1All of the following are characteristics of a project except:
- AIt is temporary.
- BIt has a definite beginning and end.
- CIt creates a unique product.
- DIt repeats itself every month.
2Which of the following statements about the project manager is true?
- AThe project manager provides subject matter expertise.
- BThe project manager ensures buy-in and gathers support for the project throughout the organization.
- CThe project manager is responsible for managing the project to meet project objectives and deliver value.
- DThe project manager determines the priorities between project constraints.
3Who has the most power in a project-oriented organization?
- AThe project manager
- BThe functional manager
- CThe team
- DThey all share power equally.
4What is a program?
- AThe same thing as a project
- BA group of related projects
- CA type of organizational structure
- DOngoing operations rather than project work
5A project team is concerned because many people are asking him to do things. If he works in a functional organization, who has the power to give him direction?
- AThe project manager
- BThe functional manager
- CThe team
- DThe PMO
6Operational work is different from project work in that operational work is:
- AUnique
- BTemporary
- COngoing and repetitive
- DA part of every project activity
7In a project-oriented organization, the project team:
- AReports to many managers
- BHas no loyalty to the project
- CReports to the functional manager
- DWill not always have a "home"
8Which of the following statements about the project management office (PMO) is true?
- AThe PMO standardizes the management of projects.
- BA supportive PMO directly manages most projects within an organization.
- CA directive PMO allows the project manager to control most aspects of the project.
- DA directive PMO provides project managers but is not responsible for the results of projects.
9What is the main difference between a matrix organization and a functional organization?
- AIn a functional organization, project managers have more authority than they do in matrix organizations.
- BMore people work full-time on projects in a functional organization than in a matrix organization.
- CProject team members usually report to two managers in a matrix organization--the functional manager and the project manager.
- DMost companies have found that a functional organizational structure provides the most flexibility for managing projects.
10A collection of programs and projects managed as a group to achieve a specific strategic business goal is called:
- AOperational work
- BA portfolio
- CA baseline
- DA life cycle
11A project manager is trying to complete a software development project but cannot get enough attention for the project. Resources are focused on completing process-related work, and the project manager has little authority to properly assign resources. What form of organization must the project manager be working in?
- AFunctional
- BMatrix
- CExpediter
- DCoordinator
12Which of the following is a responsibility of the project manager?
- AProviding funding for the project
- BHelping to write the project charter
- CProtecting the project from outside influences and changes
- DSetting priorities among different projects
13The organization's management has decided that all orders will be treated as "projects" and that project managers will be used to update orders daily, resolve issues, and ensure that the customer formally accepts the product within 30 days of completion. The project manager will not be required to perform planning or provide documentation other than daily status updates. Which of the following statements about this situation is true?
- ABecause each individual order is a "temporary endeavor," each order is a project.
- BThis is an example of program management since there are multiple projects involved.
- CThis is an example of a recurring process, not a project.
- DThe orders described here are both temporary and complex enough that they require proper project management.
14Which of the following is one of the seven project constraints?
- AChange requests
- BSellers
- COrganizational structure
- DCustomer satisfaction
15During project planning in a balanced matrix organization, the project manager determines that additional human resources are needed. From whom would she request these resources?
- AThe PMO manager
- BThe functional manager
- CThe team
- DThe project sponsor
16During which process group is the project work as defined in the project management plan completed?
- AInitiating
- BExecuting
- CMonitoring and controlling
- DClosing
17Which of the following activities takes place in the initiating process group?
- AEnsuring that the high-level product scope is as detailed as is practical.
- BEnsuring continued understanding of the work
- CRemoving roadblocks
- DReviewing bids and selecting sellers
18Which of the following is the most appropriate thing to do in project closing?
- AWork with the customer to determine acceptance criteria.
- BCollect historical information from previous projects.
- CConfirm that all the requirements in the project have been met.
- DGain formal approval of the management plans.
19Which of the following activities takes place during project planning?
- ACreating the WBS dictionary
- BDetermining high-level requirements
- CRefining controls limits
- DValidating scope
20In which process group does the project manager focus on managing the project, engaging stakeholders, and communicating according to plan, while the team is completing the project activities?
- AMonitoring and controlling
- BManaging
- CExecuting
- DPlanning
21Which of the following is the most appropriate thing to do in the executing process group?
- AEvaluate individual team member performance.
- BEvaluate customer satisfaction regarding the project.
- CDetermine acceptance criteria.
- DDecide what level of accuracy is required for estimates.
22Which of the following statements about change-driven development life cycles is true?
- AWith an adaptive development life cycle, work is planned in long increments, which lessens the need to change and reprioritize customer requirements.
- BChange-driven projects use waterfall life cycles.
- CAdaptive development life cycles involve fixed costs as well as a fixed schedule.
- DScope, schedule, and cost are all well-defined early in a project using an adaptive development life cycle.
23During which process group should a procurement strategy be selected for each project contract?
