1A project manager has been assigned to a project that involves building 100 wells for a small community that is urgently in need of access to water. What should the project manager do next?
- AHire local contractors who are familiar with the environment.
- BStart project planning and develop the project management plan.
- CFace the challenge immediately and start sending relief to the town.
- DProcess a change request for additional funding due to project urgency.
2A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials What should the project manager do next?
- AAsk the project sponsor to allocate more budget to cover the costs
- BUpdate the procurement management plan and negotiate with the contractor.
- CAsk the contractor to review the offer and reduce the costs.
- DUpdate the procurement strategy and negotiate with the contractor
3Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?
- ARemove the changes to match the original requirements.
- BAdd team members to the project to avoid more schedule delays.
- CEvaluate the impacts of the changes that were made to the project
- DUpdate project documentation with the new scope
4A project manager primarily works on implementation projects Depending on the deliverable, the project manager is able to estimate the time line based on previous projects. The project manager now receives a project that is different from the previous implementation projects. What should the project manager do next?
- ARefer to the previous protect they worked on and base the estimate on that
- BUse expert judgment to estimate the schedule and then adjust the schedule as the project progresses
- CAsk the project management office (PMO) by when the project can be completed and use that date as the project time line
- DBreak down the project into smaller tasks and estimate the durations of the activities
5A project manager is assigned to a critical software development project. The team is using a hybrid approach and has divided development into four sprints. At the end of sprint three, the project manager discovers that the earned value (EV) is US$500,000 and the planned value (PV) is US$550,000.
What should the project manager do?- AIntroduce a float.
- BAdjust the budget.
- CAdjust the project time line.
- DFast track the project.
6A business improvement opportunity to reduce energy usage has been identified.
The project manager has assembled a team that includes site engineers to deliver this project.
However, due to production imperatives, the site engineers may not be fully focused on the project.
How should the project manager manage the team?- ADevelop an approved responsibility assignment matrix (RAM) to confirm internal and external resource requirements.
- BCommit each team member's time and deliverables and aim for overall project completion.
- CContinue the project implementation without the site engineers to ensure the schedule is maintained.
- DContract external resources to fulfill the role of the site engineers who cannot support the project.
7A project manager is leading a project with several stakeholders in other functional areas of the company One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project What should the project manager have the project team update to ensure proper communications to stakeholders?
- AProject management plan
- BStakeholder engagement plan
- CStakeholder register
- DCommunications management plan
8A predictive project team come across a scenario where they need to use some agile tools and methods.
However, they did not feel this was appropriate since their organizational project management processes did not mention this.
What should the project manager do in this scenario?- AEnsure the project team follows the organizational project management processes.
- BCreate a change request to include the agile methods and proceed to implementation,
- CWork with the team to determine appropriate project methods and practices and implement them.
- DPrepare a summary and escalate this issue to the project's change control board (CCB),
9Drag the technical practices on the left to the scenario on the right.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
10A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product being developed has discrepancies with the one requested by the customer.
What should the project manager do?- AEnsure the current solution is in place to enable future usability.
- BRun a root cause analysis to identify the quality breach and update the quality management plan.
- CCheck that the product meets the requirements established by the customer.
- DMake a proposal of new specifications and submit it to the customer for approval.
11A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond’?- ANegotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance
- BDiscuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework
- CRecord the issue in the issue log and escalate the conflict to the project sponsor for assistance
- DExplain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews
12A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer. What should the project manager ask the team to do?
- APerform collaborative work that is coordinated by the project manager.
- BRely on the expert judgment of the product owner.
- CUse a market-based strategy.
- DEngage the project sponsor.
13During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project manager is not sure if some of the project deliverables will be fully compliant with the new requirements.
What should the project manager do?- AStop the project until someone in the organization can identify all the new requirements and how they impact the project.
- BRequest the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reaction time.
- CAgree with the project team that the new requirements will be applied to the next project, not the one already under development.
- DEvaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.
14A self-organizing team was delivering as committed. The team accepted a development task with new technology and the iterations started to have reduced velocity. What management decision is suited for this situation?
- AProvide opportunity for team members to learn and adjust to the technology.
- BMove team members who are not performing from the team.
