1The most important aspects of project execution include?
- AMonitoring Fees and Time
- BControlling and responding to changes in the scope of work
- CMonitoring the construction budget
- DDocumenting the design and construction phases
- EAdhering to the requirements of the authorities having jurisdiction
- FMaintaining overall quality control of the project
2Which of the following correctly apply to Monitoring Fees and Time as an important aspect of project execution?
- AEnsuring that the job's planned budget, schedule, and tasks are being met in a timely and satisfactory manner
- BThe Workplan is the primary tool for monitoring fees and time
- CComparing weekly time sheet data with the original fee projections can show how far over or under budget a project is at a given phase of work
3Which of the following is the primary tool for monitoring fees and time?
- AThe Workplan
- BGantt / Bar Chart
- CCritical Path Chart
- DConstruction Schedule
- EProject Monitoring Chart
4Which of the following is used for comparing weekly time sheet data with the original fee projections?
- AProject Monitoring Chart
- BWorkplan
- CGantt Chart
- DCritical Path Chart
5Which chart shows how far over or under budget a project is at a given phase of work?
- AProject Monitoring Chart
- BWorkplan
- CGantt Chart
- DCritical Path Chart
6Depending on the size and complexity of the project, the project manager can monitor fees and work completed every:
- Aweek
- Btwo weeks
- Cmonth
- Dday
- Ehour
- F2 months
7If according to the project monitoring chart, the actual fees and time expended exceed the estimate, or if the percentage of work completed dips below the estimate, what is the first action a project manager should take to correct it?
- AIdentify the problem
- BInform the principals or firm leadership
- CInform the owner and negotiate extended time and fees
- DBill the fees and time in excess to overhead
8Which of the following is the main source of information for the PM to accurately monitor the fees and time of a project and to provide the basis for billing and give the ongoing data needed for project monitoring?
- ATimesheets that are filled out by each staff member
- BExpenses and consultant fees
- CProject Reviews
- DGantt Chart
- EWorkplan
9Which of the following apply to timesheets?
- AAre important to the success of any architectural office
- BThey provide the basis for billing and give the ongoing data needed for project monitoring
- CProvide important historical information that can be used to accurately estimate fees for new projects
10Which of the following project management activities would most likely ensure that construction documents are completed on schedule and within budget?
- ADocumenting all meetings and correspondence
- BEstablishing time and fee projections
- CMonitoring timesheets
- DSetting Milestones
11Which of the following are potential causes of a project going over budget or work progress lagging?
- AThe wrong people are working on the project
- BThe people doing the work are not keeping pace
- CThe people doing the work are spending too much time on the project
- DTime sheets are not being filled out properly
- EChanges in the scope of work such as "Scope Creep"
12Which of the following correctly apply to Scope Creep?
- AMay cause a project to go over budgeted fees and time
- BThe client or architect makes uncontrolled changes to the original list of services set forth in the owner-architect agreement
- CMay be when a client asks for the development of a new floor plan after the first one was already approved
- DMay be when a client asks the architect to review another product
- EIf a design results in a greater cost for construction than the original estimate and the architect must adjust the design to match the budget
- FIs commonly caused by project perfection syndrome
- GA given task may be completed successfully, but the architect wants to try just one more design scheme or develop just one more refinement to some detail, however the minor improvement that might be found does not justify the disproportionately added time and fee
- HMay be caused by employees are not fully aware of the scope of work. (ie staff members may spend time on detailed designs for interior finishes, not realizing that these are not included in the contract
- ICan be prevented by rigorously and continuously comparing the work being done with what was agreed to the contract
- JIt is imperative that the pm develops a detailed work plan before the owner-architect agreement is signed, so that the full extent of the job is known and shared with all the team members
13The project team must be aware of the scope so that if a client makes requests for work that is additional to the scope of work agreed to in the contract, the team will know to bring these additional work request to the project manager for authorization to proceed with those tasks.
- ATrue
- BFalse
14Which of the following apply to the architect's responsibility of making sure that the design conforms to the original project budget?
- ACan be difficult in the early stages of schematic design if the original cost estimate has been based on the cost per square foot for a similar building type
- BAs the project design is developed and refined, new cost estimates should be developed
- CCost projections should be compared against the original budget, and modifications to the design are made as needed
- DDuring design development and the early stages of construction documentation, the parameter method of budgeting can be used to adjust decisions about materials, products, and systems in order to meet the owner's budget
- EOne advantage of project delivery with a construction manager, design-build, or integrated project delivery method is that the architect can get accurate cost information throughout the design process and work with the constructor to maintain the project budget
- FAny changes in the project scope may increase construction cost, affecting time and fees. If a decisions made by the client changes the scope of the project, the architect must immediately inform the client in writing of how the change may affect costs - both construction costs and additional design fees. The client must give written approval for any scope changes
- GThe architect must request additional fees for any additional services need to adjust the design to meet the project budget
15During which phases of a project can the parameter method of budgeting be used to adjust decisions about materials, products, and systems into order to meet the owner's budget?