- AInitiating
- BPlanning
- CExecuting
- DClosing
24Project closing includes all of the following except:
- ADetermining performance measures
- BHanding off the product of the project to the customer
- CMaking final payments on contracts
- DUpdating the company's organizational process assets
25What is the status of a project when the project team has completed all the required work packages and the final deliverables have been sent to the customer?
- AThe project is completed.
- BThe project is in the closing process.
- CThe project is at the end of project executing.
- DThe project is in the Validate Scope process.
26During which process does does the Perform Integrated Change Control process take place?
- APlanning
- BClosing
- CMonitoring and controlling
- DExecuting
27Which of the following takes place during project monitoring and controlling?
- APerforming procurement inspections
- BFacilitating the resolution of conflicting objectives
- CExpending and managing project funds
- DCreating a recognition and rewards system
28The ____________ is the logical breakdown of what a project manager needs to do to produce the project's deliverables.
- AProject life cycle
- BProduct life cycle
- COrganizational structure
- DExecuting process group
29During which process group does the Direct and Manage Project Work process take place?
- APlanning
- BClosing
- CMonitoring and controlling
- DExecuting
30In which process group does the project manager establish and manage communication channels?
- APlanning
- BClosing
- CMonitoring and controlling
- DExecuting
31Which document gives the project manager the authority to spend money and commit corporate resources?
- AProject charter
- BProject management plan
- CWork authorization plan
- DBusiness case
32An effective change management plan addresses all the following except:
- AProcedures
- BApproval levels
- CMeetings
- DLessons learned
33Which of the following is not an input to the Direct and Manage Project Work process?
- AApproved corrective actions
- BProject management plan
- CDeliverables
- DDefect repair orders
34Managing project knowledge is a key integration management responsibility of the project manager. This responsibility includes managing two kinds of knowledge on a project: tacit and explicit. Which of the following statements about tacit knowledge is correct?
- ATacit knowledge is fact-based and can be easily communicated through words and symbols.
- BTacit knowledge may need explanation or context to provide value.
- CTacit knowledge includes emotions, experience, and abilities.
- DLessons learned are an example of tacit knowledge.
35Which of the following best describes when a project baseline should be changed?
- AA project baseline should be changed when a major delay occurs.
- BA project baseline should be changed when a change to cost, schedule, or scope is approved.
- CA project baseline should be changed when a cost increase occurs.
- DChanges should never be made to a project baseline.
36A company is making an effort to improve its project performance and create historical records of past projects. What is the best way to accomplish this?
- ACreate project management plans.
- BCreate lessons learned.
- CCreate network diagrams.
- DCreate status reports.
37Which of the following is included in the performance measurement baseline?
- AThe agreed-upon schedule, including the start and stop times for each activity
- BAn analysis of the requirements and assumptions of each stakeholder
- CThe performance requirements that will be provided to sellers
- DThe metrics that will be used in the quality control system
38Which of the following best describes a project management plan?
- AThe schedule and cost baselines for the project
- BA description of the project's life cycle and the development cycle that will be used on the project
- CThe project charter, WBS, and project scope statement
- DA formal document showing a plan that is approved, realistic, and bought into
39You are beginning a new project that has been attempted unsuccessfully several times in the past few years. The previous projects were cancelled because of "politics"--differing views and direction by key stakeholders on the project. This is an example of:
- AStakeholder analysis
- BScope management
- CHistorical information
- DRisk identification
40Which of the following is included in a project charter?
- AA risk management strategy
- BWork package estimates
- CDetailed resource estimates
- DThe business case for the project
41Which of the following is not included in the project management plan?
- AChange management plan
- BIntegration management plan
- CConfiguration management plan
- DRequirements management plan
42When does the Monitor and Control Project Work process take place?
- AThroughout the project, from project initiating through project closing
- BDuring the monitoring and controlling process group
- CPrimarily during the executing and monitoring and controlling processes
- DDuring project planning, executing, and monitoring and controlling
43Which of the following best summarizes what happens during the Perform Integrated Change Control process?
- AAll requested changes are implemented, and any impacts on quality, risk, schedule, cost, resources, and customer satisfaction are documented.
- BChange requests to the charter and project plan are implemented by the project manager, without the need for further approvals.
- CChange requests are evaluated and accepted, rejected, or deferred to produce a list of approved change requests.
- DThe change control board reviews the impact of change requests on the project scope.
44Which of the following is not included in a project charter?
- AA detailed schedule and full risk analysis
- BA description of overall project risks
- CThe high-level requirements for the project
- DAn explanation of how the project relates to the organization's strategic goals
45Which of the following are all outputs of Monitor and Control Project Work?
- AChange requests, change log, and issue log
- BWork performance data, information, and reports
- CCorrective action, preventive action, and defect repair
- DDeliverables, change requests, and work authorization system
46Project requirements should be elicited from _________.
