PMP - Full Exam 1

Deleted user 200 questions

Take the quiz

Questions in this quiz (200)

  1. 1A business case, which helps to determine whether a project is worth the investment, is created on the basis of the following except for
    1. AMarket Demand
    2. BEcological Impacts
    3. CSocial Need
    4. DAvailability of Funds
  2. 2You are in charge of developing a new product for an organization. Your quality metrics are based on the 80th percentile of each of the last three products developed. This is an example of:
    1. AStatistical sampling
    2. BMetrics
    3. CBenchmarking
    4. DOperational definitions
  3. 3The two closing procedures are called:
    1. AContract closure and scope verification
    2. BClose Procurements and Close Project
    3. CProject closure and product verification
    4. DProject closure and lessons learned
  4. 4During the develop schedule process, the Project Manager may have to go through several iterations of the schedule before establishing the schedule baseline. All of the following are tools and techniques that may be used during this process:
    1. ACritical Path Method, GERT, Resource Requirements
    2. BResource Leveling Heuristics, Mathematical Analysis, Calendars
    3. CSchedule compression, Resource optimization techniques, Critical chain method
    4. DGERT, PERT, Leads and Lags
  5. 5Which of the following models of conflict resolution allows a cooling off period, but seldom resolves the issue in the long term?
    1. AProblem solving
    2. BWithdrawal
    3. CForcing
    4. DSmoothing
  6. 6In communication, the receiver decodes the messages based on all but the following:
    1. ACulture
    2. BSemantics
    3. CLanguage
    4. DDistance
    5. EKnowledge
  7. 7How much time does the typical project manager spend communicating both formally and informally?
    1. A40-60%
    2. B50-70%
    3. C60-80%
    4. D75-90%
  8. 8Group brainstorming encourages all of the following except:
    1. ATeam building A project manager facilitates communication
    2. BAnalysis of alternatives
    3. CConvergent thinking
    4. DUninhibited verbalization
  9. 9The critical element in a project's communication system is the:
    1. AProgress report
    2. BProject directive
    3. CProject manager
    4. DCustomer
  10. 10System integration consists of:
    1. AAssuring that the pieces of a project come together at the right time
    2. BPlanning for contingencies that may occur throughout the life cycle of the project
    3. CThe pieces of the project function as an integration unit
    4. Da and c

Information

Description
User has deleted their subject information Quiz on PMP - Full Exam 1, created by Deleted user on 29/03/2017.
Author
Deleted user
Language
English
Views
132
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?