- ADesign Development
- BEarly stages of construction document production
- CSchematic Design
- DProgramming
16With which of the following can the architect get accurate cost information throughout the design process and work with the constructor to maintain the project budget?
- ADesign-Bid-Build
- BFast-Track
- CMultiple Prime
- DProject Delivery with a Construction Manager
- EDesign-Build
- FIntegrated Project Delivery Method
17Which of the following correctly apply to changes in the project scope?
- AMay increase construction cost, affecting time and fees
- BIf a decision made by the client changes the scope of the project, the architect must immediately inform the client in writing of how the change may affect costs
- CBoth construction cost and additional design fees may be increased
- DThe client must give written approval for any scope changes
- EThe owner is required to provide additional fees even if the architect's design has to be adjusted due to the design being over the owner's budget
18All work done on a project must be documented because:
- AIt lets the designer look back at the project's development
- BProvides a record in case disagreement arise
- CServes as a project history that the firm may use for planning future jobs
- DIs a vital part of project communication
19Most design firms use standard forms or project management software for common documents such as:
- ATransmittals
- BJob observation reports
- CTime Sheets
- DMeeting Notes
- ESpoken Communication
- FPhone conferencing
20Which of the following correctly apply to Quality Control?
- AIs an organized set of procedures, systems, and tools established by an office
- BAids in meeting the expectations of the client
- CMaintains a high level of professional service
- DReduces risk and liability
- EQuality Management
- FQuality Planning
- GQuality Assurance
- HQuality Guarantee and Repair
- IDetermining what the client expects in regards to design, cost, schedule, and other aspects of the project and then meeting those expectations
21Which of the following are the 2 main aspects to quality control?
- AThat which is normally expected of an architect (such as designing, detailing, and specifying)
- BThat which is defined by the client (such as obtaining functioning building at the lowest possible cost and on schedule)
- CThat which is defined by the community (expectations of the public)
- DThat which is defined by design competitions (awards and recognition)
22Because meeting the needs and expectations of the client is an integral component of quality control, these needs and expectations must be clearly defined during which project phase?
- AProgramming
- BConceptualization
- CVisualization
- DSchematic Design
23Which of the following are the 2 methods of achieving quality for both client goals and professional services?
- AProcess
- BChecking
- CProgramming
- DVisioning
24Which of the following correctly apply to "Process" as a method of achieving quality for both client goals and professional services?
- AMaking sure that tasks are performed correctly the first time so that there is no need to redo them later
- BTeam member's efforts are carefully supervised, and the work of individuals is coordinated
- CAn office may establish step by step procedures and checklists for completing drawings which are then used by everyone in the office on all projects to make sure that the drawing contains the necessary information and that various key elements are drawn correctly
- DMaking sure a finished product is correct before it is deliver to the end user
25Which of the following correctly apply to "Checking" as a method of achieving quality for both client goals and professional services?
- AMaking sure a finished product is correct before it is delivered to the end user
- BReviewing drawings before they are released to the owner for review or to the contractor for bidding or construction for example
- CRedlining drawings before they are released to the owner for review or to the contractor for bidding or construction for example
- DCorrecting drawings before they are released to the owner for review or to the contractor for bidding or construction for example
- EMaking sure that tasks are performed correctly the first time so that there is no need to redo them later
26What are the basic goals of a quality control program? (Choose the four that apply)
- AMeeting the community's expectations
- BMeeting the client's expectations
- CProviding the standard of care for professional practice
- DReducing risk and liability
- EDesigning an award winning project
- FUsing the best employees for the project
27Which of the following are guidelines that can be used to establish a quality control program?
- ATop management must support and encourage the program
- BGive one person or a small committee the responsibility to guide the daily efforts of the quality control program
- CInvolve everyone in the office; all employees should contribute their thought about problem areas and how procedures can be modified to make improvements
- DApply a quality control program without adjustments or perspectives from employees - reinforce this as a mandatory requirement with periodic audits
- Ereview past problem areas - those that cause the firm the greatest difficulties or that have the most potential to harm the firm should be corrected first
- FSet priorities and schedule for action based on what the firm's particular problem areas are
- GMust be maintained and used continually - over time eliminate what doesn't work and replace it with new techniques
28Which of the following are Quality Control Techniques?
