1The probability that a risk event will occur is higher during the initial stages of a project.
- AVerdadero
- BFalso
2Risk events that occur in the early stages of a project will have a greater cost impact than those that occur in later stages.
- AVerdadero
- BFalso
3Risk management is a reactive approach that is designed to ensure that surprises are reduced and that negative consequences associated with undesirable events are minimized.
- AVerdadero
- BFalso
4One common mistake that is made early on in the risk identification process is to focus on consequences and not on the events that could produce consequences.
- AVerdadero
- BFalso
5The project being delayed is an example of a major risk that should be assessed.
- AVerdadero
- BFalso
6The first step in the risk management process is risk assessment.
- AVerdadero
- BFalso
7A risk profile is a list of questions that have been developed and refined from previous, similar projects.
- AVerdadero
- BFalso
8The risk identification process should be limited to just the core project team.
- AVerdadero
- BFalso
9While a "can do" attitude is essential during implementation, project managers have to encourage critical thinking when it comes to risk identification.
- AVerdadero
- BFalso
10Responses to all identifiable risks should be a top priority for the project manager.
- AVerdadero
- BFalso
11When considering risk value, the lower the value, the higher the level of risk.
- AVerdadero
- BFalso
12If, during risk response development, you successfully identify how you will respond to a risk, contingency planning is unnecessary.
- AVerdadero
- BFalso
13Adopting proven technology instead of experimental technology is an example of mitigating a risk.
- AVerdadero
- BFalso
14A risk is an uncertain event that, if it occurs, can have a positive or negative effect on project objectives.
- AVerdadero
- BFalso
15Performance bonds, warranties, and guarantees are financial instruments used to share risk.
- AVerdadero
- BFalso
16Fixed-price contracts are an example of transferring risk from an owner to a contractor.
- AVerdadero
- BFalso
17When developing a response to a risk by scheduling outdoor work in the summer, investing in up-front safety training, or choosing high-quality materials, these are examples of retaining a risk.
- AVerdadero
- BFalso
18Budget reserves are set up to cover identified risks associated with specific segments of a project while management reserves are set up to cover unidentified risks associated with the total project.
- AVerdadero
- BFalso
19Change management systems involve reporting, controlling, and recording changes to the project baseline.
- AVerdadero
- BFalso
20Enhancing a risk is a tactic that seeks to eliminate the uncertainty associated with an opportunity to ensure that it definitely happens.
- AVerdadero
- BFalso
21Contingency funding is made up of budget reserves and management reserves.
- AVerdadero
- BFalso
22Although most risks are presented as something not desirable, there can also be desirable risks called Opportunities.
- AVerdadero
- BFalso
23Opportunities identified within a project are treated very differently from risks.
- AVerdadero
- BFalso
24Having an environment where identified risks are treated professionally will lead to better control of risks.
- AVerdadero
- BFalso
Información
- Descripción
- Test sobre CH 7 TF, creado por shamuz ALI el 04/11/2019.
- Autor
- shamuz ALI
- Idioma
- English
- Visitas
- 1
- Valoración
- Aún sin valoraciones Valora este test