- AThe sponsor
- BThe project team
- CAll stakeholders
- DThe project manager
47The project team has just discovered that work critical to the completion of a project deliverable was not done. This situation was most likely caused by a lack of:
- AA good work breakdown structure
- BA matrix organization
- CSponsor direction
- DEffective status meetings
48Which of the following statements about scope is correct?
- AProject scope is defined as the project deliverables, with their associated features and functions.
- BProduct scope refers to the requirements that relate to the product, service, or result of the project.
- CProduct scope encompasses project scope.
- DProduct scope is the work the project will do to deliver a product, service, or feature.
49Which of the following is not part of the Define Scope process?
- AFacilitation
- BAlternative analysis
- CProduct analysis
- DInspection
50Which of the following is not shown on a WBS?
- AControl accounts
- BWork packages
- CDeliverables
- DWorkarounds
51Which of the following is an output of the Collect Requirements process?
- ARequirements traceability matrix
- BProject scope statement
- CWork breakdown structure
- DChange requests
52Which of the following is correct in regard to the Control Scope process?
- AEffective scope definition can lead to a more complete project statement.
- BThe Control Scope process must be done before scope planning.
- CThe Control Scope process must be integrated with other control processes.
- DControlling the schedule is the most effective way of controlling scope.
53Which of the following best describes product analysis?
- AWorking with the customer or sponsor to determine the product description during project initiating
- BMathematically analyzing the quality desired for the project as part of Plan Quality Management
- CAnalyzing the objectives and description of the product, as stated by the customer or sponsor, to define tangible deliverables
- DAnalyzing inspection data to determine whether the quality standards on the project can be met
54If the team is performing variance analysis on the project, which process are they in?
- ACollect Requirements
- BValidate Scope
- CDefine Scope
- DControl Scope
55Which of the following is not required to create the scope management plan?
- AA finalized requirements management plan
- BAny historical records and lessons learned from previous projects
- CAny existing templates, forms, or standards for scope management
- DA good understanding of the project scope
56Which of the following is not one of the rules for creating a WBS?
- AEach level of the WBS shows a smaller piece of the level above it.
- BIf a deliverable isn't in the WBS, it isn't part of the project.
- CThe project team helps to create the WBS.
- DAll levels of the WBS are broken down to the same level of detail.
57Two months into a design project, the customer requests a modification to the product. The change is made without notifying the project manager. During final testing, the results are different than what was planned for. This scenario can best be described as an example of which of the following?
- APoor scope control
- BPoor adherence to the communications management plan
- CPoor development of the quality management plan
- DPoor definition of the test plan
58What are the key outputs of the Plan Scope Management process?
- AAccepted deliverables and change requests
- BThe scope management plan and the requirements management plan
- CConstraints and assumptions
- DWork breakdown structure and WBS dictionary
59What is done during the Validate Scope process?
- AThe project manager measures and assesses work performance data against the scope baseline.
- BThe team confirms the validity and appropriateness of the project scope with key stakeholders.
- CThe project manager gains formal acceptance of deliverables from the customer or sponsor.
- DThe quality control department checks to see if the requirements specified for the deliverables have been met, and makes sure the work is correct.
60What does the "work" in "work breakdown structure" refer to?
- AThe tasks that are being broken down from the required activities
- BThe processes involved in completing the work packages
- CThe activities or actions needed to complete the deliverables of the work packages
- DThe products or deliverables that will result from the activities
61Which of the following is a tool or technique of the Control Schedule process?
- AProject management software
- BAlternative analysis
- CDependency determination
- DParametric estimating
62What is the best project management tool to use to determine the longest time the project will take?
- AWork breakdown structure
- BNetwork diagram
- CBar chart
- DProject charter
63Which of the following statements is correct?
- ACrashing always shortens the timeline but rarely increases risk.
- BFast tracking often results in rework, and crashing often results in increased cost.
- CCrashing is only a viable alternative if earned value analysis indicates that the project is ahead of schedule and under budget.
- DFast tracking will result in fewer parallel activities than crashing the project.
64All the following statements describe a schedule management plan except:
- AIt details the scheduling methodology that will be used on the project.
- BIt identifies schedule change control procedures.
- CIt must be issued as a formal and detailed document.
- DIt establishes a plan for managing schedule variances.
65Using the average labor hours per installation from past projects to predict the future is an example of which of the following?
- AParametric estimating
- BThree-point estimating
- CAnalogous estimating
- DMonte Carlo analysis
66Which schedule management output is used to measure the project team's progress throughout the project?
- AScope baseline
- BSchedule baseline
- CCost baseline
- DPerformance baseline
67What is shown on a project schedule network diagram?
- AThe external dependencies that affect the schedule
- BThe logical relationships among project activities
- CThe resource assignments for the project
- DThe schedule constraints and project milestones
68What is the most commonly used logical relationship represented using the precedence diagramming method (PDM)?