- AProgramming
- BChecklists
- CProcess-Based Systems
- DStaffing
- EQuality Management Meetings
- FQuality Circles
- GCorporate Knowledge
- HProject Documentation
29Which of the following are related to Programming as a technique for Quality Control?
- AThe architect must have a written record defining the client's goals
- BThe architect must have a written record defining the client's needs
- CThe architect must have a written record defining the client's expectations
- DIs the document against which the architect can direct the project and judge whether or not it is achieving the level of quality expected by the client
- EIs a document provided by the architect
30Which of the following correctly apply to checklists as a technique for Quality Control?
- AA list of things that need to be considered or accomplished in order to complete a particular task
- BMost commonly a building code checklist
- CUseful for achieving consistency and quality in tasks that must be done on every project but that are not always done by the same people
- DUseful in embedding corporate memory into office documentation, for example if a mistake is made on a project, one or more items can be added to the relevant checklist to avoid the problem on future projects
- EFor offices that specialize in certain building types, these can address the unique needs of those buildings
- FSpecific checklists can be attached to standard details for technical construction reminders
- GServe as a record of work performed
- HCan be obtained from various sources such as practice management books and AIA Document D200, Project Checklist (misc documents)
- IAre typically firm specific and are based on their own particular needs and traits, including size of staff and projects, project types, experience of staff and projects, project delivery methods used, and any special problems historically encountered
- JRFIs from contractors on previous projects are good source of useful items to add
31Most firms develop their own checklists based on their own particular needs and traits including:
- ASize of Staff and Projects
- BProject Types
- CExperience of Staff and Projects
- DProject Delivery Methods Used
- EAny special problems historically encountered
- FServices provided
32Which of the following correctly apply to Process-Based Systems as a technique for Quality Control?
- AAutomates a procedure so that a task can be performed accurately and consistently with little or no human intervention
- BProject management or financial management software can present in a consistent format the precise information needed to develop a cost estimate or project proposal and to monitor the progress of the work
- CBuilding information software can accurately detect clashes between structure, building elements, and HVAC systems
33Which of the following are the parties that should participate in Quality Management Meetings as a technique for Quality Control?
- AThe Project Manager
- BDesigners
- COffice Principals
- DClient
- EConstruction Manager
34Which of the following correctly apply to Quality Management Meetings as a technique for Quality Control?
- AAt regular intervals during a project, the project manager, designers, and office principals should hold meetings to review the progress of the project
- BThe group can determine whether the original problems are being solved
- CThe work in progress can also be reviewed to see wether it is technically correct
- DThe group can determine whether the job is proceeding according to the client's and design firm's expectations
- EThe work in progress can be reviewed to see whether it adheres to all codes and regulations
- FThe work in progress can also be reviewed to see whether it is being properly documented
35Which of the following correctly apply to Staffing as a technique for Quality Control?
- AThe quality of any endeavor depends on the people engaged in it
- BThe knowledge, skill, experience, and diligence of the staff is important for quality control
- CAny number of checklists, meetings, computers, and standard details, no matter how well prepared, will be of little use if the people involved don't apply them correctly
- DThe best professional and support staff possible should be recruited and hired
- EExperience architects, graduates, and interns who show promise of developing into good architects and who can bring fresh ideas and new knowledge to the firm
- FA good in-house mentoring and training program is important and the firm should provide all employees with training, and continuing education outside the firm should be encouraged
36Which of the following correctly apply to "Quality Circles"?
- AIs a small group of employees who meet regularly to identify, analyze, and solve problems related to their particular sphere of work and come from the same work group so they can all focus on their particular problems
- BIncludes representatives from major departments in the firm as well as from top management
- CEmployees often know better than management what their immediate problems are and how they might be solved
- DIncrease motivation, improved communication, teamwork, more involvement by employees, and higher productivity
- EHas a flexible structure and is based on the company's needs, members' schedules, and circumstances
- F6-10 particpants
- GIs led by a facilitator trained in quality control techniques
- HMembership is voluntary
- IIs overseen by a Steering Committee
- JMeets once a week
37Which of the following are benefits of Quality Circles?
- AImproved Communication
- BIncreased Motivation
- CTeamwork
- DMore involvement by employees
- EHigher Productivity
- FLower turnover rate
38Once a quality circle has been set up, it should follow a consistent pattern in dealing with problems and quality control issues. What is the first step of the process?
