Questions in this quiz (20)

  1. 1You are the project manager of the BlueSky Network Upgrade Project. You have 15 project team members and you’re speaking with them about the importance of communication. You show them the communication model and give examples of each of the components of the model. One of the project team members asks for an example of noise. Of the following, which one is an example of noise?
    1. AA. Fax machine
    2. BB. Ad hoc conversations
    3. CC. Contractual agreements
    4. DD. Distance
  2. 2You are the project manager for the JHG Project. Management has requested that you create a document detailing what information will be expected from stakeholders and to whom that information will be disseminated. Management is asking for which one of the following?
    1. AA. The roles and responsibilities matrix
    2. BB. The scope management plan
    3. CC. The communications management plan
    4. DD. The communications worksheet
  3. 3Which of the following will help you, the project manager, complete the needed communications management plan by identifying the stakeholders’ communication needs?
    1. AA. Identification of all communication channels
    2. BB. Formal documentation of all communication channels
    3. CC. Formal documentation of all stakeholders
    4. DD. Lessons learned from previous similar projects
  4. 4You are the project manager for the JGI Project. You have 32 stakeholders on this project. How many communication channels do you have?
    1. AA. Depends on the number of project team members
    2. BB. 496
    3. CC. 32
    4. DD. 1
  5. 5You are the project manager for the KLN Project. You had 19 stakeholders on this project and have added three team members to the project. How many more communication channels do you have now compared with before?
    1. AA. 171
    2. BB. 231
    3. CC. 60
    4. DD. 1
  6. 6A memo has been sent to you, the project manager, the project team members, and the project customers from the project sponsor. In this instance, who is the sender?
    1. AA. Project sponsor
    2. BB. Project manager
    3. CC. Project team members
    4. DD. Project customers
  7. 7Beth is a project manager for her organization and she is working with the stakeholders to develop a communications management plan. She wants to acknowledge the assumptions and constraints in the project. Which one of the following is an example of a project communication constraint?
    1. AA. Ad hoc conversations
    2. BB. Demands for formal reports
    3. CC. Stakeholder management
    4. DD. Team members in different geographical locales
  8. 8Project managers can present project information in many different ways. Which one of the following is not a method a project manager can use to present project performance?
    1. AA. Histograms
    2. BB. S-curves
    3. CC. Bar charts
    4. DD. RACI charts
  9. 9There are many terms that you’ll need to know for your PMI examination that deal with the project communications. Of the following, which term describes the pitch and tone of an individual’s voice?
    1. AA. Paralingual
    2. BB. Feedback
    3. CC. Effective listening
    4. DD. Active listening
  10. 10You are the project manager of the KMH Project. This project is slated to last eight years. You have just calculated EVM and have a cost variance (CV) of –$3,500, which is outside of the acceptable thresholds for your project. What type of report is needed for management?
    1. AA. Progress report
    2. BB. Forecast report
    3. CC. Exception report
    4. DD. Trends report

Information

Description
Project Communications Management