- AStart-to-start (SS)
- BFinish-to-start (FS)
- CFinish-to-finish (FF)
- DStart-to-finish (SF)
69Identifying and documenting the specific activities that must be performed to produce work packages is called:
- ADefine Scope
- BEstimate Activities
- CDefine Activities
- DSequence Activities
70What is the best method to use when estimating how long is will take to complete an activity that has not previously been done by your company?
- AAnalogous estimating
- BThree-point estimating
- CMonte Carlo analysis
- DParametric estimating
71Which of the following activities isn't part of the schedule management knowledge area?
- AIdentifying the type and quantity of resources that will be required for each activity
- BOrganizing the activities and milestones in the order in which the work will be performed
- CEstimating the amount of time required to complete each activity
- DDecomposing the work packages created in the WBS into the activities required to produce the work package deliverables
72In which schedule management processes are project schedule network diagrams created and analyzed?
- ADevelop Schedule; Control Schedule
- BSequence Activities; Develop Schedule
- CDefine Activities; Sequence Activities
- DEstimate Activity Durations; Control Schedule
73Your team is calculating triangular distributions. Which of the following processes are they engaged in?
- AControl Schedule
- BEstimate Schedule
- CSequence Activities
- DEstimate Activity Durations
74You have a project with four activities as follows. Activity 1 can start immediately and has an estimated duration of 1. Activity 2 can start after activity 1 is completed and has an estimated duration of 4. Activity 3 can start after activity 2 is completed and has an estimated duration of 5. Activity 4 has an estimated duration of 8. It can start after activity 1 is completed. Both activity 3 and activity 4 must be completed before the project is complete. What is the critical path of the project?
- AStart 1, 2, 3, End
- BStart, 1, 4, 3, End
- CStart, 1, 4, End
- DStart, 1, 2, 3, 4, End
75The critical path for your project is very close in length to the near-critical path. What does this tell you?
- AYour project has higher risk because these two paths are of similar length.
- BYou don't need to worry about the length of the near-critical path; by definition, only the critical path is "critical."
- CYou should focus on increasing the length of the near-critical path; otherwise, it could threaten the team's ability to complete the critical path on schedule.
- DHaving two paths of similar length makes the project less risky.
76Which of the following is an input to the Estimate Costs process?
- AReserve analysis
- BQuality management plan
- CBasis of estimates
- DCost forecasts
77If the team is using earned value analysis and variance analysis, they are performing:
- ACost control
- BQualitative risk analysis
- CDependency determination
- DCost budgeting
78As a rule, which of the following is a true statement about estimates that are made early in a project?
- AThey cost more to create than estimates that are made later.
- BThey are more likely to accurately predict the final results than estimates that are made later.
- CThey take more time to put together than estimates that are made later.
- DThey should be expressed as a wider range than estimates that are made later.
79During project executing, the forecasted remaining hours exceed planned remaining hours. Consequently, the project takes on a negative variance. Which calculation is the project manager likely to use as a measurement tool to validate this information?
- AEV - PV
- BEV/AC
- CEV/PV
- DEV - AC
80Which of the following are components of cost management?
- AFloat calculations, estimate at completion, and dependency determination
- BAnalogous estimating, basis of estimates, and earned value analysis
- CEarned value analysis, dependency determination, and basis of estimates
- DDependency determination, float calculations, and earned value analysis
81A cost baseline is an output of which cost management process?
- AEstimate Activity Resources
- BEstimate Costs
- CDetermine Budget
- DControl Costs
82Which of the following would not be part of a cost management plan?
- AApproved estimating techniques
- BHow the project resources will be allocated
- CRules for measuring cost performance
- DChange control procedures
83An estimate that is -25/+75 percent of actual is an example of a __________ estimate.
- ABudget
- BRough order of magnitude (ROM)
- CDefinitive
- DParametric
84Which of the following represents the estimated value of the work actually accomplished?
- AEarned value (EV)
- BPlanned value (PV)
- CActual cost (AC)
- DCost variance (CV)
85The project manager is allocating overall cost estimates to individual activities to establish a baseline for measuring project performance. What process is this?
- APlan Cost Management
- BEstimate Costs
- CDetermine Budget
- DControl Costs
86A project team accomplished $3,000 worth of work and has spent $4,000 to date. If they budgeted $5,000 for the work scheduled, what is the cost variance (CV)?
- A($1,000)
- B$2,000
- C$1,000
- D($2,000)
87In which cost management process are cost forecasts developed?
- AEstimate Costs
- BPlan Cost Management
- CDetermine Budget
- DControl Costs
88Which of the following formulas would be used during Control Costs to estimate how much more the remainder of the project will cost to complete?
- AEV - PV
- BEV - AC
- CEV/PV
- DEAC - AC
89What is least likely to be included in the key output of Plan Cost Management?
- AControl thresholds
- BRoles and responsibilities for cost activities
- CEarned value analysis
- DFunding decisions
90If planned value (PV) is $29,000, actual cost (AC) is $32,000, and earned value (EV) is $30,000, what is the schedule variance (SV)?
