from a client. The client is very clear about the requirements. A requirements analysis must be done in the first month of the project, and the client wants to see a demo of the work completed every two weeks.
What project approach should the project manager use?- AIterative for the requirements analysis and delivery phases of the project
- BAgile for all of the phases of the project, including the requirements analysis and delivery
- CPredictive for the requirements analysis and agile for delivery of the project
- DPredictive for the requirements analysis and delivery phases of the project
68A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?- A(A). Ask senior management to communicate with these departments.
- B(B). Hire a project management consultant to help resolve the issue
- C(C). Convince senior management to introduce rewards to resisting departments.
- D(D). Understand the user concerns and revisit the stakeholder engagement plan
69A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch On what should the project manager focus?
- AEnsuring that the team is also focused on the overall change management plan
- BDetermining and aligning performance indicators that will help in assessing successful delivery
- CPlanning for regular project updates to cover the status of critical deliverables
- DEnsuring that the scope management plan is in place to cover all related objectives
70A highly skilled team resource received a job offer and is leaving the project soon What should the project manager do to maintain project performance while a new team member is being onboarded?
- ALog a risk in the risk register and work with the new team member to mitigate it
- BMotivate the new team member to perform.
- CShare project documents the new team member.
- DOffer cross-training and mentoring to the new team member
71During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager react to ensure the project remains successful?
- AFocus the discussion on recovery and ways to get back on track.
- BAct in a way to highlight the criticality of the situation.
- CPunish the team member for providing negative data that will affect the team's morale.
- DThank the team member for raising this issue, log it, and move on to the next topic.
72Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company's competitive advantage. What should the project manager do?
- AReject all requested changes and bypass the company's change control process.
- BEncourage the project team to add premium features to impress the client.
- CStart the process to include the new features of the product on the next iteration.
- DAllow all requested changes and bypass the company's change control process.
73A project manager is assigned to an agile project that has an aggressive time line and a fixed budget.
Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?- APrioritize which backlog activities should be kept.
- BWork on the backlog activities with fewer story points
- CAsk for more resources to clear the backlog activities.
- DAssign an owner for each backlog activity and track progress.
74A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
- ARisk register
- BProject schedule
- CChange request
- DIssue log
75In a hybrid project, the customer decided on a major change for the project design. This change was approved and the impact on schedule and budget is known The software team leader, who is supposed to develop the software, refuses to commit to delivery dates claiming that they work using an agile approach and cannot commit to a final delivery date The hardware team depends on this software to develop their part of the product What should the project manager do?
- AAdd this risk to the risk register and monitor it according to the risk management plan
- BEscalate this to higher management and ask for help to resolve the issue.
- CImpose the delivery dates on the software team leader and notify the functional manager about the situation
- DAsk the software team leader to use a predictive approach and commit to a delivery date
76A customer interacts directly with a Scrum team and continually requests changes in priorities. This causes confusion among the team members and they complain to the project manager.
What should the project manager do?- AAdvise the customer to discuss changes with the product owner.
- BDocument this issue in the sprint backlog for discussion at a team meeting.
- CAsk the customer to submit a change request to the project sponsor.
- DEncourage the team to clarify the requests with the customer.
77A project manager is m the middle of a project when one of the key project team members needs to take an unexpected and prolonged leave of absence The project is ahead of schedule and running under budget Which two actions should the project manager take initially to resolve this problem? (Choose two)
- ACheck the risk register for a prepared response to a resource being suddenly unavailable.
- BCheck if the team member's activities are sufficiently documented to facilitate handover
- CCheck the project's responsibility assignment matrix (RAM) to determine which activities will be affected
- DReassign responsibilities across the remaining members using the available float for training.
- EObtain the project sponsors support to replace the team member on leave
78During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?- APerform a root cause analysis (RCA) to find out why the status of projects is deteriorating so fast.
- BExplore reporting the earned value (EV) key performance indicators (KPIs) using agile progress as an input.
- CAsk the project managers to report on their projects using a Kanban board format.
- DRequest the program managers to be more accurate when presenting status reports.