- CAdd new members to the team and increase the velocity
- DRe-assign the project to a team that has worked with this technology
15A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.
What should the project manager do?- AEscalate the team member's disruptive behavior to their functional manager.
- BCollaborate with the team to arrive at team ground rules and publish the rules to the team.
- CObserve to ensure this typical forming stage behavior does not escalate beyond what is acceptable.
- DRequest team members document their decisions independently and share with each other.
16At the end of the last iteration, the customer rejects the deliverables since they did not meet the customer's expectations. What should the project manager have been done to prevent this situation?
- AInvolved the customer more in the planning process for the project, and ensured agreement on the proceedings.
- BIncluded all relevant criteria in the agreed upon definition of done (DoD), and crafted a shared product vision.
- CProvided the customer with the backlog and the specified user stories at the beginning of the iteration.
- DDeveloped the DoD in close cooperation with all stakeholders to ensure their expectations were included.
17The project manager is having difficulty communicating with one of the team members The team member recently attended a training course and has been training other team members in a new agile technique However sometimes the team member is forceful in pushing ideas even if other team members are uncomfortable What personality indicators should the project manager consider when determining what communication style to use with this team member?

- AĐáp án

- BĐáp án ở trên
- AĐáp án
18A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?- AReview the requirements on a weekly basis.
- BImplement a requirements traceability matrix.
- CAdd the requirements to the project charter.
- DUnderstand the project management plan.
19A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project How should the project manager report this cost?
- AEstimate user story points and forecast a budget for that deliverable
- BDetermine the control accounts and use a top bottom estimate
- CConsider the cost performance index (CPI) based on earned value (EV) divided by costs
- DCalculate the budget at completion (BAC) based on the completed and planned features
20A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.
What should the project manager do?- AExplain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule
- BDocument who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report
- CExplain to the project sponsor that they are accountable for tracking benefits realization after project completion
- DDiscuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)
21An organization is transitioning to agile and a project has been chosen as a pilot The assigned project manager only has experience using predictive approaches but the project manager is now required to use agile approaches with the help of an agile coach During the retrospective of the fifth sprint, the project team complains that many obstacles exist with the organization that are creating project delays and rework What should the project manager do in this situation?
- AInclude impediment resolutions during daily standup meetings
- BPerform a root cause analysis during the standup meetings
- CCreate a dedicated sprint to solve the obstacles with the team
- DPromote collaboration to help remove the obstacles for the team
22A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?
- AEnsure full participation of both the product owner and business SMEs in scope planning sessions.
- BIdentify virtual communication methods and arrange for regular team meetings accordingly.
- CExplore the opportunity to have both teams colocated.
- DPlan for frequent face-to-face meetings.
23An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.
What should the project manager do?- ARecommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.
- BPropose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex items.
- CMaintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.
- DUpdate the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define the project scope.
24A project involves exporting 150 packages to the customer. However, only 30 packages have been cleared by the customer for shipment. The logistics manager provided details to the customer 2 weeks ago and set up a weekly conference call to effectively communicate with them, but the customer has not been participating in the calls.
How should the project manager handle this situation?- ARequest a change in the contract to include the shipment in the project management plan.
- BFind the root cause of the issue and discuss the customer's current engagement.
- CInform the customer that subsequent packages cannot be manufactured.
- DRequest a delivery date extension from the customer
25A project manager is about to slant the testing phase of a new project. Historical data show there is a high risk of failing the agreed acceptance criteria.
How should the project manager ensure the acceptance criteria are ret?- APerform tests and routinely track results as per the quality management plan.
- BMake sure the stakeholders are aware of the acceptance criteria.
- CNegotiate to obtain approval if most of the tests have passed.
- DModify the acceptance criteria before the official delivery.
26A company is transitioning projects from a predictive to an agile approach. The CFO is concerned that one of the agile projects has an important feature for the financial department that is being delayed for a later iteration.
What should the project manager do to clarify the situation?- ACreate an executive board to review the product backlog and replan the next iterations.
- BClarify with the CFO that the prioritization process is based on business value.
- CRequest support from the CEO on how to deal with the situation.
- DIncrease the size of the team in order to match any prior expectations of the CFO.