- A0.938
- B$1,000
- C1.034
- D($2,000)
91Which statement about quality and grade is true?
- A"Grade" refers to the degree to which a deliverable fulfills requirements.
- B"Quality" is used to categorize deliverables or resources that have a common function but varying technical specifications.
- CA low-grade resource could be of acceptable quality if it meets the established quality requirements.
- DA resource is only of acceptable quality if it is high grade.
92The purpose of a quality audit is to:
- ACheck if the customer is following their quality process
- BHave the customer formally accept the quality of a particular deliverable
- CIdentify inefficient and ineffective policies
- DDetermine the quality processes that will be used on the project
93What tool or technique in Plan Quality Management involves reviewing the quality practices used on other similar projects to establish quality metrics?
- ACost-benefit analysis
- BBenchmarking
- CMatrix diagrams
- DFlowcharts
94All of the following are tools or techniques of Control Quality except:
- ACost of quality
- BInspection
- CControl charts
- DChecklists
95Which of the following presents measurement results in order of frequency and helps the project team identify the root causes resulting in the most problems?
- AFlowchart
- BFishbone diagram
- CControl chart
- DPareto diagram
96During ________, the project manager regularly evaluates project performance to ensure that quality standards are being followed.
- APlan Quality Management
- BManage Quality
- CControl Quality
- DPerform Quality Management
97Identifying ways to eliminate the causes of quality problems would most likely lead to:
- AQuality audits
- BWork performance information
- CRecommended corrective actions
- DStatistical sampling
98Which quality management process involves determining the definition of quality for the project and planning how to ensure that the project achieves that level of quality?
- AManage Quality
- BControl Quality
- CPlan Quality Management
- DPlan Quality Assurance
99Which of the following is not typically part of the Control Quality process?
- AChecking to see whether the defined quality standards and procedures are being followed
- BUsing statistical sampling and inspections to confirm that quality standards are being met
- CEvaluating a quality problem to see how it can be addressed
- DObtaining confirmation that the agreed-upon requirements have been met
100One purpose of a fishbone diagram is to:
- AShow how a process or system flows from beginning to end
- BConfirm that quality policies and procedures are being followed
- CDetermine the organization of the project
- DShow functional responsibilities and how they are related to one another and to the objectives of the project
101Which of the following tools and techniques is not used in Plan Quality Management?
- AMatrix diagrams
- BMind mapping
- CBenchmarking
- DProcess analysis
102Inputs to the Control Quality process include quality metrics, approved change requests, and:
- AControl charts
- BWork performance data
- CVerified deliverables
- DWork performance information
103Which of the following tools or techniques would be the most useful for organizing the results of a root cause analysis in Manage Quality?
- AAffinity diagram
- BAudit
- CDesign for X
- DFlowchart
104What are quality checklists used for?
- ATo verify that a required action has taken place or a required item has been included
- BTo gather data, such as the number of quality defects found during inspections
- CTo document variances from the quality standards
- DTo measure the quality of the project management planning process
105Which of the following is least likely to be included in the key outputs of Plan Quality Management?
- AWhich metrics will be used to control quality
- BWhich parts of the deliverables will be checked, and when
- CWhich practices and standards will be used to measure quality
- DThe schedule for the quality audits, including who will do them
106What is the most correct statement about conflict?
- AThe primary source of conflict is personality.
- BConflict can be beneficial.
- CConflict is best resolved by smoothing.
- DConflict is caused by a failure of leadership.
107Which of the following best describes what is included in the resource management plan?
- AThe results of team performance assessments
- BThe established roles and responsibilities for the project
- CProject team assignments
- DChange requests related to the project's physical resources
108The project manager is reviewing the organization's hiring procedures and policies related to assigning resources to the project. What process are they working in?
- APlan Resource Management
- BEstimate Activity Resources
- CAcquire Resources
- DControl Resources
109The project team is working in an adaptive environment on a complex project that requires a lot of coordination. Under these circumstances, the best strategy is to:
- AColocate the team
- BHire a contractor
- CHold more meetings to get the word out
- DGain extra assistance from management
110What does a resource histogram show that a responsibility assignment matrix (RAM) does not?
- AThe person in charge of each activity
- BActivities
- CInterrelationships
- DTime
111Which resource management process deals strictly with physical resources?
- APlan Resource Management
- BEstimate Activity Resources
- CAcquire Resources
- DControl Resources
112Which type of hierarchical chart categorizes project work by type of resource?
- AOrganizational breakdown structure
- BWork breakdown structure (WBS)
- CResource breakdown structure
- DRACI chart
113Two team members are having a big disagreement over the type of computer hardware to use on the project. Who should resolve the dispute?
- AThe team members and their project manager
- BThe project manager
- CManagement
- DThe sponsor
114All the following are included in the key outputs of the Plan Resource Management process except:
- ATraining goals
- BProject organizational charts
- CWork performance information
- DProcess for acquiring physical resources
115What is multicriteria decision analysis?
