  1. 1You are planning a storage device migration in a data center. During this phase of the project, who should be controlling the project?
    1. AProject Manager
    2. BSME’s
    3. CSponsor
    4. DManagement
  2. 2Your most recent quality control chart shows that all data points measured fall within the control range. However, there is a group of 8 consecutive data points sitting above the mean. What do you do?
    1. ADo nothing. The control processes are working as designed.
    2. BChange the standard deviation by +/- 1.
    3. CTell the stakeholders there is a possible quality control issue and you are investigating the cause.
    4. DUse project contingency funds to pay for the rework of these items
  3. 3In a multi-phase project, the procurement team decided to close the procurements applicable to a particular phase of the project. What happens to unresolved claims?
    1. AUnresolved claims are usually resolved at the end of all phases of the project.
    2. BUnresolved claims are also closed when the procurements for that phase are closed.
    3. CUnresolved claims remain open for a period of 1 year from closure of procurements.
    4. DUnresolved claims may still be subject to litigation after closure
  4. 4The product design your project team developed was very well received by the customer. There were two key contributors to this design. The customer calls you to tell you how pleased he is with the design. What do you tell him?
    1. AAsk to negotiate a bonus payment.
    2. BThank the customer.
    3. CThank him on behalf of the team and call out the contributions made by two of the team
      members.
    4. DTell the customer that you worked very hard on the design and that you are happy he is pleased.
  5. 5You are managing a project for a customer that has just gone bankrupt and is subject to liquidation proceedings. There are several outstanding invoices that this customer has not paid to your company. What should you do now?
    1. AGo into alternate dispute resolution
    2. BDo nothing.
    3. CContact the appropriate management at your company for advice how to proceed.
    4. DSend the invoices to the bankruptcy attorneys.
  6. 6Peter works as a project manager for GOODSTEEL, a steel melting shop. He was assigned by his Executive Project Manager to study and prepare a report on the defects that eroded the blast furnace lining which has caused a drastic decline in production. Since this report will be used by the management to control the process and material quality, Peter performed a careful study and identified two major factors out of many factors related to refractories that caused majority of the lining problems. Which of the following statements BEST illustrate the technique Peter must have used in this scenario?
    1. AA Pareto chart indicates that the vital few sources of the problem.
    2. BA cause and effect diagram indicates how various causes show the history and variation of defects
    3. CA Pareto chart identifies the possible relationship between changes observed in two independent variables
    4. DA cause and effect diagram indicates how various factors or causes can be linked to potential problems
  7. 7The Identify Stakeholders process is an initiating process. At this stage, which of the following organizational process assets is the most crucial input to this process?
    1. AChange control procedures
    2. BLessons learned from previous projects.
    3. CFinancial control procedures
    4. DRisk control procedures
  8. 8You have been chosen by a program management office (PMO) to write a purchase order for your expertise in business writing. You have learned that the PMO has already selected a seller for a software product and would like to award the procurement contract to the selected seller as a purchase order which you must prepare. In this scenario, the PMO is administering:
    1. AThe close procurements process
    2. BThe control procurements process
    3. CThe plan procurement management process
    4. DThe conduct procurements process
  9. 9The morale of the team members of a project is very low. The team members feel that they were not given opportunities to participate in the organizational team development activities due to over allocations to project tasks, and hence they missed opportunities to grow. Which of the following is a primary factor for this situation?
    1. AUse of zero-sum rewards in the project
    2. BA poorly defined resource calendar
    3. CToo many senior team members
    4. DPoor interpersonal skills in the team
  10. 10Calculation of late finish dates and late start dates for the uncompleted portion of the project is called .
    1. ASchedule compression
    2. BAn arrow diagram
    3. CA backward pass
    4. DA forward pass

Information

Description
Fourth 20 Q
Language
English
Views
341
History
Created on 18 Dec 2017 · updated on 19 Dec 2017
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?