27A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new Hems Match the risks on the left Io the correct category on the right.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
28An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?- ARequire that all team members be physically present for the weekly project review.
- BOffer the team member an incentive to stay until the end of the project.
- CReplace the team member with someone who has similar qualifications and is located closer
- DSet up a weekly video conference to monitor the progress of the team member's work.
29A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?
- AAccept the change and use contingency funds to implement this change with minimal schedule impacts
- BReject the change because it is contrary to what was agreed to during earlier phases of the project
- CTransfer the change to the steering committee for them to evaluate and decide the appropriate next steps
- DEvaluate the proposed change with integrated change controls and discuss the change with the project sponsor
30A junior team member escalates an issue to the project manager about another member's interpersonal skills causing the team to be less effective.
What should the project manager do first?- AHave the team members resolve the issue on their own.
- BHighlight the impact of their behavior and motivate the team member to make improvements.
- CGather information and find the root cause of the problem.
- DDocument the escalated issue and address it at the end of the project.
31A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.
What should the project manager do to help the team and the customer?- AManage the risks associated with the proposed approach.
- BAssist the team with identifying the minimum viable product (MVP) to validate assumptions.
- CCoordinate with the business unit to get detailed requirements.
- DWork closely with the marketing team on market research and product segments
32A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.
What is the first thing the project manager should do"?- AInclude the requirement into the project and schedule it as soon as possible
- BInform the project sponsor about the situation and request assistance
- CEvaluate the impact that the inclusion of this new requirement will have on project performance
- DInform the stakeholder that it is impossible to add new requirements to an approved project scope
33A new project manager for an agile project is reviewing with an established team, some of the roles to avoid confusion on what to expect. Drag the description on the left to the role on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
34An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?
- ALaissez-faire
- BTransactional
- CTransformational
- DCharismatic
35A few developers have submitted their resignation after completing their annual review and receiving their annual bonus. The project manager cannot find replacements for all of the developers in time to meet the project's deadline.
What should the project manager do?- ARequest additional budget to recruit more developers.
- BLower the recruitment criteria.
- CLog the issue in the issue log.
- DAnalyze the impact and inform the stakeholders.
36During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred What should the project manager do to address this issue?
- ABook one-on-one meetings with the team members who are not speaking up during the daily meetings to get their updates
- BCheck the ground rules of the meeting to review the initial agreement with the team members
- CIdentify one team representative to speak up during the daily meeting and share the team updates
- DUse round-robin check-ins to facilitate the meeting so all participants have the opportunity to speak
37A project manager has experience working with a specific provider that has been requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?- AHire resources to obtain knowledge about the provider's specific capabilities.
- BAdd penalty clauses to the contract and update the risk register.
- CEncourage the provider to work overtime with no additional costs to the project.
- DContract another provider with less experience and give them a chance to provide the deliverables.
38A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution.
The project manager must assess and prioritize the impact of these changes on the project scope/backlog.
Which analytical tool can be used by the project manager to define this scenario?- APolitical, economic social, technological legal, and environmental (PESTLE)
- BStrengths, weaknesses opportunities, and threats (SWOT)
- CValuable rare, inimitable resources, and organization (VRIO)
- DNet present value (NPV)
39A research and development department is planning to develop a product that will introduce a new line of business for the organization What should the project manager do to increase the project's chances of success?
- APlan a working session focusing on the scope, vision, and mission of the initiative
- BStart developing the project management plan based on a previous project template from the project management office (PMO).
- CConduct benchmarking to determine the business viability of the initiative
- DConduct an impact analysis of the new initiative to determine how the project should be rolled out
40During the execution of a maintenance project the contractor submits an offer for additional work The project manager realizes that the activities billed are included in the initial scope of work. What should the project manager do next in this situation?
- AReview the project scope and negotiate with the contractor
- BRefuse the offer as it is included in the initial project scope
- CReview the project costs and communicate this to the project sponsor
- DSubmit a change request to approve the offer
41A vendor informed the project manager that a critical resource will be on a long leave of absence The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost The project is currently on schedule and slightly under budget What should the project manager do next?
