EVM Quiz

venkatram_vasi 10 preguntas

Hacer el test

Este test tiene tiempo límite, así que se abre en el reproductor de siempre.

Preguntas del test (10)

  1. 1BAC=300; PV=200;AC=220;EV=100

    If the future work is assumed to be performed at an efficiency rate that considers both the cost and schedule performance indices what is the EAC (Estimate At Completion).
    1. A660
    2. B500
    3. C745
    4. D1109
  2. 2BAC=300; PV=200;AC=220;EV=100.
    If you future work is assumed that it will be similar to current variance , the VAC (variance At Ccompletion) is.
    1. A-300
    2. B-360
    3. C+360
    4. D+445
  3. 3In a project, Earned Value is half of the Planned Value. Actual cost is double the Planned Value. Comment on the cost and schedule performance of the project.
    1. Aon schedule, on cost
    2. Bahead of schedule, under cost
    3. Cbehind schedule, over cost
    4. Dbehind schedule, on cost
  4. 4You are a Project manager for a road construction project to lay a road of length 20km.
    The budget for 1km road is $4000. half way down 10km road has been laid but the actual cost is $60,000.
    Assuming the current variance will continue in the future what is the Estimate At Completion(EAC)?
    1. A$120,000
    2. B$100,000
    3. C$40,000
    4. D$60,000
  5. 5A project's PV,EV and AC values are shown in this picture. What is the cost and schedule performance of the project?Imagen de la pregunta 5
    1. Abehind schedule, over cost
    2. Bbehind schedule, on cost
    3. Con schedule, on cost
    4. Dahead of schedule, under cost
  6. 6A project's estimated VAC = -$10,000. The BAC of the project = $50,000 and the ETC pending works = $15,000. What is AC till date?
    1. A$25,000
    2. B$45,000
    3. C$40,000
    4. D$35,000
  7. 7In your project, currently there are variances, which are not expected to occur in the future. What is the EAC of your project? BAC = $400,000; AC = $250,000; EV = $200,000; CPI = 1.25
    1. A$320,000
    2. B$750,000
    3. C$450,000
    4. D$600,000
  8. 8CPI = 1.5, SPI = 0.8
    What about the cost and schedule performance of the project?
    1. Aon schedule, on cost
    2. Bbehind schedule, over cost
    3. Cbehind schedule, under cost
    4. Dahead of schedule, on cost
  9. 9SV = 4000 and CV = 0.
    What is the cost and schedule performance of the project?
    1. Aahead of schedule, under cost
    2. Bbehind schedule, on cost
    3. Cahead of schedule, over cost
    4. Dahead of schedule, on cost
  10. 10In a project , PV > EV and AC > EV.
    Which of the following is true?.
    1. ACost performance alone is good
    2. BSchedule performance alone is not good
    3. CBoth cost and schedule performance are good
    4. DBoth cost and schedule performance are not good

Información

Descripción
this is a sample test quiz
Idioma
English
Visitas
695
Etiquetas
testpmpquiz2
Valoración
Aún sin valoraciones
Valora este test
Valora este test

Escríbenos

¿Sobre qué es tu mensaje?

¿Qué te parece el nuevo diseño?

¿Te gusta?