Project Mngt Chapter 9

damimgd2u 60 questions 10,302 views

Take the quiz

Questions in this quiz (60)

  1. 1Preceding activities are those that must occur before others can be done.
    1. AT/F
    2. BAnswer: TRUE
  2. 2A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.
    1. AT/F
    2. BAnswer: FALSE
  3. 3A merge activity has two or more immediate predecessors.
    1. AT/F
    2. BAnswer: TRUE
  4. 4Float is always measured in exactly the same way as slack.
    1. AT/F
    2. BAnswer: TRUE
  5. 5The PERT technique assumes that durations are more deterministic
    1. AT/F
    2. BAnswer: FALSE
  6. 6Burst activities are those with two or more successor activities.
    1. AT/F
    2. BAnswer: FALSE
  7. 7You must know the mean of an activity in order to determine its standard deviation.
    1. AT/F
    2. BAnswer: FALSE
  8. 8In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.
    1. AT/F
    2. BAnswer: TRUE
  9. 9The late start time should be calculated using a forward pass through the network.
    1. AT/F
    2. BAnswer: FALSE
  10. 10Negative float exists when a project's critical path has been completed more quickly than anticipated.
    1. AT/F
    2. BAnswer: TRUE

Information

Description
Project Mngt Chapter 9 Test Questions
Author
damimgd2u
Language
English
Views
10,302
Rating
No ratings yet
Rate this quiz
Rate this quiz

Feedback

What is it about?

What do you think of the new look?

How do you like it?