- ARequest a replacement resource
- BPerform a cost-benefit analysis
- CImplement risk responses
- DPerform Integrated Change Control
42A project team is having difficulties understanding technical details regarding requirements The information was not initially provided by the customer, but the information is critical in the current iteration for clarification on how tasks need to be accomplished How should the project manager approach this situation?
- ARequest that the customer reviews and clarifies feature definitions for the current sprint
- BSend a burndown chart of the current sprint to the customer and seek clarifications.
- CEducate the customer and have them participate in daily standup meetings.
- DSchedule weekly meetings and product reviews with the customer to clarify requirements
43Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.
What should the project manager do?- AAsk the contractor to solve this problem because this is a contractual obligation.
- BTerminate the contract and initiate a new one with a local contractor.
- CImplement key performance indicators (KPIs) and convince the contractor to engage the team.
- DReassess continually to remove blockers for the team.
44At the end of planning a new project, the project manager needs to schedule the kick-off meeting but is having difficulty finding a common time slot when all necessary stakeholders can be available onsite. How should the project manager proceed to schedule the kick-off meeting?
- AEmail all stakeholders with the objectives of the project and ask for feedback.
- BWait for a date when all required attendees can be available onsite.
- CRun separate meetings to accommodate everyone's schedule.
- DSchedule a virtual meeting so onsite and remote stakeholders can attend at the same time.
45A project manager is executing a project where an external vendor will provide some deliverables Alter awarding the contract to the vendor the project manager is informed that the vendor is running behind schedule on a separate project Finding another vendor will exceed the budget What should the project manager update first?
- AIssue log
- BLessons learned register
- CStakeholder engagement plan
- DRisk register
46The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action What two actions should the project manager take’? (Choose two)
- ADiscuss with the construction team alternatives on moving the new train station to another location.
- BPublish information on the city's website about the benefits that the new tram station will bring
- CHave a meeting with the mayor and explain the importance of the new train station to the city.
- DConduct regular meetings with the neighbors to get their buy-in for the project
- ERegister this situation as a risk and develop a mitigation plan
47A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concern- AProvide team-building activities so that the team can learn how to overcome disruptive behavior
- BInform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately
- CRequest a meeting with the disruptive team member and help to resolve the issue
- DEncourage self-governance and ask the concerned team member to speak to the disruptive team member directly
48In a newly formed project team one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
- AAsk the team member to enter this potential schedule delay in the risk register.
- BExplain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges
- CActively listen to the team member and identify ways to support their needs in completing the tasks.
- DSet up team-building activities with the project team members to reduce tension
49A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
- AAcquire project resources from the new country to mitigate the risk of uncertainty
- BEvaluate the environmental and regulatory factors and identify high-level risks and assumptions
- CIdentify and monitor the risks closely since the company does not have lessons learned for this country.
- DEnsure that project sponsors are in agreement on the project deliverables and timeline during the project
50A project team is executing a megaproject, and several contract requirements have been identified. In the planning phase, the project team agreed that a contract would be required 3 months prior to the project's finish date. During project execution, it was determined that the contract was required immediately.
What should project manager do?- ASeek management's approval for executing the contract earlier than planned.
- BRequest the team to initiate a change request to execute the contract.
- CSupport the team's request and allow for early contract execution.
- DChallenge the project team to identify the reasons for early contract execution.
51A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.
What should the project manager do?- AContact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team
- BEscalate the issue to the functional manager
- CHelp the team member to perform the quantitative risk analysis through coaching, mentoring and training
- DPerform the quantitative risk analysis for the team member.
52A project manager in an automotive company is scheduling activities for a complex project Some of the project requirements are fixed and some are flexible Match the items on the left with the methodology on the right that the project manager is using.

- AĐáp án

- BĐáp án ở trên
- AĐáp án
53A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter What should the project manager do?
- AModify the baseline of the project for minor impact changes to the project scope
- BUse a focus group and brainstorming sessions to gather more details about the project scope
- CRegister the changes in the configuration management plan and send it to the change control board (CCB).
- DExplain to the sponsor that these requests could endanger the schedule and cost of the project
54A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponsor expressed concerns about the low quality of the product, What should the project manager, as a servant leader, do to address this situation?
- ADedicate the next sprint to completing the missing details.