- AProblem areas or specific projects should be identified (the ideas may come rom anywhere: circle members, management, staff members, or others)
- BThe ideas or problems are discussed and defined so that the circle has something definite to work on
- CThe problem is analyzed, alternate solutions are discussed, and a solution is developed
- DThe problem and solution is presented to management and the steering committee, if there is one
39Which of the following are guidelines for Quality Circles?
- AProvide training in quality control / circle techniques in management training programs and private management consulting firms which can provide ongoing support and advice
- BThe concept and process must have support from top management, including a commitment to seriously consider suggestions made by the quality circles. In larger firms, middle management must also support the idea
- CThe quality circles must be ongoing activities. They cannot run for a few months or a year and then be forgotten
- DQuality circles should be kept small. For larger firms or firms with several service areas, more than one circle may be established
- EAlthough Quality circles can work with a firm of any size, they are often more valuable for large firms, where communication between management and staff may be more difficult
- FA twenty to thirty person firm could probably benefit from a single quality circle
- GQuality circles should be considered a means to help employees develop while generally improving the quality of the work output
40Which of the following correctly apply to Corporate Knowledge?
- AIs the documentation of information that an architectural firm has gained through the work it has done and that can be applied to new projects
- BThe knowledge of experienced people in the firm and a means of accumulating such knowledge in a fixed, tangible form so that it can be shared with present and future employees
- CCan be documented through Checklists
- DCan be documented through Standard Details
- ECan be documented through Master Specifications
- FIn-house computer databases
- GPost-occupancy evaluations
- HProject procedure manuals
- IHand-written notes
41Which of the following correctly apply to Standard Details?
- AIs a form of documentation of Corporate Knowledge
- BRecord information for future project use
- CCan be used to streamline the production of future construction documents
- DAccompanying notes can help less experienced staff understand the proper use of the detail
- EAccompanying notes can document what is most important
- FAccompanying notes can document how details may be modified for certain uses
- GAccompanying notes can document applicable industry standards and reference sources
- HIs a form of checklist as a means of documentation of corporate knowledge
42Correctly Label the Standard Details of a Parapet

- Alap and seal roofing flashing
- BSealant, if required
- CExterior Cladding
- DMetal Stud
- ESheathing
- FRoof Insulation
- GCover Board
- HTPO Roofing
- ISeal with lap edge sealant
- JMetal bar anchor fastened
- KFlashing Membrane
- LPrime parapet as required
- M3" Minimum
- N3" Maximum
- OMetal coping with drips
- P8" Minimum
- Q8" Maximum
- RVerify maximum with mfg.
43Which of the following correctly apply to project documentation for quality control?
- AIs needed for administration of the project
- BAids in communication
- CServices as an archive of information that can be used on future jobs
- DProvides a record if disputes arise during the project or in arbitration or litigation after the project
44Which of the following are the 2 categories of project documentation that an architectural firm should maintain?
- AConstruction Documents (drawings and specifications)
- BEverything else related to the project (contracts, change orders, shop drawing logs, etc)
- CSchematic Design
- DDesign Development
45At the end of a job, all documentation should be:
- AConsolidated into a project file and retained for an amount of time required by records retention guidelines
- BConsolidated into a project file and retained indefinitely
- CConsolidated into a project file and retained for at least 10 years
46Which of the following correctly apply to Project Files?
- AShould be a record of how the entire job progressed from initial marketing to project closeout and follow-up
- BShould document the sequence of events of a project, including the what, who, when, how, and why of all actions
- CEnsures that the design solution meets the client's objectives
- DReduce risk and liability and defend the architectural office against claims and legal action
- EThe firm should establish a standard office protocol for accumulating, preparing, and distributing notes, minutes, and other information, and must keep adequate backup in case the original source is lost
47Which of the following are some of the most important types of project records to maintain for the General Administration of the Project using a standard Design-Bid-Build method of project delivery?
- AMarketing information and proposals, including all communications with the prospective client before the contract is signed
- BContact information for the client and client's representatives, including billing information and all records of communications with the client after the contract is signed
- CContracts and agreements and documents related to fee negotiations and agreements, including scope of services
- DDocuments related to design and construction schedules, including the client's preliminary schedule, approved schedules, and any changes
- EDocuments related to construction budgets, including the client's preliminary budget, approved budget, and any changes during the course of the project
- FFee and staffing allocations
- GInvoices, statements, and back up documents related to client billing and records of accounts receivable
- HRecords of expenses billed or assigned to the project, including expense invoices and consultant's billing
- IOther account records pertaining the project
- JAll communications between the design office and other parties concerning the project, including correspondence, meeting notes, emails, text messages, and telephone logs
48Which of the following are some of the most important types of project records to maintain for Programming using a standard Design-Bid-Build method of project delivery?