79A global program is being kicked off, and various distributed teams are Involved in delivering the initiative.
Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings- APhone conversations
- BEncrypted emails
- CVideoconterencing
- DChat conversations
80A company is implementing a growth strategy by constructing a new production facility, which will soon move into the operation phase. Although a governance policy was already in place, the company must comply with new financial regulations that have been recently implemented. Compliance with the regulations will cause a major change in project scope.
How should the project manager respond to this requirement?- A(A). Proceed with the existing company governance policy.
- B(B). Perform an analysis to assess the impact on the project.
- C(C). Directly comply with the financial regulatiors.
- D(D). Escalate the issue to upper management and let them decide.
81A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders What document should the project manager use to communicate these requests?
- ARisk log
- BChange log
- CBacklog
- DIssue log
82A project manager is tasked with managing a customer relationship management (CRM) implementation project. The project charter is approved, and the project is now in the planning phase. The project manager meets with the stakeholders several times to gather the initial requirements. However, each time they meet, the stakeholders provide additional information that is different from what they provided earlier. The stakeholders are becoming frustrated, and the sponsor is now unresponsive.
What should the project manager have done to avoid this situation?- AInitiated requirements planning to analyze, document, and manage requirements
- BApplied requirements elicitation to involve engaging stakeholders consistently in the requirements process
- CImplemented the change request process to harness change to the stakeholders' advantage
- DUsed progressive elaboration to enhance the scope management plan with additional details
83An organization is adopting an agile mindset. On the first agile project, the project manager faced an issue because the team was unable to make decisions on time.
What should the project manager do to address the problem?- ADefine clear guidelines on how decisions should be made under the new organizational policy and reinforce them with the team on every occasion.
- BInvite senior leadership to a team-building workshop and restate the importance of accountability and leadership under the new company direction.
- CAssess the situation to understand how the organization's culture impacts the decisionmaking process, and coach the team toward a new model.
- DAdopt an autocratic leadership style and dictate all decisions in order to speed up the team's velocity.
84A complex project is in the execution phase. A key stakeholder who is new to the project has not been approving project deliverables, which could impact the overall progress.
What should the project manager do next?- ACapture this in the issue log and escalate it to the project sponsor.
- BMeet with the stakeholder to understand what is causing the delays.
- CFacilitate a brainstorming session to find potential workarounds.
- DDiscuss the need to influence this stakeholder with the sponsor.
85Drag the organizational characteristics on the left to the correct scenario on the right

- A

- BĐáp án ở trong ảnh :))
- A
86The project schedule is falling behind and the project manager observes that the project team seems to be spending the majority of their time writing documentation instead of performing project tasks What should the project manager do to help ensure that the team focuses on project tasks?
- AAssign a team member to handle the documentation activities.
- BCoach the project team to complete the project documentation activities
- CReview and adapt the appropriate project artifacts.
- DSave all documentation activities until tire end of the project
87A project manager is instructed by the project sponsor to draft the project charter. The project sponsor asks the project manager to involve a particular stakeholder m order to provide necessary resources However, the stakeholder is refusing to get involved because the stakeholder thinks mat there is no benefit m using the project deliverable What should the project manager do to resolve this?
- AMeet with the stakeholder to discuss the impact of the deliverable
- BConsider the stakeholder as a risk and evaluate possible solutions with the project team
- CImprove communication with the stakeholder to obtain their assistance in the future
- DEscalate to the project sponsor due to the political nature of the issue
88During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?
- AStakeholders are satisfied with the current status.
- BThe project is under budget and on schedule
- CThe project is aligned with the project charter
- DThe protect is aligned with the benefits management plan
89During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?- ASolve the issue for the team member.
- BPerform a brainstorming session to address the issue and add the solution to the sprint.
- CEscalate the issue to the software vendor for technical resolution
- DCoach the team to come up with their own solution and add it to the next sprint
90Two team members are arguing about which technology they should use when implementing iteration tasks.
The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.