- BApply fast-track techniques to work on the missing details in parallel,
- CContinue iterating and monitoring quality aspects sprint by sprint.
- DCreate a new risk entry for the delay in the risk management plan.
55A customer calls the project manager to express concern about a project team member who has been making changes within the live environment without approval. The team member mentioned that the customer called and asked them to make the changes.
What should the project manager do next?- AReinforce the value of documenting and approving all change requests and ask the customer to issue these through the agreed channels.
- BOrganize a meeting to mediate the relationship between the customer and the team member to ensure no feelings are hurt.
- CAsk the customer to email all requests directly to you and you will ensure they are actioned by the correct team member.
- DExplain to the customer that the team member was just trying to help and the changes can be reverted if necessary.
56A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?
- ADraft a project decision request to include in the scope for the current iteration and ask the sponsor to approve.
- BExplain that the team is fully dedicated to the current sprint activities and negotiate a mutually agreeable time.
- CAdd this to the project backlog and have the product owner determine where it fits in terms of priority.
- DIndicate that this was a not a requirement identified during project planning and it is outside of the scope.
57Drag the to the correct scenario on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
58A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer.
What should the project manager do?- AAsk the team member to submit a formal change request.
- BAccept the suggestion as it has no impact on the project.
- CAsk another team member to validate the impacts of the suggestion.
- DReject the suggestion and ask the team member to focus on executing the plan.
59An agile team has released the second version of its product, but the feedback is that the software has many bugs that compromise the user experience. What should the project manager do?
- AFacilitate the next retrospective meeting, focusing the team on analyzing root causes and proposing solutions.
- BClosely evaluate the skill set of the team, looking for technical gaps that need to be filed in order to improve quality.
- CHire an external consultancy firm to focus on testing and quality control to avoid the issue in the future.
- DPropose an internal program that offers incentives for the team members who find and fix bugs.
60A company is transitioning from a predictive to agile delivery of projects. Based on the requirements, the project team estimates the budget and decides to use a fixed-price contract with its vendor. However, during the execution of the project, the requirements evolve and priorities start to change constantly, which puts the project and the estimate at completion (EAC) off by 40%.
What should the project manager do next?- ASend a detailed status report highlighting the issue with funding to all of the stakeholders
- BSubmit a change request to the financial manager to increase the funding and continue as is.
- CMeet with the stakeholders to recommend the use of a time and materials (T&M) contract to address the problem.
- DWait until the next gate review meeting to highlight the risk of low funds to the stakeholders.
61A project has a very tight delivery schedule The project is approaching the delivery date and the project sponsor often sends the project manager alerts to avoid any schedule slippage The project team has performed at an acceptable level until now but the project manager wants to ensure the team's performance level is maintained until the end What action should the project manager take to motivate the project team's performance?
- ASend a formal notice to team members instructing them to maintain performance
- BHire a few temporary team members to help with the additional work
- CAward certificates of appreciation to encourage the team
- DInform the team about the delivery pressure from the project sponsor
62A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The engineering executive wants to prioritize features based on level of effort, completing the smallest items first.
The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?- AComplete tasks associated with regulatory components as the team cannot deliver business value that does not adhere to compliance regulations.
- BEnsure that the team assesses opportunities to deliver the highest business value items incrementally
- CEnsure that the project value is within the quality guidelines by prioritizing and completing intricate tasks earlier in the project.
- DComplete the smaller tasks first to allow the team opportunities to prototype and evaluate development processes.
63A project manager has been hired to help coordinate an ongoing project Historically the biggest problem as reported by the company's CEO is that the change request process has been handled by managers who did not have dear information on the project schedule and budget. This information has been inconsistent and handled by finance, risk. and functional subject matter experts (SMEs) What should the project manager do to control this situation?
- ARedefine the communications management plan
- BDevelop an integrated change management plan
- CDocument the risk in the project risk register
- DReview the scope defined in the project charter
64During a project's initiation phase a lessons learned sharing session was held with the team from another project Low construction productivity was discussed as a potential delay to project completion What should the project manager do next?