- AComplete program requirements, including functional groupings, occupants, individual space requirements, furniture and equipment needs and growth projections
- BStatement of the client's goals and objectives as well as sustainability goals and requirements
- CDocumentation of existing conditions, if the project is an addition or renovation
- DWritten client approval of the program
- ERevised project budget, if changed from the agreement
- FSoil test information and Survey information, including request for survey, communications with the surveyor, and billing information
- GBuilding code checklist and other regulatory requirements
- HAll communications between the design office and the parties concerning the project, including correspondence, meeting notes, emails, text messages, and telephone logs
49Which of the following are program requirements?
- AFunctional Groupings (adjacencies)
- BOccupants
- CIndividual Space requirements
- DFurniture and equipment needs
- EGrowth Projections
- FStatement of the client's goals and objectives
50Which of the following are some of the most important types of project records to maintain for Schematic Design using a standard Design-Bid-Build method of project delivery?
- ASketches, models and other drawings and computer files used to develop schematic design
- BFinal schematic design presentation, including budget and schedule
- CClient's written approval of schematic design and authorization to proceed
- DAll communications between the design office and other parties concerning the project including correspondence
- EMeeting notes
- FEmails
- GText Messages
- HTelephone Logs
51Which of the following are some of the most important types of project records to maintain for Design Development using a standard Design-Bid-Build method of project delivery?
- ASketches models and other drawings and computer files used to complete design development
- BFinal design development presentation
- CApprovals of applicable regularity agencies
- DRecords of all changes, who made them, and why
- EFinal design development presentation, including budget and schedule
- FClient's written approval of design development and authorization to proceed
- GAll communications between the design office and other parties concerning the project including correspondence, meeting notes, emails, text messages, and telephone logs
52Which of the following are some of the most important types of project records to maintain for Construction Documentation using a standard Design-Bid-Build method of project delivery?
- ASupporting information for developing the construction drawings and specifications
- BRecords of materials and product investigation and selection
- CWritten approval of the documents by the client
- DRecords related to advertising for bids or proposals
- EAll communications between the design office and other parties concerning the project, including correspondence , meeting notes, emails, text messages, and telephone logs
53Which of the following are some of the most important types of project records to maintain for Bidding and Negotiation using a standard Design-Bid-Build method of project delivery?
- ARecords of each prime bidder or negotiating contractor
- BRecord of issuance of contract documents
- CAddenda records, including requests for information and distribution log
- DBidding records, including submitted bids and bid summary log
- EPre-bid conference notes
- FAll communications between the design office and other parties concerning the project, including correspondence, meeting notes, emails, text messages, and telephone logs
54Which of the following are some of the most important types of project records to maintain for Construction Administration using a standard Design-Bid-Build method of project delivery?
- ARecord of all prime contractors, including record of receipt of bonds, certificates of insurance, dates of approval, and contract signed
- BReference copy of the contract between the owner and contractor
- CList of subcontractors with contact information
- DCopy of the contractor's approved schedule, Copy of payment schedules, schedule of values, and other cost-related documents
- ECopies of test reports and field reports, photographs and videos
- FRecords of issuance of all permits
- GShop drawings and shop drawing log, samples and sample submittal log
- HChange orders, including pricing requests, approved copies, and change order log
- IApplication and certificates for payment
- JAll communications between the design office and other parties concerning the project, including correspondence, meeting notes, emails, text messages, and telephone logs
55Which of the following are some of the most important types of project records to maintain for Project Closeout and Follow-Up using a standard Design-Bid-Build method of project delivery?
- APunch List and follow ups
- BCertificate of substantial completion
- CFinal certificate for payment
- DTesting and balancing reports (if not part of commissioning)
- ECommissioning reports
- FCopies of release of liens or dates of release of liens
- GCopies of guarantees, bonds, and operating instructions
- HCopies of record drawings
- IProject closeout form
- JConstruction cost summary
56Social media can be used for communicating project information or for project records.
- ATrue
- BFalse
57Which of the following correctly apply to Contemporaneous Documentation?
