  1. 1Preceding activities are those that must occur before others can be done.
    1. AT/F
    2. BAnswer: TRUE
  2. 2A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
    1. AT/F
    2. BAnswer: FALSE
  3. 3A merge activity has two or more immediate predecessors.
    1. AT/F
    2. BAnswer: TRUE
  4. 4Float is always measured in exactly the same way as slack.
    1. AT/F
    2. BAnswer: TRUE
  5. 5The PERT technique assumes that durations are more deterministic
    1. AT/F
    2. BAnswer: FALSE
  6. 6Burst activities are those with two or more successor activities.
    1. AT/F
    2. BAnswer: FALSE
  7. 7You must know the mean of an activity in order to determine its standard deviation.
    1. AT/F
    2. BAnswer: FALSE
  8. 8In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
    1. AT/F
    2. BAnswer: TRUE
  9. 9The late start time should be calculated using a forward pass through the network.
    1. AT/F
    2. BAnswer: FALSE
  10. 10Negative float exists when a project's critical path has been completed more quickly than anticipated.
    1. AT/F
    2. BAnswer: TRUE

Información

Descripción
Project Mngt Chapter 9 Test Questions
Idioma
English
Visitas
10.302
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?