- ADiscuss this issue with the project sponsor to request additional funding to implement mitigation
- BHire a construction management consultant to develop a comprehensive site execution plan
- CPrequalify contractors with proven track records to eliminate productivity concerns
- DAdd construction productivity to the risk register and develop a mitigation strategy for site execution
65A contract has fust been awarded for an automation project that was supported by the local community. The project manager was warned by the elected officials that the project cannot proceed.
Why did this action occur?- AInadequate funds for the automation project
- BInadequate engagement of the political stakeholders
- CLack of competence to manage the automation project
- DLack of a proper legal framework in place
66A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)
- ARisk steering committee
- BFunctional managers
- CBoard of directors
- DAdvisory team panel
- EChief executive officer
67A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team's performance level is performance is maintained until the end.
What action should the project manager take to motivate the project team's performance?- AAward certificates of appreciation to encourage the team
- BInform the team about the delivery pressure from the project sponsor
- CSend a formal notice to team members instructing them to maintain performance
- DHire a few temporary team members to help with the additional work.
68Drag the characteristics of the stage on the left to the correct Tuckman Ladder stage on the right

- AĐáp án

- BĐáp án ở trên
- AĐáp án
69A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The remote team member feels they are not being adequately rewarded and recognized for their job.
What should the project manager do?- AInform the human resource (HR) manager of this situation and ensure this news does not spread.
- BMake arrangements with the resource's functional manager to relocate the team member to another existing project.
- CSend a copy of the engagement contract to the remote ber and indicate that the team member is entitled to what is included in the contract.
- DEngage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.
70A project manager is managing an internal project that was poorly defined. Recently, the project manager received several change requests raised by the organization's upper management.
What should the project manager do first?- AReview the benefits of the proposed changes in relation to the business case.
- BAssess the time overrun, and start implementation to avoid additional delays.
- CRequest a provisional budget increase to avoid any budget overruns.
- DMotivate the team to avoid the frustration of working on a prolonged project.
71The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
- AReschedule the project execution date.
- BContinue project execution using the current blueprints from the client.
- CEscalate this issue to the project sponsor
- DConsult with the client to determine if project execution should be continued.
72A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict schedule and budget, and the project manager is concerned about their ability to deliver it. What should the project manager do?
- ARequest a budget extension to get local resources experienced in agile.
- BPlan to have the agile resources temporarily relocate to the project manager's location.
- CEngage the agile resources through video conferencing on a daily basis.
- DAdvise the sponsor that the project will be delayed as agile training will be required.
73A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?
- AFollow the risk response plan
- BUse the contingency fund
- CPrepare a change request
- DUpdate the risk register
74A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment.
The project manager started communication with the team to move the project forward What should the project manager do first at this pomp- AMeet with the quality planning manager to identify the reason why the quality plan was not created yet
- BMeet with the hardware design engineers to identify the minimum performance required to establish a market for the machine
- CMeet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers
- DMeet with the key stakeholders to identify the proper product concept for the development team
75During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?
- AAdd the stakeholder details into the periodic reports and update the project management plan
- BInvite the stakeholder to all future project review meetings and update the project management plan
- CUpdate the project management plan with the new information and inform all of the relevant stakeholders
- DMeet with the stakeholder to better understand their expectations and update the stakeholder engagement plan
76A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
- AUpdate the project management plan in order to get back on track.
- BEnsure the team receives continuous feedback from customers users.
- CSubmit a change request to adjust the project scope.
- DEnsure the team understands all additional project requirements.
77A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te... that another team is working on a product that could work as a solution, but it is still a prototype What should the project manager do to accelerate this solution?
- AContact the other project team and ask them to organize a demo of the prototype
- BPerform iterative planning with the team to use the prototype
- CCheck the burnup charts to see what progress has been made to integrate the solution
- DPrioritize the backlog with the customer to remove the feature
78The testing backlog for a hybrid project has increased significantly and is becoming a bottleneck. The team has researched a tool that could resolve the bottleneck, and the project manager has been informed.
What should the project manager do next?- AAdd developers to remove the backlog.
- BEscalate the issue with the product owner.
- CReduce the testing scope of the backlog.
- DEnroll team members in training on the tool.
79A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?- AAssess the impact of the stakeholder and engage properly.
- BEscalate the stakeholder issue to the project sponsor.
- CDevelop a specific communications strategy for this stakeholder.