- AIs the recording of communications, decisions, and other actions that are not normally relegated to a standard form or whose occurrence cannot be predicted to take place at a given time or circumstance, such as within a regularly scheduled project meeting
- BShould record spoken communication (in person conversations and telephone calls)
- CShould record electronic correspondence (emails and text messages)
- DThese records may be tracked through use of a daily journal or notebook entries
- EIf electronic messages and documents are used there should be an office protocol for using the associated devices and safely archiving the records
- FMeeting notes from a regularly scheduled project meeting
58Which of the following are guidelines for documentation?
- ABe sure to communicate potential problems to the appropriate members of the team
- BAvoid assigning blame for a problem, whether to others or to oneself. Just give the facts and indicate that the problem must be further investigated
- CInclude the date of each communication, and make a note of the parties who are privy to it
- DIf using paper journals or notebooks, use a spiral-bound the. This will help establish that the notes were sequential and contemporaneous, and that no new pages were added at a later time
- EIf paper-based documentation is used, write in ink
- FWhen keeping the client informed of progress, as required by the contract, be consistent in how the information is communicated, the length and style of the message, and the amount of information given.
- GCommunicate through social media on an outlet where all correspondence is time stamped and backed up onto a cloud based server
59Which of the following correctly apply to Hearsay?
- AIs a written or oral statement that was made outside of the court, usually by another person other than the witness
- BIs normally not allowed as evidence in court
- CIs normally allowed as evidence in court
- DProject records can be considered hearsay evidence unless they are found to come under an exception allowed by the law, known as the business entry rule or the business records execution to the hearsay rule
- EProject records cannot be considered hearsay because they are found under an exception allowed by the law known as the business entry rule or the business records exception to the hearsay rule
60To quality under the exception, Business entry rule or the business records exception to the hearsay rule, to not be considered hearsay, project records must:
- AHave been made during the normal course of business
- BMust have been made at or shortly after the act, event or transaction being recorded
- CMust be the regular course of business for such a record to be made
- DIf the firm must communicate to the client in between regular communications (such as to report an urgent safety problem on the job site), the communication should make clear that the contract requires the firm to notify the client in a timely manner
61Which of them following is one of the main sources of claims of negligence?
- AProject Records
- BConstruction Documents
- CDesign Development
- DContract Documents
62It is important that the project manager be able to budget and monitor the progress of the construction documents so that there is not a rush to complete the project under less-than-ideal conditions.
- AConstruction documents are one of the main sources of claims of negligence
- BCDs are the most complex part of the project delivery process and preparing them requires a great deal of coordination among many people
- CCDs are typically completed when time and fees are running out, and less experience staff members are often assigned to complete them
63Which of the following are guidelines that can be used as the foundation for proper construction document production?
- AA single source of control
- BIndustry Standards
- CProfessional Standards
- DCommunication and Coordination
- EWork Procedures
- FResearch
- GEvaluation and Feedback
- HOutsourcing
64Which of the following correctly apply to a Single Source of Control as guideline for construction documentation?
- AOne person should be in control of construction documentation production and coordination among the various members of the team: client, consultants, firm management, governmental agencies etc
- BThis person should be a competent project manager who maintains continuity throughout the entire project delivery process, from initial proposal to project follow-up
- COn large jobs, the project manager does not necessarily have to handle daily production issues (these can be handled by a job captain)
- DThe project manager should know and understand the complexities of construction documents and how they are produced
65Which of the following correctly apply to Industry Standards as a guideline for producing construction documents?
- Abe aware of accepted standards of practice and trade customs in the construction industry
- BStay current with standards of quality in the industry
- CEstablish a policy regarding the use of industry standards and under what circumstances it is appropriate to deviate from these standards
- DIf the firm wants a higher standard of workmanship than usual on a project, this needs to be clearly expressed in the drawings and specifications
66Which of the following correctly apply to Professional Standards as a guideline for construction documents production?
- AA design professional is expected to exercise the degree of skill, knowledge, and judgment that is normally exercised by other professionals in similar circumstances in similar communities - the standard of care is one of the basic legal concepts concerning liability and negligence
- BIf conduct fall below this standard of practice, the professional may be held liable for damages
- COne way to achieve this level of performance is to follow general accepted methods and procedures of practice
- DIncludes drawing standards and specification standards
- EThe architect can also use accepted details of trade associations
67Which of the following correctly apply to Communication and Coordination as a guideline for construction documents production?
- ALack of communication is the source of many problems and can result in needless time and effort that will be spent later correct the problems that result
- BA firm should set policies that encourage and facilitate communication among all members fo the project team
- CPolicies should include procedures for meetings and written communications
- DPolicies should include procedures for regular exchange of progress drawings, use of design checklists, and assigning to one person the responsibility for implementing these policies
- EIn most cases the project manager should be the person responsible for implementing policies of communication
- FUsing a shared building information model (BIM) can also facilitate this coordination
68Which of the following correctly apply to Work Procedures as a guideline for construction document production?