What should the project manager do to resolve this issue and help the team move on to the next iteration?- APostpone the selection of the technology used until more information is gathered
- BSuggest their own approach to solve the issue and ask the team to follow it
- CCall for an open dialogue which the team will arrive at through consensus
- DAllow the team to decide since the teams should be autonomous
91Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?- AEnsured that communications were sent to all stakeholders when requirements change
- BEnsured procurement contracts were able be canceled when situations like this arise
- CEnsured project requirements were validated and communicated with the procurement team
- DEnsured changing stakeholder needs and requests were properly monitored
92After reviewing the project management plan with key stakeholders, the project manager was told that an
18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?- APlan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.
- BReview the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline
- CSeek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule
- DGo over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline
93An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story What should the agile leader do 1?
- AEmphasize to the team that each member is responsible for their story but the team is collectively responsible for finishing the sprint
- BAsk the team to address this at the next sprint planning instead of at the retrospective
- CSuggest that the team assign stones at the beginning of the sprint based on each person's strengths to maximize performance
- DWork with the product owner to remove the story from the sprint because the points cannot be splits
94A project manager is responsible for building a bridge The high-level elements of the project are handled using a predictive approach The software responsible for retracting the bridge has been developed based on agile principles During software development, the workflow is often interrupted by various delays or impediments due to lack of information How should the project manager handle this situation?
- AApply lean manufacturing to limit the team's work
- BIncrease retrospectives to deliver results fast
- CMake work visible using kanban boards.
- DIncorporate small batches of work into the project
95A project manager is starting a new project, and the project team is located in different countries. The team was going to use a specific tool to hold virtual meetings.
However, that tool is not available in one team member's country. How should the project manager deal with this situation?- AContact the project sponsor to have the team member removed from the project.
- BAsk the team member to move to another location where the tool is available.
- CStart the project and use email to communicate with the team member until the tool is available.
- DInvestigate alternative tools for virtual meetings that are available to all team members.
96A project is comprised of team members who are not engaged and committed to project success. What should the project manager do to address this situation?
- AAccept the situation knowing there is schedule slack available to release on an incremental basis when necessary.
- BCall each team member to gain their perspective on the problem, then bring the whole team together to discuss a solution.
- CSend each team member a direct email indicating that disciplinary action is likely if they do not change their attitude.
- DContact the project sponsor to request approval to release the current team and hire replacement personnel.
97A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?
- ASubmit a change request to the change control board (CCB) in order to reflect the new requirements and longer timeline of the project
- BRefer to the resource management plan to find out if more business analysts may be assigned to process the requirements changes
- CPoint out to the project team and the customer that all information concerning the timeline of the project should be communicated by the project manager.
- DExplain that distribution of important news can only be done using traceable communication methods
98A global company hired a project manager for a new implementation at all of its sites After reviewing the business case and project charter, the project manager notes that the project team has different locations and regions to consider.
What should the project manager do to address this situation?- AInform the steering committee of the situation and request additional resources.
- BCoordinate virtual and face-to-face meetings at each site to improve communication
- CCoordinate virtual meetings to assess the project team's communication needs
- DInform the project sponsor of this situation and request cultural orientation training.
99A project manager leads a software development project in a hybrid environment. During project planning, the project manager identified a risk where a technical resource for a critical path item may not be available when needed. One week before the resource is needed, the technical engineer had a personal emergency and had to take a leave.
What should the project manager do next?- AUpdate the lessons learned report and the risk log to reflect that this risk has materialized.
- BRevise the project management plan and move the task to a time when the technical resource will be available.
- CConsult the risk register for an appropriate planned risk response and implement.
- DReview the business requirement with stakeholders and exclude the task assigned to the technical resource.
100In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.
What should the project manager do next1?- AUpdate the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder
- BInform the project sponsor that there are stakeholders who are not included in the communications management plan
- CInform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan
- DAsk the stakeholder to get the project status report from another stakeholder listed in the communications management plan.
Information
- Description
- Công nghệ số Quiz on PMP exam 1, created by Lê Hiếu on 12/07/2022.
- Author
- Lê Hiếu
- Language
- English
- Views
- 98
- Tags
- Rating
- No ratings yet Rate this quiz