- DUse interpersonal skills to gain stakeholder engagement.
80A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?
- AAdd the situation to the project risk register to be managed
- BIdentify competitors that are qualified to replace the current supplier
- CInform the purchasing department that manages the supplier relationship
- DUse the issue log to record the situation immediately
81A project manager is working directly with a vice president who is also the project sponsor. The project is an organizational transformation for a company that primarily works on predictive projects. The project manager has been asked to use a hybrid approach to deliver before a defined date by using sprints.
What should the project manager do first?- AFormalize the product owner assignment.
- BReview similar projects in the company.
- CSet the project's purpose, mission, and vision.
- DCarry out the product backlog creation.
82A project manager is assigned to a new project. The project management office (PMO) and the project manager agree that this is the right opportunity to include daily standup meetings. The project team has never used such tools, and a few members are challenging the decision.
What should the project manager do in this situation?- AEngage an external vendor to perform the design phase under an iterative approach.
- BRequest that new team members familiar with iterative approaches be assigned to this project.
- CUpdate the project schedule to consider a daily standup as part of the project design phase
- DDefine the ground rules, responsibilities, and conflict management strategies.
83A protect manager has just finished planning for a project when the client adds a new project team member The project manager Knows that the new team member only works remotely and is not in the main office. In addition, the new team member engages with decisions quickly in a face-to-face environment, but is slow to respond otherwise.
How should the project manager reflect this in their planning?- ASend out recurring onsite project meeting invites to ensure the team member's presence.
- BUpdate the project charter to include the new team member for this project.
- CMonitor the new team member's input to gauge their value to the project.
- DInclude the team member in the stakeholder register and update the communications management plan.
84A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?- ACoordinate with team members to define and communicate ways of working, roles and responsibilities, scheduling, time zone, and cultural observance information.
- BExplain to the team that since they are all SMEs and know one another, they are expected to immediately collaborate and deliver effectively.
- CUpdate the communications management plan and determine an issue resolution process for when future conflicts arise.
- DColocate the team members at the beginning of the project to explain the expectations for team interaction, meeting schedules, and overall project governance.
85A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became concerned that the product quality will be sacrificed.
What should the project manager do?- AEnsure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.
- BInvite the customer to join the daily standup meetings to better understand the product design and progress.
- CEnsure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.
- DInvite the customer to join the regular sprint planning sessions to better understand the project's progress.
86In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet What should the project team have done to avoid this issue?
- AHeld a touchpoint with marketing before the demo to discuss any impediments
- BScheduled a demo presentation of the product during the first reason
- CAsked the marketing team to start working on the product immediately
- DConfirmed marketing requirements and constraints when adding to the backlog
87A project manager is meeting with the project sponsor regarding a new project.
The project manager tells the sponsor that, as part of the communications management plan, a weekly email will be sent with the status of the project, so the sponsor can be informed of the progress. The sponsor indicates that the email is not necessary because they will ask for a status update whenever it is needed.
What should the project manager do next?- AAdvise the project sponsor to request a 15-minute meeting, whenever necessary, with prior notification.
- BAgree to the project sponsor's request, but continue to copy them on the weekly email so they can be informed of progress in case it is needed.
- CTell the project sponsor that if they prefer to not receive the communication, there is no problem in removing them from the email distribution.
- DAsk the project sponsor what sort of information is needed and agree on a frequency for the communication.
88A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?- ASet up a meeting with key stakeholders to clarify requirements
- BEscalate to the project steering committee and request additional time
- CTravel to the development team's office to push the schedule
- DCreate prototypes with the development team to confirm requirements
89An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.
What should the project manager recommend?- ATime-boxed iterations to allow the testing team to thoroughly test the product increments
- BIncremental delivery and frequent backlog refinement based on user feedback
- CIterative development and collection of frequent feedback from project team members
- DFrequent retrospectives to ensure that lessons learned and improvement actions are implemented
90A project team with a tight schedule has succeeded in maintaining a schedule performance index (SPI) of the through regular daily standups and overtime, when required After a few months the project manager notices that some of the team members' performance has decreased but mat the overall project team performance is still ahead of schedule by a few days What should the project manager do first to maintain the project team's performance level?