- AAll staff should use quality control checklists
- BQuality control checklists maintains consistent quality form job to job and minimizes the possibility of omissions
- CStandard details should also be used, as they not only save time and money in production jobs, but are also an excellent way to record the knowledge that the firm develops concerning how to build well
- DThese methods simply let designers spend more of their time concentrating on design rather than production
69Which of the following correctly apply to Research as a guideline for construction documents production?
- AEvery firm should make an ongoing commitment to research in all aspects of the practice
- BThis should include research into products, ways to improve specifications, design techniques, and other applicable topics
- CIn an increasing number of cases, design professionals have been held liable for incorrect product use, design solutions etc
- DGood research reduces the firm's risk of liability
70Which of the following correctly apply to Evaluation and Feedback as a guideline for construction document production?
- AEvery firm should learn from its successes and mistakes
- BA regular process of evaluation and feedback is integral to quality control and necessary for continuing improvement
- CThis the way to develop and strengthen corporate member, one of the most valuable sources of information a design offices has
71Before the construction documents phase can begin, there are two basic requirements:
- AFirst, the owner must approve the design development submission in writing as required by the agreement
- BSecond, the architect should settle all design decisions and select the materials needed, so that the drawings and specifications can be completed
- CSecond, the owner must approve the design development submission in writing as required by the agreement
- DFirst, the architect should settle all design decisions and select the materials needed, so that the drawings and specifications can be completed
72Leaving design decisions until the construction documents phase is a sure way to make mistakes and go over budget
- ATrue
- BFalse
73Before starting construction documents, which of the following tasks should be completed?
- AVerify that the design solution meets all program requirements
- BVerify that the design solutions meets all regulatory requirements that apply
- CObtain from the client all the information needed for inclusion in the project manual
- DThe architect should settle all design decisions and select the materials needed, so that the drawings and specifications can be completed
- EPrepare an outline of the scope of construction documents required
- FCheck whether the client has special requirements for the drawings of the project manual
- GUpdate the design development budget to reflect any changes or development of details (including mechanical and electrical)
- HDetermine what staffing is needed to complete the construction documents according to schedule
- IAllow enough time at the end of document production to check for errors and correct them, as well as for reproduction
74Which of the following correctly apply to, "Verify that the design solution meets all program requirements," prior to starting construction documents?
- ATo make this verification, use the checklists developed during programming
- BTo make this verification, use correspondence with the client
- CTo make this verification use the final programming report and other documentation as needed
75Which of the following correctly apply to, "Verify that the design solution meets all regulatory requirements that apply," prior to starting construction documents?
- AApplicable zoning and building code requirements
- BShould be checked during the design phases too, but last-minute changes often affect compliance
- CBe alter to changes, and reexamine the drawings with this in mind
- DIf preliminary approval from governing agencies is required, verify that this approval has been obtained in writing
76Which of the following correctly apply to, "Obtain from the client all the information needed for inclusion in the project manual," prior to starting construction documents?
- AIncludes the type of contract the client wants to use
- BIncludes the insurance and bonding requirements
- CIncludes modifications to the general and supplementary conditions of the contract
- DIncludes approved alternatives
- EIncludes items to be supplied by the owner and similar concerns
77Which of the following correctly apply to, "Prepare an online of the scope of construction documents required," prior to starting construction documents?
- AIncludes working drawing sheet mock-ups
- BIncludes detail lists
- CIncludes the numbering system for the drawings
- DIncludes a list of required technical sections of the project manual and other required documents of the project manual
- EA great deal of time, money, and confusion can be saved if this simple step is completed
78Which of the following correctly apply to, "Check drawings at 50% completion?"
- ASubmit these drawings to the client for review and approval
- BMake it clear to the client that this review is for checking the drawings against he original program requirements and the design development approval
- CMake it clear to the client that this is not a time for making changes
- DChanges made at this time are extra services and could require a time extension
79During production of construction documents, which of the following tasks should be completed?
- ACheck drawings at 50% completion
- BReview completed construction and bidding documents with the client
- CAllow enough time at the end of document production to check for errors and correct them, as well as for reproduction
80Which of the following correctly apply to, "Review completed construction and bidding documents with the client?"
- AObtain the client's written approval to proceed to the bidding or negotiation phase
- BIf there is signified variance from previous cost budgets, advise the client immediately
81Which of the following correctly apply to, "Update the design development budget to select any changes or development of details (including mechanical / electrical)?"
