PMP exam 6

Lê Hiếu 100 preguntas

Hacer el test

Preguntas del test (100)

  1. 1A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to water. What should the project manager do next?
    1. AHire local contractors who are familiar with the environment.
    2. BStart project planning and develop the project management plan.
    3. CFace the challenge immediately and start sending relief to the town.
    4. DProcess a change request for additional funding due to project urgency.
  2. 2A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials What should the project manager do next?
    1. AAsk the project sponsor to allocate more budget to cover the costs
    2. BUpdate the procurement management plan and negotiate with the contractor.
    3. CAsk the contractor to review the offer and reduce the costs.
    4. DUpdate the procurement strategy and negotiate with the contractor
  3. 3Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?
    1. ARemove the changes to match the original requirements.
    2. BAdd team members to the project to avoid more schedule delays.
    3. CEvaluate the impacts of the changes that were made to the project
    4. DUpdate project documentation with the new scope
  4. 4A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects. What should the project manager do next?
    1. ARefer to the previous protect they worked on and base the estimate on that
    2. BUse expert judgment to estimate the schedule and then adjust the schedule as the project progresses
    3. CAsk the project management office (PMO) by when the project can be completed and use that date as the project time line
    4. DBreak down the project into smaller tasks and estimate the durations of the activities
  5. 5A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
    What should the project manager do?
    1. AIntroduce a float.
    2. BAdjust the budget.
    3. CAdjust the project time line.
    4. DFast track the project.
  6. 6A business improvement opportunity to reduce energy usage has been identified.
    The project manager has assembled a team that includes site engineers to deliver this project.
    However, due to production imperatives, the site engineers may not be fully focused on the project.
    How should the project manager manage the team?
    1. ADevelop an approved responsibility assignment matrix (RAM) to confirm internal and external resource requirements.
    2. BCommit each team member's time and deliverables and aim for overall project completion.
    3. CContinue the project implementation without the site engineers to ensure the schedule is maintained.
    4. DContract external resources to fulfill the role of the site engineers who cannot support the project.
  7. 7A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project What should the project manager have the project team update to ensure proper communications to stakeholders?
    1. AProject management plan
    2. BStakeholder engagement plan
    3. CStakeholder register
    4. DCommunications management plan
  8. 8A predictive project team come across a scenario where they need to use some agile tools and methods.
    However, they did not feel this was appropriate since their organizational project management processes did not mention this.
    What should the project manager do in this scenario?
    1. AEnsure the project team follows the organizational project management processes.
    2. BCreate a change request to include the agile methods and proceed to implementation,
    3. CWork with the team to determine appropriate project methods and practices and implement them.
    4. DPrepare a summary and escalate this issue to the project's change control board (CCB),
  9. 9Drag the technical practices on the left to the scenario on the right.Imagen de la pregunta 9
    1. AĐáp ánImagen de la opción A
    2. BĐáp án ở trên
  10. 10A project manager is leading a project that is implementing an assembly line.
    During the quality review meeting, a team member reports an issue stating that the product being developed has discrepancies with the one requested by the customer.
    What should the project manager do?
    1. AEnsure the current solution is in place to enable future usability.
    2. BRun a root cause analysis to identify the quality breach and update the quality management plan.
    3. CCheck that the product meets the requirements established by the customer.
    4. DMake a proposal of new specifications and submit it to the customer for approval.

Información

Descripción
Công nghệ số Test sobre PMP exam 6, creado por Lê Hiếu el 24/07/2022.
Idioma
English
Visitas
32
Etiquetas
công nghệ số
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué deberíamos añadir?