- AInitiate a performance-based bonus for the team members to provide them with a monetary incentive
- BRemind the team frequently that the project must be delivered on time and within budget
- CInvite the team to a team-building event to alleviate their stress while strengthening teamwork
- DProvide routine mentoring and coaching to the team members to identify any demotivating issues
91A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?- AConsult the previous project manager to discuss how they managed these questions.
- BEnsure all engineers are aware that questions should only be submitted in their weekly reports.
- CEmail the company vision to the engineers and tell them they need to meet deadlines
- DReinforce to all engineers the company vision of a safety-first approach to project activities
92A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?- AOrganize a conference call with the internal expert and the client to estimate the amount of effort required to fix it.
- BDecline the request politely since the issue, although critical, is not the responsibility of the project team.
- CAllocate a task to the team member as a high priority and inform the customer that the issue will be resolved the next day.
- DInform the customer that they should contact the sales manager and submit a formal request for a quote.
93The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?
- AAsk the vendor to identify the stakeholders affected, create an action plan and determine an implementation date
- BDraft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable
- CIdentify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.
- DContact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation
94A team is working on implementing a communications system when the client says that they are considering closing the project. The project manager schedules an urgent meeting with the client to understand why the project is at risk Which two tools or techniques can the project manager use to influence the client's decision to keep the project active? (Choose two)
- AAlternatives analysis
- BVoting
- CCost-benefit analysis
- DMulti-criteria decision making
- EAutocratic decision making
95A project manager in one country is reporting to a lead project manager for a new software development project in another country. The lead project manager constantly requests updates from the project manager, often demanding information via multiple communication channels if the project manager does not respond within a few minutes of a request. Both of them are equal in seniority and both report to the same functional manager.
How should the project manager proceed?- AUpdate the communications management plan and the stakeholder engagement plan.
- BEscalate the issue to the functional manager and explain the situation to them.
- CNegotiate a mutually agreeable feedback cycle with acceptable timelines.
- DRefer the lead project manager to the communications management plan.
96A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?- ACalculate the payback period (PBP) for building a new branch in each location versus renting an existing building.
- BCalculate the costs for each option in each location and compare the net present value (NPV) for each.
- CPerform a Kano analysis on building a new branch versus renting in each of the locations.
- DPerform a gap analysis on renting in each of the locations.
97A project manager has been assigned to a project where collaboration with the business is a critical key factor.
The project manager is not sure about which approach to use. A senior project manager has been assigned to help the project manager.
What advice should the senior project manager provide?- AProvide a project management template for the project manager to follow as a guide.
- BSuggest using an agile approach since customer and team collaboration is critical for project success.
- CWork with the project manager to develop a new approach that will bring benefits to the project.
- DEstablish a project management methodology that requires the customer to provide daily updates to the team.
98A project manager is appointed to simultaneously deploy a new solution to branches located in different countries Deployment teams in each country will integrate and deploy the solution. The project manager discovers that the deployment teams each encounter similar issues However, each team addresses the issues separately What should the project manager do to help ensure more collaboration between the teams?
- AOrganize regular meetings with all of the deployment teams to share issues and solutions
- BPropose that some of the teams delay deployments in their countries
- CAsk the project sponsor to appoint new managers for the deployment teams
- DAsk each deployment team to provide a very detailed schedule and action plan
99A new team member is assigned to a team that consistently delivers each iteration. The new team member is does not understand many of the processes followed and begins to negatively impact the schedule.
What should the project manager do?- APlace the new team member on a performance improvement program.
- BAsk another team member to take some of the new team member's work.
- CAssign easier activities to the new team member.
- DAllocate time within the iterations to mentor the new team member.
100During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented m the lessons learned. What should the project manager do?
- ACheck with the team to learn what can be done, and consult an expert
- BAsk the sponsor to close the project and pay the contracted penalty.
- CCheck that this information was documented corrects
- DMeet with the sponsor to ask for their support
Information
- Description
- Công nghệ số Quiz on PMP exam 6, created by Lê Hiếu on 24/07/2022.
- Author
- Lê Hiếu
- Language
- English
- Views
- 33
- Tags
- Rating
- No ratings yet Rate this quiz