6) Construction Surveying

  1. Tertiary control

    • Sight rails
      • Monitor excavation
    • Batter boards
      • Control Slopes
    • Profiles
      • Define the corners&sides of buildings
  2. Area determination

    • Measurement of dimensions
      • Straight sided figures
      • Figures with irregular boundaries
        • Reduction to straight sided figures
    • Coordinates
      • Straight sided figure with n sides
        • Area=½(Y1X2+Y2X3+...+YnX1)-(X1Y2+X2Y3+...+XnY1)
  3. Volume determination

    • From dimensions formulae
    • Spotshots -grid of observation
      • v=A/V(Σsingle depths+2Σdouble depths+3Σtriple depths+4Σquadruple depths)
      • Trapezoidal rule
        • A=D/2(A1+A2+2A3+...+2An)
      • Simpsons rule
        • A=D/3(A1+An+4Aeven+2Aodd)
    • Contours
    • Prismoidal formula
      • V=D/3(A1+A5+4[A2+A4]+2[A3]
        • V=D/3[A1+An+4Aeven+2Aodd]
    • Simpsons rule for Volumes
      • Only applicable to an odd number of sections
      • V=d/3(A1+4A2+2A3+4A4+...+2An-2+4An-1+An)
    • End Areas
      • V=d/2(A1+2A2+2A3+...+2An-1+An)
  4. Mass-Haul diagramm

    • Drawn after earthwork quantities have been calculated
    • Directly below the longitudinal section of the surveyd center line
    • Shows accumulated volume at any point
      • Can find from it: distance over which cut&fill will balance, quantities of material to be moved and their direction, amounts, etc.

Información

Descripción
2nd year Construction Surveying Mapa Mental sobre 6) Construction Surveying, creado por Bianca Kring el 24/01/2017.
Creado por
Bianca Kring
Visitas
1
Valoración

Más sobre Areas, Volumes and Contours

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?