- AAn analytical tool for making decisions about team-building and training activities
- BA technique used to evaluate potential team members
- CA quantitative approach to developing recognition and rewards systems
- DA technique used for designing personnel assessment tools
116What does "RACI" stand for?
- ARole, Activity, Communication, Information
- BReward, Appraise, Confirm, Invite
- CRecognize, Act, Check, Identify
- DResponsible, Accountable, Consult, Inform
117Preassignment and negotiation are important tools and techniques in which resource management process?
- ADevelop Team
- BAcquire Resources
- CPlan Resource Management
- DManage Team
118While working in the Control Resources process, the project manager needs to compare actual versus planned resource usage. Which document would provide the necessary information regarding how physical resources should be utilized?
- ALessons learned register
- BResource breakdown structure
- CWork performance information
- DResource management plan
119Which of the following is an input to Develop Team?
- ATeam performance assessments
- BProject team assignments
- CInterpersonal skills
- DPersonnel assessment tools
120Resource requirements documentation and updates to the resource breakdown structure are outputs of which process?
- APlan Resource Management
- BControl Resources
- CPlan Procurement Management
- DEstimate Activity Resources
121Inputs to the Plan Communications Management process include:
- AProject communications
- BThe stakeholder register
- CWork performance reports
- DForecasts
122The team is assessing how communications are going throughout the project to see if the right information is getting to the right people, at the right time, and in the right way. Which process are they engaged in?
- AManage Communications
- BMonitor Communications
- CPlan Communications Management
- DMonitor and Control Project Work
123The documentation of a project's successes and failures that is produced during the Manage Communications process and then saved for the benefit of other projects is called:
- ALessons learned
- BStatus reports
- CFeedback
- DPerformance appraisals
124The project manager wants to let the team know that the weekly project status report is now officially due by 4 p.m. on Thursdays. Which form of communication would be most appropriate in this situation?
- AFormal written communication
- BFormal verbal communication
- CInformal written communication
- DInformal verbal communication
125Which of the following is not something you need in order to perform Monitor Communications?
- AProject management plan
- BWork performance reports
- CYour firm's procedures, reporting formats, and standards for communication
- DIssue log
126Which of the following are all reporting tools used in Manage Communications?
- AStatus reports, quality reports, and lessons learned documentation
- BTrend reports, forecasting reports, and lessons learned documentation
- CPayroll reports, status reports, and trend reports
- DForecasting reports, payroll reports, and quality reports
127A report that is focused on predicting future project status and performance is called a:
- AForecasting report
- BTrend report
- CStatus report
- DVariance report
128What is one of the most important things for a project manager to keep in mind when developing a plan for project communications activities?
- ACommunication skills are most important during project executing.
- BThe receiver is responsible for making sure communications are clear.
- COnly the team members need to be concerned about communicating with each other.
- DThe plan should be based on the information needs of stakeholders and on the needs of the project.
129Change requests are an output of which communications management process?
- AManage Communications
- BDefine Communications
- CMonitor Communications
- DPlan Communications Management
130A team of seven people adds two more people to the team. How many communication channels are there now?
- A9
- B36
- C18
- D81
131If the team is analyzing communication requirements and assessing communication models, technology, and methods, which process are they engaged in?
- AManage Stakeholder Engagement
- BPlan Communications Management
- CMonitor Communications
- DManage Communication
132Which of the following should the project manager be doing as part of Manage Communications?
- APreparing and distributing work performance reports
- BUpdating the issue log
- CProviding opportunities for stakeholders to request additional information
- DAnalyzing communication requirements
133During Monitor Communications, the project manager will need to rely on metrics established in the communications management plan, as well as ___________, to determine if communication is breaking down on the project.
- AParametric estimating
- BSoft skills
- CDecision tree analysis
- DAffinity diagrams
134Which of the following is an example of push communication?
- AA blog post
- BA sales meeting
- CVideoconferencing
- DAn interview
135Three additional people have been added to the project team. What does the project manager need to keep in mind in terms of project communications?
- AThe number of communication channels on the project will increase by six.
- BThe number of communication channels on the project will triple.
- CThe communication needs of a project grow rapidly with each additional stakeholder.
- DA formal written introduction should be sent to the existing members of the project team.
136For which risk management process is the project charter a required input?
- AMonitor Risks
- BPlan Risk Responses
- CIdentify Risks
- DPlan Risk Management
137The project manager is assessing the data used to identify the project risks to determine its accuracy and reliability. What tool or technique are they using?
- ATrigger data analysis
- BData quality assessment
- CA risk rating matrix
- DAnalysis of trends in qualitative risk analysis
138Which of the following best describes a risk owner?
- AThe person who identified a risk
- BThe department that is the source of the risk and is most knowledgeable about it
- CThe department that will be most affected by the risk
- DThe person who will be responsible for implementing the risk response strategy
139The team is conducting a risk audit. What process are they working in?
