1Scope creep occurs when your project is completed over-budget.
- AVerdadero
- BFalso
2There is a strong correlation between project success and clear project scope definition
- AVerdadero
- BFalso
3Project scope describes what you expect to deliver to your customers when the project is complete
- AVerdadero
- BFalso
4One of the items included on a project scope statement or checklist is the review with the customer
- AVerdadero
- BFalso
5An expected output over the life of a project would be classified as a target
- AVerdadero
- BFalso
6An activity that represents a major segment of work is a good example of a milestone
- AVerdadero
- BFalso
7The fact that a new home being built must meet local building codes is an example of a limit and exclusion
- AVerdadero
- BFalso
8If a project criterion should be optimized if at all possible, it is classified as being constrained
- AVerdadero
- BFalso
9If the project time should be accepted, then the project must be completed on time
- AVerdadero
- BFalso
10During the course of a project, it is possible that the project priorities may change
- AVerdadero
- BFalso
11Profit, time and performance are all basic classifications of project priorities
- AVerdadero
- BFalso
12Integrating a project's work packages within the organization's management structure is known as work breakdown structure
- AVerdadero
- BFalso
13The highest element in the hierarchical breakdown of the WBS is the first major deliverable for the project and the lowest element is a work package
- AVerdadero
- BFalso
14Process breakdown structures are used when the size and the scope of the project do not warrant an elaborate WBS or OBS
- AVerdadero
- BFalso
15Responsibility matrices are used primarily with small and medium-sized projects and have limited use in large projects
- AVerdadero
- BFalso
16A communication plan should include limits on who has access to certain kinds of information
- AVerdadero
- BFalso
17The intersection of work packages and the organizational unit creates a project control point called a cost account
- AVerdadero
- BFalso
18The project charter provides the project manager with written authority to use organizational resources for project activities
- AVerdadero
- BFalso
19For large companies, the organization breakdown structure is used rather than the work breakdown structure
- AVerdadero
- BFalso
20The hierarchical work breakdown structure provides management with information appropriate to each level
- AVerdadero
- BFalso
21The final stage in defining a project is coding the organization breakdown structure or OBS for the information system
- AVerdadero
- BFalso
22Reviews with customer" only refers to projects with external customers who are paying for the project
- AVerdadero
- BFalso
23A typical responsibility matrix will include not only those responsible for a specific task but can also include those who supply support and assistance
- AVerdadero
- BFalso
24Creating a communication plan typically follows a process that begins with a stakeholder analysis.
- AVerdadero
- BFalso
25Responsibility Matrices are useful for assigning and organizing responsibilities.
- AVerdadero
- BFalso
26A Process Breakdown Structure is a replacement for the Work Breakdown Structure for projects with tangible outcomes
- AVerdadero
- BFalso
Información
- Descripción
- Test sobre chapter 4 TF, creado por shamuz ALI el 06/11/2019.
- Autor
- shamuz ALI
- Idioma
- English
- Visitas
- 3
- Valoración
- Aún sin valoraciones Valora este test
Más sobre Project Scope Management