  1. 1Planning Processgroup of processes used to develop the Project Plan (defines the activities, values of variables necessary to achieve fixed objectives )
  2. 2main purpose of planning......is to identify and define:
    - scope of project
    - timing
    - amount of resources
    - costs
    -risks
    -quality
  3. 3Project Plan-dossier that contains project charter, goals, costs, risk plan, ...
    --> dynamic document! we expect it to be changed
  4. 4baselinefirst official version of the project -> cannot be modified
    - requieren in order to analyze scope, cost variance
    - essential for measuring the performance
  5. 5Scope Statement-represents an insight of project charter that can be further developed (after requirements analysis )
  6. 6Work Breakdown Structure (WBS)- what has to be done
    -> i.e. breaking down the project scope into it elementary work units (Work Packages WP) -> assigned to a single person, accountable for the result -> Top Down Process
  7. 7PRO Arguments about WBS (Work Breakdown Structure)- smaller, easier-to-handel elements of entire project
    - strict, rational base for project planning and control
    - creates main reference point for communication, reporting
  8. 8WBS (Work Breakdown Structure) Dictionary- documents that describes each WP (Work Package)
  9. 9Product Breakdown Structure- structured representation of the project in terms of deliverables
    -> Top To Lower
    -> only includes physical elements of a product
  10. 10Project Resource Management- addressed to people trying to achieve projects goal and goods
    -> Initiation
    -> Planning
    -> Execution
    -> Control
  11. 11Organizational Breakdown Structure (OBS)-> WHO (who has which project responsibilities )
    -> represents the project organization decomposition
  12. 12Resposonsibility Assignment Matrix (RAM)-> crossing WBS ( what has to be done) with OBS ( who is doing what)
    -> WHO DOES WHAT
  13. 13RAM - Legenda- Responsible ( who do the work to achieve the task)
    - Accountable (delegates work to those responsible, sign off work that responsible provides)
    - Consulted ( subject matter experts, 2-way communication)
    - Informed ( up-to-date on progress, 1-way comm.)
    - Support ( help complete the task)
  14. 14Project time management- defining, planning and controlling time sequence of project activities
    -> Planning (define activities, estimate activity durations, develop schedule)
    -> Control (schedule)
  15. 15Project schedule network diagram- graphical representation of connected and sequenced activities
    -> purpose: identify logical relations between project activities ( in order to correctly execute and schedule the project)
  16. 16Dependencies- btw. activties are due to existence of different constraints (internal and external)
    -> Mandatory dependencies (hard logic): electronic project, prototype must be built before it can be tested
    -> Discretionary dependencies (soft logic): defined by management team
  17. 17Graphic representation of scheduling network- Precedence (Vorrang) Diagramming Method (PDM)
    - Arrow Diagramming Method (ADM)
  18. 18Precedence Diagramming Method (PDM)( activity-on-node AON)
    -using nodes (Knoten) to represent activities and connecting them through arrows, representing dependencies
    4 Types:
    Finish-to-start (most common)
    Finish-to-finsih
    Start-to-start
    -Start-to-finish
  19. 19Arrow Diagramming Method (ADM)(activity-on-arrow AOA)
    - arrows represent activates and connecting to nodes, to show dependencies
    only "finish-to-start"
  20. 20Estimate resources- determine the resources needed for each activity
    - defining: list of resources, amount, availability, unitary cost
  21. 21Types of project resources- People (work time, skill)
    - Facilities
    - Equipment
    - Materials
  22. 22Resource Breakdown Structure (RBS)- hierarchical chart of resources based on category and type definition
    -> optimize resource utilization, plan procurement (Beschaffung), account costs
  23. 23Estimate activity durations- determine the time required to complete each activity of the project
    -> deterministic ( vorher bestimmbar) or probabilistic (wahrscheinlich)
    Variables taken into account:
    Duration
    Total wohl
    Percentage of working time, allocated to the activity
  24. 24Activity durations estimating - Techniques- Expert judgement : guided by historical information
    - Analogous estimating (top down): using actual duration of previous, similar project
    - Parametric estimating ( statistical relationship btw. historical data and other variables )
    - Three point estimating ( applying average of optimistic,pessimitsic and most likely estimates)

Información

Descripción
Project Managemnt Fichas sobre Lesson 4, creado por odessa m el 30/09/2019.
Creado por
odessa m
Visitas
0
Valoración

Más sobre Work Breakdown Structure

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?