Test
Project Management Tools Quiz
Este test tiene tipos de pregunta que se abren en el reproductor de siempre.
Preguntas del test (10)
1A critical activity has...
- ANegative slack time
- BZero slack time
- CPositive slack time
2Critical path: The path of activities which represent the [blank_start]longest[blank_end] total time required to complete the project. A delay in an activity on the critical path causes a delay in the [blank_start]entire project[blank_end].
- Alongest
- Bshortest
- Centire project
- Dpreceding activity
- Eparallel activities
3Finish to start lag: The minimum amount of time that must pass between the [blank_start]finish[blank_end] of one activity and the [blank_start]start[blank_end] of its successor(s)
- Afinish
- Bstart
- Cfinish
- Dstart
4The variance in the project completion time can be calculated by [blank_start]summing[blank_end] the variances in the completion times of the activities in the critical path
- Asubtracting
- Bsumming
- Cmultiplying
5The normal distribution assumption holds if the number of activities in the path is large enough for the [blank_start]central limit theorem[blank_end] to be applied.
- Acentral limit theorem
6The following times for completion an activity have been estimated.
Optimistic time: 4 days
Most likely time: 7 days
Pessimistic time: 10 days.
The variance in the expected time is [blank_start]1[blank_end] days.- A1
7When preparing a Work Breakdown Structure, continue to subdivide components until the lowest level component requires between [blank_start]8[blank_end] and [blank_start]80[blank_end] hours of work.
- A8
- B80
8When components of a WBS are defined in sufficient detail for management and planning purposes, they are known as [blank_start]work packages[blank_end].
- Awork packages
9High level elements in the WBS should match, word for word, nouns used to describe outcomes in the [blank_start]scope statement[blank_end].
- Ascope statement
10The current activity has an Early Start of March 1st and a duration of 3 days.
The succeeding activity has an Early Start of March 7th. Assuming everyday is a work day, then the free float is [blank_start]3[blank_end] days.- A3
Información
- Descripción
- Quiz on project management
- Autor
- Niamh Ryan
- Idioma
- English
- Visitas
- 112
- Etiquetas
- Valoración
- 5,0 de 5 · 1 valoración Valora este test