Chapters 5-9 T/F
Create a free account to finish this quiz
Save your progress and see your final score.
Already have an account? Sign in
Questions in this quiz (50)
1Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.
- AT/F
- BAnswer: FALSE
2The statement of work is a detailed narrative description of the work required for a project.
- AT/F
- BAnswer: TRUE
3A comprehensive statement of work includes an estimate of time and costs, resource requirements, and the scope of the work to be performed.
- AT/F
- BAnswer: TRUE
4Until a project has gone through work breakdown structure, it is impossible to determine the relationships among the constituent activities.
- AT/F
- BAnswer: TRUE
5The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.
- AT/F
- BAnswer: FALSE
6A work package may be composed of one or more subdeliverables.
- AT/F
- BAnswer: FALSE
7A work package may consist of more than one milestone.
- AT/F
- BAnswer: TRUE
8Work authorization functions as the formal "It's OK to begin work," on the project.
- AT/F
- BAnswer: TRUE
9The terms lump-sum contract and turnkey contract are interchangeable.
- AT/F
- BAnswer: TRUE
10A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.
- AT/F
- BAnswer: FALSE
11Team building and conflict management skills are two of the most important people skills that project managers can cultivate.
- AT/F
- BAnswer: TRUE
12The first step in assembling a project team is to talk to potential team members.
- AT/F
- BAnswer: FALSE
13If preferred project team members are not available, the project manager should notify top management of the consequences.
- AT/F
- BAnswer: TRUE
14Project managers are best able to promote a sense of enthusiasm within the project team when they create an environment that is challenging, supportive, and personally rewarding.
- AT/F
- BAnswer: TRUE
15High turnover among project team members is a key element of success since new team members will bring fresh perspectives and ideas to the group.
- AT/F
- BAnswer: FALSE
16Project team productivity is at its peak during the norming phase of group development.
- AT/F
- BAnswer: FALSE
17The punctuated equilibrium model suggests that groups spend the majority of their time in stasis.
- AT/F
- BAnswer: TRUE
18Cross-functional cooperation directly influences both the actual implementation of the project and the team members' assessment that the project experience was worthwhile.
- AT/F
- BAnswer: TRUE
19In general, a superordinate goal is a replacement goal for the goals of all functional groups involved in the project.
- AT/F
- BAnswer: FALSE
20Accessibility is the perception of the project team members that they are physically located in such a way that it is easy for them to interact.
- AT/F
- BAnswer: FALSE
21The risk is highest in the earliest phase of the project life cycle.
- AT/F
- BAnswer: TRUE
22Opportunity emerges from favorable project circumstances and risk from unfavorable events.
- AT/F
- BAnswer: TRUE
23As risk decreases in the project life cycle, opportunity increases
- AT/F
- BAnswer: FALSE
24Risks can be quantified by multiplying the likelihood a failure will occur by the severity of the failure.
- AT/F
- BAnswer: TRUE
25Technical risk is the probability that the project will not perform to the required standards or produce substandard products or have excessive operating cost consumption.
- AT/F
- BAnswer: TRUE
26The probability that the investments made to fund the front-end activities will be lost due to project abandonment is financing risk.
- AT/F
- BAnswer: FALSE
27One approach to risk mitigation is simply to accept it.
- AT/F
- BAnswer: TRUE
28Risk cannot be transferred because ultimately your own project will suffer the consequences if the event occurs.
- AT/F
- BAnswer: FALSE
29Contingency reserves require a construction company to hold back some funds in an account just in case something happens that increases the overall project cost.
- AT/F
- BAnswer: TRUE
30The highest dollar value of reserves is typically task contingency.
- AT/F
- BAnswer: FALSE
31Direct costs are those clearly assigned to the aspect of the project that generated the cost.
- AT/F
- BAnswer: TRUE
32Material is an example of a cost that is recurring, variable and direct.
- AT/F
- BAnswer: TRUE
33An expedited cost is one that does not vary with respect to their usage.
- AT/F
- BAnswer: FALSE
34The term expedited cost has the same meaning as crashing cost in the project management milieu.
- AT/F
- BAnswer: TRUE
35An order of magnitude estimate is usually more accurate than a ballpark estimate.
- AT/F
- BAnswer: FALSE
36Comparative estimates are more accurate than definitive estimates when applied to the same project.
- AT/F
- BAnswer: TRUE
37A learning rate of 90% means that for every doubling of output, the time required by the activity falls by 10%.
- AT/F
- BAnswer: TRUE
38Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.
- AT/F
- BAnswer: FALSE
39A common reason for cost overruns in a project is a low initial estimate of project cost.
- AT/F
- BAnswer: TRUE
40There is a tendency for different departments or functions to compete for scarce resources in a zero-sum game when bottom-up budgeting is used to develop a project budget.
- AT/F
- BAnswer: FALSE
41Preceding activities are those that must occur before others can be done.
- AT/F
- BAnswer: TRUE
42A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
- AT/F
- BAnswer: FALSE
43A merge activity has two or more immediate predecessors.
- AT/F
- BAnswer: TRUE
44Float is always measured in exactly the same way as slack.
- AT/F
- BAnswer: TRUE
45The PERT technique assumes that durations are more deterministic.
- AT/F
- BAnswer: FALSE
46Burst activities are those with two or more successor activities.
- AT/F
- BAnswer: FALSE
47You must know the mean of an activity in order to determine its standard deviation.
- AT/F
- BAnswer: FALSE
48In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
- AT/F
- BAnswer: TRUE
49The late start time should be calculated using a forward pass through the network.
- AT/F
- BAnswer: FALSE
50Negative float exists when a project's critical path has been completed more quickly than anticipated.
- AT/F
- BAnswer: TRUE