¡GoConqr estrena diseño! Cuéntanos qué te parece.

Mapa mental

1_SAB10#55_Estimate_Activity_Durations

Anyelo Chavez Español

1_SAB10#55_Estimate_Activity_Durations

Contenido del mapa

1_SAB10#55_Estimate_Activity_Durations

  • Estimate the necessary work according to the availability of resources
  1. Schedule Management Plan

  2. Activity List

  3. Activity Attributes

  4. Resource Calendars

  5. Resource Requirements of Activities

  6. Project Scope Statement

  7. OPAs

  8. EEFs

  9. Expert Judgment

  10. Analogous Estimating

    • Is when you look at activities from previous projects that were similar to this one and look at how long it took to do similar work before. But this only works if the activities and the project team are similar!
  11. Three-Point Estimates

    • Are when you come up with three numbers: a most likely estimate that probably will happen, an optimistic one that represents the best-case scenario, and a pessimistic one that represents the worst-case scenario. The final estimate is the average.
  12. Parametric Estimating

    • Means plugging data about your project into a formula, spreadsheet, database, or computer program that comes up with an estimate. The software or formula that you use for parametric estimating is built on a database of actual durations from past projects.
  13. Reserve analysis

    • Means adding extra time to the schedule (called a contingency reserve or a buffer) to account for extra risk.
  14. RBS

    • Create a hierarchical image that organizes the planned resources by their category and type (a resource breakdown structure)
  15. Project Document Update

    • Activity and Attributes List
    • Activity Duration Estimates
      • Includes not lag
  16. Risk Register

  17. Group Decision Techniques

    • Help the team decide on the best estimates for the activities they’ve defined.

Imágenes y archivos del mapa

  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations
  • 1_SAB10#55_Estimate_Activity_Durations

Información

Descripción
Mapa Mental sobre 1_SAB10#55_Estimate_Activity_Durations, creado por Anyelo Chavez el 07/05/2016.
Creado por
Anyelo Chavez
Visitas
7
Historial
  • Creado por Anyelo Chavez · 7 may 2016
  • Copiado por Anyelo Chavez · 7 may 2016
Valoración

Más sobre Estimating Activity Resources and Durations

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?