- APlan Risk Responses
- BManage Risks
- CMonitor Risks
- DPlan Risk Management
140The project manager is performing decision tree analysis to choose between several alternative courses of action. If one risk event has a 90 percent change of occurring, and its consequences will be $10,000, what does $9,000 represent?
- ARisk value
- BPresent value
- CExpected monetary value (EMV)
- DContingency budget
141Which section of the risk management plan defines how risk management will be performed for the project?
- AMethodology
- BDefinitions
- CTiming
- DRoles and responsibilities
142The risk owner was notified that a risk trigger has occurred, and they are leading the risk response plan to react to the risk event. What process are they working in?
- AMonitor Risks
- BIdentify Risks
- CPlan Risk Responses
- DImplement Risk Responses
143In response to an identified risk, the project manager meets with the team and management to develop a strategy. After discussions, they decide that it would be best to ensure that the risk happens. This is an example of which risk response strategy?
- AShare
- BExploit
- CEscalate
- DEnhance
144While performing quantitative risk analysis, which tool would the project manager use to simulate the cost or schedule results of the project?
- AMonte Carlo analysis
- BNetwork diagram
- CQualitative risk analysis
- DPrecision testing
145A project manager has just completed subjectively evaluating risks on the project. Which of the following is the most important output of this process?
- AAn assessment of overall project risk exposure
- BA determination of which risks to process further and which to simply document
- CThe identification of risk triggers
- DThe identification of residual risks
146When you were first assigned to the project, the sponsor informed you that a schedule delay of 30 days would be unacceptable. What is the term for this kind of constraint?
- ARisk tolerance
- BRisk appetite
- CRisk averse
- DRisk threshold
147Which of the following is not included in the risk register as an output of Identify Risks?
- AList of risk owners
- BList of potential risk responses
- CThe root causes of the risks
- DList of risks
148The project manager is communicating risk status, ensuring that proper risk management procedures are being followed, and closing out risks. What process are they working in?
- AIdentify Risks
- BMonitor Risks
- CPlan Risk Management
- DImplement Risk Responses
149Which of the following statements is true?
- AManagement approval is needed to use contingency reserves.
- BManagement reserves are for items that the project team was not able to identify.
- CThe project manager can approve the use of management reserves.
- DManagement reserves are calculated and become part of the cost baseline.
150What is the difference between risk appetite and risk threshold?
- ARisk threshold refers to the acceptable level of risk in general, and risk appetite refers to the specific point at which the risk becomes unacceptable.
- BRisk threshold refers to the acceptable level of risk related to the schedule, and risk appetite refers to a specific amount of acceptable risk related to scope.
- CRisk appetite refers to the acceptable level of risk in general, and risk threshold refers to the specific point at which risk becomes unacceptable.
- DThere is little difference between the two terms; they can be used interchangeably.
151With which type of contract is the seller most concerned about project scope?
- AFixed price (FP)
- BCost plus fixed fee (CPFF)
- CTime and material (T&M)
- DPurchase order
152Which of the following activities occurs during the Plan Procurement Management process?
- AMake-or-buy decisions
- BAnswering sellers' questions about the bid documents
- CAdvertising
- DProposal evaluation
153The contract for the project specifies that the seller will be paid for actual costs plus a percentage of any cost savings if the actual costs are below a targeted amount. What type of contract is being used?
- AFixed price incentive fee (FPIF)
- BTime and material (T&M)
- CCost plus incentive fee (CPIF)
- DPurchase order
154Which of the following should the project manager do in the Conduct Procurement process?
- AEvaluate risks.
- BSelect a contract type.
- CPerform market research.
- DAnswer sellers' questions about procurement documents.
155A team is in the Plan Procurement Management process. Which of the following are they working on?
- AEvaluating proposals received
- BAwarding a procurement contract
- CCreating a request for proposal (RFP)
- DConducting a procurement audit
156What is one of the buyer's key objectives during contract negotiations?
- AObtain a fair and reasonable price.
- BNegotiate a price under the seller's estimate.
- CEnsure that all project risks are thoroughly delineated.
- DEnsure that an effective communications management plan is established.
157Which of the following is an example of a contract price that might be included in a cost plus fixed fee (CPFF) contract?
- A$10,000 plus fee
- BCost plus $10,000 as a fee
- C$10,000
- D$150 per hour
158Source selection criteria are an output of which procurement management process?
- AControl Procurements
- BPlan Risk Responses
- CPlan Procurement Management
- DEstimate Costs
159Which input to Conduct Procurements is a response to the project's bid documents?
- AIndependent cost estimates
- BChange requests
- CSelected sellers
- DSeller proposals
160Which of the following statements about contracts and agreements is true?
- AAn agreement is a type of contract, but a contract isn't necessarily an agreement.
- BContracts can only be in writing.
- CContracts are generally used within an organization rather than in connection with procurements with external entities.
- DA contract is a type of agreement, but an agreement isn't necessarily a contract.
161Work performance data is an input to which procurement management process?