- AIf there is significant variance from previous cost budgets, advise the client immediately
- BReview with the client and obtain approval before proceeding with construction documents
- CProceed with construction documents to avoid construction delays
82Which of the following correctly apply to, "Determine what staffing is needed to complete the construction documents according to schedule?"
- AIt may be necessary to bring in staff from other departments or to use a subcontractor to provide drafting services
- BThis phase often requires more detailed scheduling that other phases so it may be necessary to expand the original schedule
- COutsource
83Which of the following correctly apply to Coordination during construction documents?
- AReview with the consultants any changes made during design development
- BSupply consultants with the information they need on desired specification items - this can include information about plumbing fixtures, light fixtures, air diffusers, sprinkler heads, switches, and so on - can also include performance requirements such as color and appearance
- CSupply consultants with a template for the desired specification format - include the number system, page layout, etc
- DTo avoid confusion as consultants to follow the architect's specifications
- EHold regular meetings with consultants - exchange progress drawings weekly or biweekly as needed
- FVerify that the working drawings comply with building code requirements - this includes details, specified materials, measurements, and other elements
- GProvide to each person working not the construction documents a copy of the code checklist that was completed during the programming or design phases
84When the construction documents are complete, they should be:
- AThroughly checked ideally by someone outside the firm such as a code consultant
- BAllow sufficient time for this external review
- Cchecked by someone within the firm who has the knowledge needed by who has not worked on the project
- DThis includes reviewing the consultant's drawings and specification sections to ensure proper coordination
85If the building project requires approval from planning agencies or other governmental bodies before detailed design can begin:
- AThe project manger is responsible for guiding the owner's project though the approval process
- BThe client is responsible for guiding the project though the approval process
- CThew work required to gain approval may include developing preliminary site plans
- DMay require land-use proposals
- EMay require sketching preliminary building designs
- FMay require meeting with governmental agencies and neighborhood groups or presenting before regulatory boards
- GThis work requires additional fees beyond the normal fee for building design so the architect must estimate the time and costs needed for the work and obtain the client's approval before proceeding
86If the building present unusual design challenges, it may require zoning variances or unusual building techniques or materials
- AThe architect will have to work with building officials or zoning regulations early in the pre-design phase to obtain their advice and approval for any deviation from zoning requirements
- BThe architect may have to find other means and methods of construction as allowed by building codes
- CIn some circumstances a code consultant may be needed to guide the project through the code approval process
- DIn this case a construction manager is required to work with building officials or zoning regulations early in the pre-design phase to obtain their advice and approval for any deviation from zoning requirements
87It is the project manager's responsibility to:
- AEnsure that as the design develops, it is continually checked against the requirements of the building code and any state and local regulations
- BThe pm may do this personally but more often building code checks are done by someone in the firm who is especially knowledgable in this area
- CIf the project is very large or complex code consultants can be retained to provide this service
- DShould also make sure that the construction documents contain all information required by the local authority having jurisdiction
- EEnsure that the principal continually checks against the requires of the building code and any state and local regulations
88During which phase of a project should the project team review the code requirements or interact with officials having jurisdiction over the project? (choose the four that apply)
- AAt the end of the construction document phase
- BAt the beginning of the schematic design phase
- CAt the beginning of the programming phase
- DDuring a scope change in the project
- EBefore the end of the predesign phase
- FMidway through construction
89Which of the following apply to the main goal of a quality control program?
- AIs to manage the project in such way that the original design objectives of the client are achieved
- BTo accomplish this the project manager and the deign team must keep in mind the original assumptions about the project design (which are typically formalized in the program)
- CThese include the size and relationships of spaces
- DThe overall functionality of the building
- EThe requirements pertaining to building systems, materials and finishes
- FSustainability issues
- GTh general level of quality the owner desires
90Design review can be accomplished with:
- AChecklists
- BRegular comparison with the program
- CRegular client reviews and written approvals
- DOutsourcing
91Assumptions about the project design that are formalized in the program include:
- ASize and relationships of spaces
- BThe overall functionality of the building
- CThe requirements pertaining to building systems, materials, and finishes
- DSustainability issues
- EThe general level of quality the owner desires
Information
- Description
- Architectural Registration Exam - NCARB A.R.E 5.0 Project Management Quiz on Project Execution and Quality Control, created by Marita Rose on 07/03/2018.
- Author
- Marita Rose
- Language
- English
- Views
- 0
- Tags
- Rating
- No ratings yet Rate this quiz