- AAcquire Resources
- BControl Procurements
- CPlan Procurement Management
- DConduct Procurements
162Which tool or technique of Control Procurements involves negotiating a form of seller change requests?
- AContract change control system
- BInspections and audits
- CPerformance reporting
- DClaims administration
163The project manager has determined that a consultant is needed to immediately begin working on a part of the project. The work is expected to last a few weeks. What is the most appropriate contract type in this situation?
- AFixed price (FP)
- BFixed price with economic pride adjustments (FPEPA)
- CTime and material (T&M)
- DCost plus fixed fee (CPFF)
164Bidder conferences are used during which procurement management process?
- AConduct Procurements
- BControl Procurements
- CPlan Procurement Management
- DPlan Procurements
165The stakeholder engagement plan, the change log, and __________ are inputs to the Manage Stakeholder Engagement process.
- AStakeholder questionnaires
- BBrainstorming
- CThe communications management plan
- DFormal and informal conversations
166Stakeholder assessment and classification information is documented in an output of which process?
- APlan Stakeholder Engagement
- BIdentify Stakeholders
- CManage Stakeholder Engagement
- DMonitor Stakeholder Expectations
167What is a stakeholder engagement assessment matrix?
- AA tool used in Manage Stakeholder Engagement
- BAn input to Monitor Stakeholder Engagement
- CAn output of Identify Stakeholders
- DA tool used in Plan Stakeholder Engagement
168Which of the following is not true about the stakeholder engagement plan?
- AIt is part of the project management plan.
- BIt should be sent out to everyone on the team or posted in an accessible location.
- CIt will be re-evaluated and updated throughout the project.
- DIt provides the specifics about how and why various project information will be distributed to stakeholders.
169In which of the following would the project manager document any concerns, disagreements, confusion, or unresolved questions that arise during the project?
- AStakeholder engagement assessment matrix
- BIssue log
- CWork performance report
- DStakeholder register
170Which part of the team charter outlines the behavioral expectations for the project team and other stakeholders?
- AGround rules
- BStakes
- CThe stakeholder cube
- DStakeholder register
171Which of the following is an input to Identify Stakeholders?
- AStakeholder register
- BChange requests
- CUpdates to the assumption log
- DProject charter
172Which of the following is true about the communications management plan and the stakeholder engagement plan?
- AThe communications management plan identifies the communications technologies that will be used, and the stakeholder engagement plan identifies the methods that will be used for specific stakeholders.
- BThe stakeholder engagement plan addresses the how of communication, while the communications management plan addresses the why.
- CThe stakeholder engagement plan needs to be completed before the development of the communications management can begin.
- DThe stakeholder engagement plan explains why stakeholders need to receive certain information, while the communications management plan explains the models of communication that will be used.
173One of the project stakeholders is an expert in the accounting processes that are at the core of the software being developed by the project team. What type of stake does this represent?
- AOwnership
- BKnowledge
- CInterest
- DContribution
174The team is in the process of assessing the engagement of their stakeholders and categorizing them as unaware, resistant, neutral, supportive, or leading. Which stakeholder management process is the team involved in?
- APlan Stakeholder Engagement
- BIdentify Stakeholders
- CManage Stakeholder Engagement
- DMonitor Stakeholder Expectations
175The team is analyzing data they have gathered about stakeholders and comparing it to their stakeholder engagement metrics. Which process are they engaged in?
- AIdentify Stakeholders
- BMonitor Stakeholder Engagement
- CManage Stakeholder Engagement
- DAnalyze Stakeholders
176All of the following are potential outputs of the Manage Stakeholder Engagement process except:
- AChange requests
- BUpdates to the issue log
- CExpert judgment
- DUpdates to the stakeholder engagement plan
177Which of the following statements best explains why it is important to identify all stakeholders on the project as early as possible?
- AThe stakeholder register should be continuously updated throughout the project.
- BChanges made later in the project are more expensive than those made earlier.
- CStakeholder engagement must be documented in the stakeholder engagement plan.
- DThe project manager is responsible for encouraging stakeholder support of the project and its outcome.
178In the project's power/interest grid, a stakeholder has been categorized as _________. Because of that, the project manager has identified ways to elicit requirements from the stakeholder as efficiently as possible and intends to get the stakeholder to approve those requirements to ensure their accuracy.
- AHigh influence/low interest
- BLow influence/high interest
- CHigh influence/high interest
- DLow influence/low interest
179Which stakeholder management process may result in change requests, updates to the project management plan, and work performance information?
- AIdentify Stakeholders
- BPlan Stakeholder Engagement
- CManage Stakeholder Engagement
- DMonitor Stakeholder Engagement
Información
- Descripción
- Test sobre Practice Exam, creado por Karolina Dubauskas el 26/02/2021.
- Autor
- Karolina Dubauskas
- Idioma
- English
- Visitas
- 7
- Etiquetas
- Valoración
- Aún sin valoraciones Valora este test